GRAND BAIE, Mauritius, March 01, 2019 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM: TSXV, “Alphamin”, or the “Company”) is pleased to announce an update to the development status of its flagship tin project in the DRC.

The processing plant front-end crushing circuit commissioning has been completed and has run at nameplate capacity of sixty tonnes per hour. To date, some six thousand, five hundred tons of ore has been crushed and stockpiled for feeding into the gravity separation circuit.

Cold commissioning on the gravity concentration section has also commenced and is progressing well.

In connection with the previously announced change of mining method to a cut and fill method, a detailed mine schedule for 2019 and 2020 has been received. Production of ore from the cut and fill stoping operation has now commenced. A life of mine schedule is expected during Q2 2019 following which the Company plans to update its NI 43-101 and announce updated project economics. Initial analysis indicates the unit costs per ton will be higher in 2019 and 2020 than had been anticipated in the Company’s most recent feasibility study.

Full commissioning and ramp up is scheduled to occur during Q2 2019. Production at planned through put  is planned to commence in Q3, 2019.

The Company has reviewed the working capital requirements to achieve planned production volumes . The current cashflow projections indicate a likely short term working capital shortfall. Factors impacting the projected working capital shortfall include a delayed response to a request to partially export concentrates by airfreight, requiring the company to truck all export material, which has impacted delivery times and related revenue receipts; a delay in VAT refunds and the delayed manufacture and delivery of certain components to finalise plant commisioning. In addition to this, the change in the mining method has resulted in a slower ramp up of material to the ROM stockpile.

The Company estimates that up to $9m may be required to bridge this expected working capital deficit and enables the Company to acquire certain sustaining capital and critical spares.

Management considers it prudent to seek a working capital facility of up to US$12m, which exceeds the projected shortfall of $9m but provides a buffer for any additional unforseen events or challenges. The Company is in discussion with its lenders to provide this facility.

FOR MORE INFORMATION, PLEASE CONTACT:

Boris Kamstra                                                   

Chief Executive Officer                                      

Alphamin Resources Corp.                                              

Tel: +230 269 4166

E-mail:

Grand Baie, Mauritius

CAUTION REGARDING FORWARD LOOKING STATEMENTS

Information in this news release that is not a statement of historical fact constitutes forward-looking information. Forward-looking statements contained herein include, without limitation, statements relating to the terms and intended completion of the Private Placement, the anticipated use of funds from the Private Placement, the anticipated additional debt drawdown, the participation of the IDC and other stakeholders, costs of production, success of mining operations, the ranking of the project in terms of cash cost and production, economic return estimates, social, community and environmental impacts, and continued positive discussions and relationships with local communities and stakeholders. Forward-looking statements are based on assumptions management believes to be reasonable at the time such statements are made. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Although Alphamin has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. Factors that may cause actual results to differ materially from expected results described in forward-looking statements include, but are not limited to: Alphamin’s ability to secure sufficient financing to advance and complete the Project, uncertainties associated with Alphamin’s resource and reserve estimates, uncertainties regarding global supply and demand for tin and market and sales prices, uncertainties associated with securing off-take agreements and customer contracts, uncertainties with respect to social, community and environmental impacts, adverse political events, uncertainties with respect to optimization opportunities for the Project, as well as those risk factors set out in the Company’s Management Discussion and Analysis and other disclosure documents available under the Company’s profile at . Forward-looking statements contained herein are made as of the date of this news release and Alphamin disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws.

Neither the TSX Venture Exchange nor its regulation services provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

EN
01/03/2019

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Alphamin Resources Corp.

 PRESS RELEASE

ALPHAMIN ANNOUNCES RECORD FY2025 TIN PRODUCTION /FY2026 PRODUCTION GUI...

ALPHAMIN ANNOUNCES RECORD FY2025 TIN PRODUCTION /FY2026 PRODUCTION GUIDANCE/ EXPLORATION UPDATE/ SENIOR MANAGEMENT CHANGES Grand Baie, MAURITIUS, Jan. 19, 2026 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX)( “Alphamin” or the “Company”) is pleased to provide the following update for the year and quarter ended 31 December 2025:      FY2025 tin production of 18,576 tonnes, up 7% from the prior year     Q4 tin production of 5,008 tonnes (Q3: 5,190 tonnes)     FY2025 EBITDA2,3 guidance of US$341m, an estimated increase of 25% from actual FY2024 at a tin price of US$34...

 PRESS RELEASE

ALPHAMIN ANNOUNCES RESIGNATION OF DIRECTOR

ALPHAMIN ANNOUNCES RESIGNATION OF DIRECTOR Grand Baie, MAURITIUS, Jan. 05, 2026 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX) (the “Company” or “Alphamin”) announced today that Mr. Paul Baloyi has resigned as a director of the Company effective January 31, 2026. Mr. Baloyi has served on the board since April 2017 as an appointee of the Industrial Development Corporation of South Africa Ltd. (IDC) and the board of directors wishes to thank him for his contributions to Alphamin during his tenure. FOR MORE INFORMATION, PLEASE CONTACT: Charles Needham              ...

 PRESS RELEASE

ALPHAMIN REPORTS FATALITY AT MPAMA SOUTH UNDERGROUND MINE

ALPHAMIN REPORTS FATALITY AT MPAMA SOUTH UNDERGROUND MINE Grand Baie, Mauritius                               , Dec. 25, 2025 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX) (the “Company” or “Alphamin”) deeply regrets to report that an employee of operating subsidiary Alphamin Bisie Mining S.A. (“ABM”) was fatally injured at its Mpama South underground mine in east-central Democratic Republic of the Congo.On 24 December at approximately 18:00 local time, following the scheduled evacuation of the underground areas for the planned night shift blast, an incident occurr...

 PRESS RELEASE

ALPHAMIN ANNOUNCES CAD $0.04 PER SHARE SECOND INTERIM FY2025 DIVIDEND ...

ALPHAMIN ANNOUNCES CAD $0.04 PER SHARE SECOND INTERIM FY2025 DIVIDEND / FILES Q3 2025 FINANCIAL STATEMENTS AND MD&A Grand Baie, MAURITIUS, Nov. 03, 2025 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX)( “Alphamin” or the “Company”) announced today the declaration of a second interim FY2025 dividend and the filing of its unaudited condensed consolidated financial statements and accompanying Management’s Discussion and Analysis (“MD&A”) for the three and nine months ended 30 September 2025 on SEDAR+ at . Second Interim FY2025 Dividend Declared The Board has declar...

 PRESS RELEASE

ALPHAMIN PROVIDES Q3 2025 OPERATIONAL UPDATE

ALPHAMIN PROVIDES Q3 2025 OPERATIONAL UPDATE Grand Baie, MAURITIUS, Oct. 07, 2025 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX)( “Alphamin” or the “Company”) is pleased to provide an operational update as follows: Q3 2025 contained tin production of 5,190 tonnes, up 26% from the previous quarter (Q2 2025: 4,106 tonnes (period from phased restart on April 15 to June 30))FY2025 contained tin production guidance increased to between 18,000 and 18,500 tonnes (17,500 tonnes previously)Contained tin sales of 5,143 tonnes for the quarter, up 12% from the prior periodQ3 2...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch