Almonty Announces the Signing of the EPC Contract for the Sangdong Mine Development with POSCO E&C – WORK TO COMMENCE EFFECTIVE JANUARY 2ND, 2018

Almonty Industries Inc. (TSX-V:AII) (“Almonty”) announces that it has signed an EPC (Engineering, Procurement and Construction) Contract with POSCO E&C for the development works at the Sangdong Tungsten and Molybdenum Mine located in the Republic of Korea.

The EPC Contract, entered into on December 28, 2017 with POSCO E&C, one of top tier general contractors in Korea and a subsidiary of the third largest steel mill in the world, is a turnkey based contract for the development and construction of primary facilities for processing tungsten ore mined out of the Sangdong Mine. Under the EPC Contract, POSCO E&C is responsible for not only engineering, civil & architectural, machinery & electrical works of processing plant and auxiliary facilities, but also commissioning of such facilities.

The EPC Contract has a net contract price of KRW40.3 billion (approx. US$37.3 million) and, including the value of primary equipment which will be erected and installed by POSCO E&C, the EPC price reaches KRW54.0 billion (approx. US$50.0 million) which accounts for 65% of the total capital expenditure budgeted for the Sangdong Project. The remaining 35% will be spent for the development of underground transportation galleries and accesses to tungsten veins, mine infrastructure, backfill plant, owner’s cost, and other expenses. The primary facilities of the processing plant will be built for 900,000 to 1.2 million tpa capacity while the initial years of operation targets 640,000 tpa.

The EPC Contract stipulates a construction period of 18 months and commissioning period of 6 months. Following general rules of EPC contracts, cost overrun and project delay will be the responsibility of the EPC Contractor.

Almonty’s Chairman, President and CEO Lewis Black said:

“The signing of the EPC Contract for Sangdong Mine redevelopment will be an important and meaningful step to Almonty for bringing what was historically one of the largest and lowest cost tungsten mines in the world back into production. We are particularly pleased to work with POSCO E&C which is a part of the prestigious POSCO Group. POSCO has been committed to the Sangdong Mine Project by offering a competitive contract price as the Project carries the historical implication of rebuilding its original mother company. POSCO was founded by Korea Tungsten (ex-Sangdong Mine) in 1968. Based on the current EPC and mine development contracts we believe that Sangdong will be in commercial production after ramp up latest Q3 2019. The production at Sangdong Mine will undoubtedly contribute to a much enhanced leadership of Almonty in the global tungsten space.”

About Almonty

The principal business of Almonty is the mining, processing and shipping of tungsten concentrate from its Los Santos Mine in western Spain, its Wolfram Camp Mine in north Queensland, Australia and its Panasqueira mine in Portugal as well as the development of the Sangdong tungsten mine in Gangwon Province, Korea and the Valtreixal tin/tungsten project in north western Spain. The Los Santos Mine was acquired by Almonty in September 2011 and is located approximately 50 kilometres from Salamanca in western Spain and produces tungsten concentrate. The Wolfram Camp Mine was acquired by Almonty in September 2014 and is located approximately 130 kilometres west of Cairns in northern Queensland, Australia and produces tungsten and molybdenum concentrate. The Panasqueira mine, which has been in production since 1896, is located approximately 260 kilometres northeast of Lisbon, Portugal, was acquired in January 2016 and produces tungsten concentrate. The Sangdong mine, which was historically one of the largest tungsten mines in the world and one of the few long-life, high-grade tungsten deposits outside of China, was acquired in September 2015 through the acquisition of a 100% interest in Woulfe Mining Corp. Almonty owns 100% of the Valtreixal tin-tungsten project in northwestern Spain. Further information about Almonty’s activities may be found at www.almonty.com and under Almonty’s profile at www.sedar.com.

Legal Notice

The release, publication or distribution of this announcement in certain jurisdictions may be restricted by law and therefore persons in such jurisdictions into which this announcement is released, published or distributed should inform themselves about and observe such restrictions.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Disclaimer for Forward-Looking Information

When used in this press release, the words “estimate”, “project”, “belief”, “anticipate”, “intend”, “expect”, “plan”, “predict”, “may” or “should” and the negative of these words or such variations thereon or comparable terminology are intended to identify forward-looking statements and information. This press release contains forward-looking statements. These statements and information are based on management’s beliefs, estimates and opinions on the date that statements are made and reflect Almonty’s current expectations.

Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of Almonty to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: any specific risks relating to fluctuations in the price of ammonium para tungstate from which the sale price of Almonty’s tungsten concentrate is derived, actual results of mining and exploration activities, environmental, economic and political risks of the jurisdictions in which Almonty’s operations are located and changes in project parameters as plans continue to be refined, forecasts and assessments relating to Almonty’s business, credit and liquidity risks, hedging risk, competition in the mining industry, risks related to the market price of Almonty’s shares, the ability of Almonty to retain key management employees or procure the services of skilled and experienced personnel, risks related to claims and legal proceedings against Almonty and any of its operating mines, risks relating to unknown defects and impairments, risks related to the adequacy of internal control over financial reporting, risks related to governmental regulations, including environmental regulations, risks related to international operations of Almonty, risks relating to exploration, development and operations at Almonty’s tungsten mines, the ability of Almonty to obtain and maintain necessary permits, the ability of Almonty to comply with applicable laws, regulations and permitting requirements, lack of suitable infrastructure and employees to support Almonty’s mining operations, uncertainty in the accuracy of mineral reserves and mineral resources estimates, production estimates from Almonty’s mining operations, inability to replace and expand mineral reserves, uncertainties related to title and indigenous rights with respect to mineral properties owned directly or indirectly by Almonty, the ability of Almonty to obtain adequate financing, the ability of Almonty to complete permitting, construction, development and expansion, challenges related to global financial conditions, risks related to future sales or issuance of equity securities, differences in the interpretation or application of tax laws and regulations or accounting policies and rules and acceptance of the TSX-V of the listing of Almonty shares on the TSX-V.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to, no material adverse change in the market price of ammonium para tungstate, the continuing ability to fund or obtain funding for outstanding commitments, expectations regarding the resolution of legal and tax matters, no negative change to applicable laws, the ability to secure local contractors, employees and assistance as and when required and on reasonable terms, and such other assumptions and factors as are set out herein. Although Almonty has attempted to identify important factors that could cause actual results, level of activity, performance or achievements to differ materially from those contained in forward-looking statements, there may be other factors that cause results, level of activity, performance or achievements not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate and even if events or results described in the forward-looking statements are realized or substantially realized, there can be no assurance that they will have the expected consequences to, or effects on, Almonty. Accordingly, readers should not place undue reliance on forward-looking statements and are cautioned that actual outcomes may vary.

Investors are cautioned against attributing undue certainty to forward-looking statements. Almonty cautions that the foregoing list of material factors is not exhaustive. When relying on Almonty’s forward-looking statements and information to make decisions, investors and others should carefully consider the foregoing factors and other uncertainties and potential events.

Almonty has also assumed that material factors will not cause any forward-looking statements and information to differ materially from actual results or events. However, the list of these factors is not exhaustive and is subject to change and there can be no assurance that such assumptions will reflect the actual outcome of such items or factors.

THE FORWARD-LOOKING INFORMATION CONTAINED IN THIS PRESS RELEASE REPRESENTS THE EXPECTATIONS OF ALMONTY AS OF THE DATE OF THIS PRESS RELEASE AND, ACCORDINGLY, IS SUBJECT TO CHANGE AFTER SUCH DATE. READERS SHOULD NOT PLACE UNDUE IMPORTANCE ON FORWARD-LOOKING INFORMATION AND SHOULD NOT RELY UPON THIS INFORMATION AS OF ANY OTHER DATE. WHILE ALMONTY MAY ELECT TO, IT DOES NOT UNDERTAKE TO UPDATE THIS INFORMATION AT ANY PARTICULAR TIME EXCEPT AS REQUIRED IN ACCORDANCE WITH APPLICABLE LAWS.

EN
28/12/2017

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Almonty Industries

Peter Thilo Hasler
  • Peter Thilo Hasler

H1/2024 above estimates – increasing price target to CAD 2.31

On the backdrop of higher production and increased tungsten recovery rates at the Panasqueira Mine, H1/2024 profits from mining operations were significantly above our estimates and last year’s level. With the world’s longest producing mine (Panasqueira) and the world’s largest tungsten deposit (Sangdong) under construction, Almonty is – in our view – very close to becoming one the most important global suppliers of conflict-free tungsten material. We continue to value the shares of Almonty Indu...

Peter Thilo Hasler
  • Peter Thilo Hasler

Defence spendings support tungsten demand

As geopolitical tensions continue to rise, the demand for advanced defence technologies is likely to increase, driving the demand for tungsten armour which is less regulated than depleted uranium and also considered “exportable” by the US government. With the world’s longest producing mine (Panasqueira) and the world’s largest tungsten deposit (Sangdong) under construction, Almonty is – in our view – very close to becoming the most important global supplier of conflict-free tungsten material. We...

Peter Thilo Hasler
  • Peter Thilo Hasler

H1/2023 in-line with estimates – Los Santos about to reopen

With CAD 12.6mn and CAD -3.8mn, both sales (H1/2022 CAD 13.3mn) and pre-tax loss (H1/2022: CAD -3.9mn), respectively, were in-line with our expectations in H1/2023. 100% of revenues were generated by the Portuguese Panasqueira mine, where ore mined and processed declined by 20.9% in H1/2023. Free cash flow for the first six months was CAD -10.3mn (H1/2022: CAD -5.8mn) which was financed by the issuance of shares (CAD 5.0mn) and long-term debt (CAD 4.8mn, net of repayments). We continue to value...

Peter Thilo Hasler
  • Peter Thilo Hasler

Reopening Los Santos mine utilizing proprietary technology

We continue to value the shares of Almonty Industries using a two-stage Discounted Cashflow entity model of Almonty’s producing assets (Sangdong, Los Santos, and Panasqueira) to which we have added the discounted value of the development project (Valtreixal). Given a lower number of shares outstanding and lower capex from re-operationalising the Spanish Los Santos mine than previously anticipated, we adjust our target price to CAD 1.69 from CAD 1.59 per share. With an expected share price perfor...

Peter Thilo Hasler
  • Peter Thilo Hasler

Sangdong on track for commissioning in 2024e

We value Almonty Industries using a two-stage Discounted Cashflow entity model of Almonty’s producing assets (Sangdong, Los Santos, and Panasqueira) to which we have added the discounted value of the development project (Valtreixal). Reflecting the higher number of shares outstanding, our fully diluted price target slightly declines to CAD 1.59 from CAD 1.66 per share. Given a 144.6% upside from the current share price of CAD 0.65 we are reiterating our Buy rating for the shares of Almonty Indus...