AMG1L Amber Grid AB

Decisions adopted in the Extraordinary General Meeting of Shareholders of AB Amber Grid

Decisions adopted in the Extraordinary General Meeting of Shareholders of AB Amber Grid

Decisions adopted in the Extraordinary General Meeting of Shareholders of AB Amber Grid

AB Amber Grid, legal entity code: 303090867. Address: Laisvės ave. 10, LT-04215 Vilnius, Lithuania.

The following decisions were adopted in the Extraordinary General Meeting of Shareholders of AB Amber Grid on 10 September 2025:

 1) On conclusion of contract for the design services and construction works for the modernization of the Jauniūnai Gas Compressor Station

1. Approve the conclusion of the contract for the design services and construction works for the installation and reconstruction of the electric gas compressor at the Jauniūnai Gas Compressor Station, and to approve the following essential terms of the contract (hereinafter – the Contract):

1.1. Subject matter (object) of the Contract – Design and construction works for the installation and reconstruction of an electric gas compressor at the Jauniūnai Gas Compressor Station

1.2. Parties of the Contract:

• AB Amber Grid, company code 303090687, address Laisvės Ave. 10, LT-04215 Vilnius, Lithuania (hereinafter – the Client), and

• UAB MT Group, company code 302203568, address Dariaus ir Girėno St. 34F, LT-02188 Vilnius, Lithuania (hereinafter – the Contractor).

1.3. Contract price – EUR 30,924,000.00 excluding VAT and EUR 6,494,040.00 VAT. Total including VAT – EUR 37,418,040.00.

1.4. Payment procedure:

- 60% (sixty percent) of the compressor price (including VAT) as indicated in the Contractor’s proposal, to be paid within 5 (five) business days from the date of receipt of the invoice, once the Contractor has coordinated the factory drawings of the compressor with the Client, submitted the order to the compressor manufacturer, and received confirmation from the manufacturer (which the Contractor must provide to the Client) that the order has been accepted and the compressor will be manufactured;

- 30% (thirty percent) of the compressor price (including VAT) as indicated in the Contractor’s proposal, to be paid within 5 (five) business days from the date of receipt of the invoice, once the Contractor delivers the compressor to the construction site and the Client inspects and confirms its suitability (upon signing the initial inspection report by

both parties), and the Contractor installs the compressor at the location specified in the Project;

- 10% (ten percent) of the compressor price (including VAT) as indicated in the Contractor’s proposal, to be paid within 5 (five) business days from the date of receipt of the invoice, upon receipt of the Construction Completion Certificate;

- for works performed during the reporting period (month), based on the signed handover-acceptance act(s) and the corresponding VAT invoice, payment shall be made within 30 (thirty) days.

1.5. Contract price calculation method – fixed price with review.

1.6. Conditions for changing the Contract price:

- in the event of a change in the VAT rate;

- due to changes in the price level (indexation).

- the Engineering Networks Construction Price Index shall be applied for contract price review. The price adjustment may be made no earlier than 3 months after the Contract enters into force and, in any case, no earlier than 6 months after the final proposal submission date, provided the index exceeds 0.05;

- due to changes in the scope (quantities) of the Works (increase or decrease), in accordance with the procedure and conditions established by the Law on Procurement in the Fields of Water Management, Energy, Transport, or Postal Services of the Republic of Lithuania. The value of the additional scope (quantities)  cannot exceed 15 per cent of the initial Contract price;

- the remaining part of the compressor price, after deducting the advance payment (if already paid), may be recalculated based on the price index change. Recalculation applies only to construction works and the remaining compressor price. Other works, such as design or cadastral data determination, are not subject to recalculation. The recalculated price becomes effective and is applied only to works and materials (excluding the compressor) performed or delivered after the date of signing the recalculation agreement.

1.7. Deadline for fulfilling obligations – the final deadline for completing the works is no later than 42 (forty-two) months from the effective date of the Contract.

Final Deadline for Completion of the Works may be changed in accordance with the procedure and conditions set out in the Contract in the following circumstances:

1.7.1. Prolonged (lasting more than 14 (fourteen) consecutive days) adverse weather conditions at the work site/location that make it impossible to carry out the works – such as heavy rainfall, flooding, dense fog, squalls, heavy snowfall, blizzards, etc. This applies only to works whose quality and execution depend on weather conditions;

1.7.2. Actions or inaction by the Client that hinder the proper and timely fulfilment of the Contractor’s obligations under the Contract, including delays in appointing specialists responsible for fulfilling the obligations set out in the Contract, failure to hand over the construction site to the Contractor, failure to issue approvals or other necessary consents for the execution of the works (for which the Client is responsible), or failure to fulfil other contractual obligations;

1.7.3. Changes or intended changes to the design solutions of the project on the basis of which the procurement was carried out;

1.7.4. Changes or intended changes to the scope of the works;

1.7.5. Failure by any state or municipal institution, agency, organization, or other entity to perform its statutory functions within the prescribed (or reasonable, if not prescribed) time frame;

1.7.6. Circumstances that arise during the execution of the works that could not have been reasonably foreseen at the time of signing the Contract, such as: actions or inaction of third parties; changes in legal regulations related to the execution of the Contract; delays or refusal by landowners (on whose land the works are to be carried out under the Project and/or this Contract) to establish servitudes and/or special land use conditions, or to grant other rights to carry out the works on their land; and other third-party-dependent circumstances that the Contractor cannot eliminate despite taking reasonable and appropriate measures;

1.7.7. Delays in procurement procedures that make it impossible or excessively difficult to start and/or complete the works within the timeframe set in the Contract (e.g., the Contract was signed later than indicated in the Client’s notice of contract award; based on the data provided during the procurement process, the Contractor reasonably planned to start the works earlier, etc.).

1.8. Performance Guarantee:

- Bank guarantee;

- Guarantee amount – 10% of the Contract price excluding VAT.

1.9. Additional condition for the Contract to enter into force:

- approval/endorsement from the National Energy Regulatory Council has been obtained for the implementation of the project “Optimization of the capacity of the Jauniūnai Gas Compressor Station.” If National Energy Regulatory Council does not approve or endorse the implementation of the project, the Contract will not enter into force, and the works will not be procured or carried out.

2. To authorize the Company's CEO (with the right to delegate):

2.1. To conclude the Contract under the essential terms specified in clause 1.1;

2.2. Without a separate decision of the Board:

2.2.1. To reduce the Contract price without any limitations in cases and under the procedure provided for in the Contract and/or legal acts, provided that no other Contract terms, which were approved by the Board, are changed;

2.2.2. In cases and procedures provided for in the contract and/or legal acts, the Contract Price may be increased by no more than EUR 2,000,000, in accordance with the price recalculation procedure specified in this Board decision, provided that no other Contract terms, which were approved by the Board, are changed.

3. To agree on other (non-essential) terms of the Contract when entering into the relevant transactions and other agreements or documents on behalf of the Company.

More information:

Dovilė Binkevičienė, Communication Project Manager,

Ph. , e-mail



EN
10/09/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Amber Grid AB

 PRESS RELEASE

Agreement Signed on Gas Transit to Kaliningrad

Agreement Signed on Gas Transit to Kaliningrad Lithuania’s gas transmission system operator Amber Grid has signed a natural gas transportation agreement through the Republic of Lithuania to the Kaliningrad region. The gas transit is organized based on international agreements and EU regulations. The new transit service conditions are set for five years – until December 31, 2030. Service prices are determined by the National Energy Regulatory Council, with the permissible revenue level for 2026 set at about €30 million. During the contract period, the possibility is provided to use a capaci...

 PRESS RELEASE

Pasirašyta sutartis dėl dujų tranzito į Karaliaučių

Pasirašyta sutartis dėl dujų tranzito į Karaliaučių Lietuvos dujų perdavimo sistemos operatorius „Amber Grid“ pasirašė gamtinių dujų transportavimo sutartį per Lietuvos Respubliką į Karaliaučiaus sritį. Dujų tranzitas organizuojamas tarptautinių sutarčių, ES reguliavimo ir Lietuvos respublikos gamtinių dujų įstatymo pagrindu. Naujos tranzito paslaugos sąlygos nustatytos penkeriems metams – iki 2030 gruodžio 31 d. Paslaugų kainas nustato Valstybinė energetikos reguliavimo taryba, 2026 metams nustatytas leistinas pajamų lygmuo sudaro apie 30 mln. eurų. Priedas ...

 PRESS RELEASE

AB Amber Grid has entered into a tripartite loan transfer agreement an...

AB Amber Grid has entered into a tripartite loan transfer agreement and a new internal loan agreement with UAB EPSO-G. 22nd December 2025   AB Amber Grid announces that it has entered into a tripartite debt transfer agreement with UAB EPSO-G and the Nordic Investment Bank (NIB). Under the terms of the agreement, UAB EPSO-G assumes a loan of EUR 10.9 million that was granted under the loan agreement dated August 19, 2015, between AB Amber Grid and NIB, intended to finance the Klaipėda–Kiemėnai pipeline capacity expansion project (construction of the Klaipėda–Kuršėnai pipeline). The original...

 PRESS RELEASE

AB „Amber Grid“ sudarė trišalį skolos perkėlimo susitarimą ir naują vi...

AB „Amber Grid“ sudarė trišalį skolos perkėlimo susitarimą ir naują vidinę paskolos sutartį su UAB „EPSO-G“ 2025 m. gruodžio 22 d.   AB „Amber Grid“ informuoja, kad sudarė trišalį skolos perkėlimo susitarimą su UAB „EPSO-G“ ir Šiaurės investicijų banku (Nordic Investment Bank, NIB). Pagal susitarimą UAB „EPSO-G“ perima 10,9 mln. Eur paskolą, suteiktą pagal 2015 m. rugpjūčio 19 d. sudarytą paskolos sutartį tarp AB „Amber Grid“ ir NIB, skirtą dujotiekio Klaipėda-Kiemėnai pajėgumų padidinimo projektui (dujotiekio Klaipėda-Kuršėnai statybai)  finansuoti. Pirminės sutarties paskolos grąžinimo t...

 PRESS RELEASE

Notice on Convening of the Extrardinary General Meeting of Shareholder...

Notice on Convening of the Extrardinary General Meeting of Shareholders of AB Amber Grid Under the initiative and decision of the Board of AB Amber Grid (company code 303090867, registered office address: Laisvės ave. 10, LT-04215 Vilnius, Lithuania) (further on Amber Grid, the Company), the Extraordinary General Meeting of Shareholders of Amber Grid is convened at the Company’s registered office (address: Laisvės ave. 10, LT-04215 Vilnius, Lithuania) on 9 January 2026 at 10:00 a.m.  The agenda of the Extraordinary General Meeting of Shareholders of Amber Grid: 1) On the selection of an a...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch