Velcan Holdings: Extension of Time for the Land Acquisition Procedure of the Indian Hydropower Projects

Velcan Holdings: Extension of Time for the Land Acquisition Procedure of the Indian Hydropower Projects



PRESS RELEASE

New Delhi, 8th April 2019

VELCAN HOLDINGS: EXTENSION OF TIME FOR THE LAND ACQUISITION PROCEDURE

OF THE INDIAN HYDROPOWER PROJECTS

Under the land acquisition regulations applicable to the Heo-Tato1 hydropower tandem project (426 MW) in India, the “Section 11 preliminary notification” was due by 27th March 2019. Such notification is the act by which the State Government decides it is appropriate to acquire the concerned land for public purpose, based on the completion of the first phase of the acquisition procedure.

This first phase of the procedure involved a social impact assessment, a social impact management plan, public hearings in all 9 concerned villages, the recommendation of an expert group, the establishment of a list of land owners, the obtaining of the consent of at least 80% of the individual land owners and the obtaining of the consent of all the concerned village councils.

The above activities and steps were successfully completed between June 2016 and March 2019. However due to the current preparation of the national and local elections, scheduled on 11th April 2019, the “code of conduct” has entered into force, hence preventing the State Government to take any decision outside the day to day current affairs. Therefore, in compliance with the possibility offered by applicable regulations, the State Government has decided a time extension of 6 months, until 26th September 2019, to issue the Section Notification.

Under the concession agreement and applicable regulations, the land is to be acquired by the State Government itself, and then leased to the project developer. The completion of this phase, especially obtaining the land owners consent (subject to Section 11 Notification), is a major step in the land acquisition procedure, although it does yet not resolve the land registry disputes. At a later stage, the settlement of these disputes will be necessary to determine the sharing of financial compensations between land owners.

If and when the Section 11 notification is issued, the State Government will have to conduct another set of surveys and complex procedural steps such as notably a detailed and individual census of affected families, the marking of land boundaries, the hearing of individual objections, the preparation and publication of Rehabilitation & Resettlement plans (Section 19), the public hearings on such plans, the issuance of financial awards (Sections 23 and 31) and the physical possession of the Land (Section 38).

*          *          *

Investor Relations Contact        

About Velcan:

Velcan Holdings is a Luxemburg headquartered investment holding company founded in 2005, operating as an independent power producer in emerging countries and managing a global portfolio of financial assets.

The company owns and operates a 15MW hydro power plant in Brazil that it developed and built in 2009. The company is developing a cascade of hydropower concessions located in India and totalling 571 MW.

Hydropower concessions provide long periods of cash generation but their development outcome is uncertain and many years are needed to bring these projects to maturity in emerging countries: it involves field studies in remote places, obtaining the necessary authorizations and permits, and land acquisition in political and regulatory environments that can be unstable or heavily hampering. Meanwhile Velcan Holdings actively manages its treasury, investing in listed and unlisted financial instruments.

Velcan Holdings’ headquarters are in Luxemburg, with administrative and financial offices in Singapore and Mauritius. The team dedicated to the development of the Indian hydropower cascade is based in New Delhi and at the project site (Arunachal Pradesh). The team dedicated to the Rodeio Bonito plant is based in Sao Paulo and Chapeco (Santa Catarina State).

The company was launched more than 10 years ago by its reference shareholder Luxembourg Hydro Power SA, owned by Velcan Holdings’ management team.

Velcan Holdings is listed on the Paris Euronext Growth Stock Market (Euronext Growth/Ticker ALVEL/ISIN FR0010245803).

Velcan Holdings never performed any Public Offer as understood under Directive 2003/71/CE of the European Parliament and Council.

 

Disclaimer

This press release contains prospective information about the potential of the projects in progress and/or of the projects of which the development has begun. This information constitutes objectives attached to projects and shall not be construed as direct or indirect net income forecast of the concerned year. Reader’s attention is also drawn on the fact that the performance of these objectives depends on future circumstances and that it could be affected and/or delayed by risks, known or unknown, uncertainties, and various factors of any nature, notably related to economic, commercial or regulatory conjuncture, which occurrence could be likely to have a negative impact on future activity and performances of the Group.

This announcement does not constitute a public offering (“offre au public”) nor an invitation to the public or to any qualified investor in connection with any offering. This announcement is not an offer of securities in the United States of America or in any other jurisdiction/country.

Attachment

EN
08/04/2019

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Velcan

 PRESS RELEASE

Velcan Holdings: First Half Results

Velcan Holdings: First Half Results PRESS RELEASE VELCAN HOLDINGS: HALF YEARLY RESULTS (CONSOLIDATED AND UNAUDITED)FINANCIAL RESULT AFFECTED BY FOREX VARIATION LEADING TO A SHARP DECREASE OF THE NET PROFIT  30.06.202530.06.2024Var %Turnover Half Year (Million Euros)1.01.0+3%Net Result Half Year (Million Euros)0.64.0-85% 30.06.202531.12.2024 Cash and Financial instruments (Million Euros)132135-3%Consolidated Equity (Million Euros)135135+0% Brief comments on 2025 first half H1 2025 was marked by heightened volatility across trade, macroeconomic and geopolitical fronts, notably due to rene...

 PRESS RELEASE

Velcan Holdings: Share buyback program

Velcan Holdings: Share buyback program Luxembourg, 16 July 2025 SHARES REPURCHASE PROGRAMMEAuthorized by the shareholders’ meeting held on 29th June 2021Implemented upon the decision of the Board of Directors dated 8 January 2025, DISCLOSURE OF PURCHASES EFFECTED FROM 7 JULY 2025 TO 11 JULY 2025 Market: Euro MTF, LuxembourgType of shares: ordinary shares ISIN FR0010245803 Trading date Number of shares purchasedPurchase price per share Total amount of purchases PurposeMarket10/07/2025750€ 17.93€ 13 449.98Cancellation or free shares coverageEuro MTF Luxembourg10/07/202540 000€ 18.00€ 720...

 PRESS RELEASE

Velcan Holdings: Convening Notice of the Ordinary Annual General Meeti...

Velcan Holdings: Convening Notice of the Ordinary Annual General Meeting to be Held on June 25, 2025 PRESS RELEASE Luxembourg, May 23, 2025 VELCAN HOLDINGS: CONVENING NOTICE OF THE ORDINARY ANNUAL GENERAL MEETING TO BE HELD ON JUNE 25, 2025 VELCAN HOLDINGS announces to the shareholders of the Company that the Ordinary Annual General Meeting will be held on Wednesday, June 25, 2025, at 11 a.m, in the offices of the law firm Tabery & Wauthier, 10 rue Pierre d’Aspelt, L‐1142 Luxembourg, in order to vote mainly on the approval of the 2024 condensed non-audited consolidated financial state...

 PRESS RELEASE

Velcan Holdings : Convocation de l’Assemblée Générale Ordinaire annuel...

Velcan Holdings : Convocation de l’Assemblée Générale Ordinaire annuelle le 25 juin 2025 COMMUNIQUE DE PRESSE Luxembourg, le 23 mai 2025 VELCAN HOLDINGS : CONVOCATION DE L’ASSEMBLEE GENERALE ORDINAIRE ANNUELLE LE 25 JUIN 2025 VELCAN HOLDINGS annonce que les actionnaires de la Société sont convoqués en Assemblée Générale Ordinaire Annuelle le mercredi 25 juin 2025 à 11 heures, dans les locaux de l’Etude Tabery & Wauthier, 10 rue Pierre d’Aspelt, L‐1142 Luxembourg, à l’effet de délibérer principalement sur l’approbation des comptes consolidés condensés non audités de l’exercice 2024 et ...

 PRESS RELEASE

Velcan Holdings: Annual Results 2024

Velcan Holdings: Annual Results 2024 PRESS RELEASE Luxembourg, 29th April 2025 VELCAN HOLDINGS: ANNUAL RESULTS 2024 STRONG FINANCIAL RESULTS, STABLE TURNOVER OF THE RODEIO BONITO PLANT, NON-AUDITED KEY CONSOLIDATED FIGURES2024 2023 Var %Revenues (EUR m)3.02.9+2%EBITDA (EUR m)-5.61.8NA%Net Income (EUR m)11.20.52005%Cash and Financial assets and liabilities135125+8%Shareholders’ Equity (EUR m)135128+5% The financial portfolio value of the Group has experienced a significant growth mainly driven by the positions held in precious metals, Japanese stocks and capitalizing on key investments...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch