Atico Reports First Quarter 2018 Production Results and Provides Update on Union Negotiations

Atico Reports First Quarter 2018 Production Results and Provides Update on Union Negotiations

VANCOUVER, British Columbia, April 15, 2019 (GLOBE NEWSWIRE) -- Atico Mining Corporation (the “Company” or “Atico”) (TSX.V: ATY | OTC: ATCMF) announces its operating results for the three months ended March 31, 2019 from its El Roble mine. Production for the quarter totaled 2.36 million pounds of copper and 1,552 ounces of gold in concentrates, a decrease of -57% and -45% for copper and gold, respectively, over the same period in 2018.

“The strike at the El Roble mine has had a significant impact on the Company’s ability to meet operational objectives in the first quarter. The mine has not operated for over fifty days during this period and this is directly reflected in this quarter’s results,” said Fernando E. Ganoza, CEO. “Once the operation resumes and for the remainder of the year, the Company will make its best effort to minimize the impact of lost production.”

First Quarter Operational Highlights

  • Production of 2.36 million pounds of copper contained in concentrates; a decrease of 57% over Q1 2018.
  • Production of 1,552 ounces of gold contained in concentrates; a decrease of 45% over Q1 2018.
  • Average processed tonnes per day of 885, an increase of 9% over Q1 2018.
  • Copper head grade of 3.29%, a decrease of 13% over Q1 2018.
  • Gold head grade of 2.24 grams per tonne; an increase of 10% over Q1 2018.
  • Copper and gold recovery of 91.1% and 60.6%; a decrease of 3% for copper and 5% for gold respectively over Q1 2018.

Union Negotiations

During the quarter the Company entered into its biennial union negotiations with the miners as reported in the news release published on . These negotiations led to a strike which has stopped almost all Company’s activity at the mine for the remainder of the quarter. Friday April 12, 2019 marked the sixtieth day of the strike after which, dictated by Colombian law, a legal mechanism to end the strike with an arbitrage process began. According to Colombian Labor Code the process of assembling the arbitrator’s council is anticipated for the 8th working day proceeding April 12, 2019, after which operations should resume within 3 working days.

Despite 20 meetings and 8 complete proposals by the Company to solve the negotiations amicably, the strike has lasted longer than anticipated due to unacceptable terms requested by the union. The arbitration process contemplated in the Colombian Law will now be the solution to the labor dispute, three arbitrators will decide in the coming months the labor conditions for the unionized workers. 

The Company believes this is a sustainable solution for all stakeholders and sets an important precedent for future negotiations.

First Quarter Operational Details

 Q1 2019

Total
Q1 2018

Total
% Change
Production (Contained in Concentrates)   
Copper (000s pounds)2,3625,476-57%
Gold (ounces)1,5522,825-45%
Mine   
Tonnes of ore mined34,79667,022-48%
Mill   
Tonnes processed35,58169,499-49%
Tonnes processed per day8858129%
Copper grade (%)3.293.80-13%
Gold grade (g/t)2.242.0310%
Recoveries   
Copper (%)91.694.0-3%
Gold (%)60.662.8-4%
Concentrates   
Copper and Gold Concentrates (dmt)4,92111,474-57%
    
Payable copper produced (000s lbs)2,2445,202-57%

Note: Metal production figures are subject to adjustments based on final settlement.

2019 Operational Guidance

The 2019 projections stated below and in January 29, 2019 News Release will be negatively affected by the ongoing strike at the El Roble mine and will be adjusted by the Company once operations resume.

The Company set the following objectives for 2019 at the El Roble mine:

  • Process between 280,000 and 290,000 tonnes.
  • Maintain copper recovery above 93% and 62% for gold.
  • Maintain an average copper head grade between 3.4% and 3.6%
  • Maintain an average gold head grade between 1.8 g/t and 2.0 g/t
  • Increase production between 43,000 and 45,000 dry tonnes of concentrate.
  • Maintain production between 9,000 and 9,500 tonnes of copper.
  • Maintain production between 10,200 and 10,700 ounces of gold.

  • Mantain the mill mechanical availability to 95% with 345 days worked.

  • Continue increasing the safety and environmental standards.

El Roble Mine

The The El Roble mine is a high grade, underground copper and gold mine with nominal processing plant capacity of 850 tonnes per day, located in the Department of Choco in Colombia. Its commercial product is a copper-gold concentrate. Since obtaining control of the mine on November 22, 2013, Atico has upgraded the operation from a historical nominal capacity of 400 tonnes per day.

El Roble has Proven and Probable reserves of 1.47 million tonnes grading 3.40% copper and 1.88 g/t gold, at a cut-off grade of 1.93% copper equivalent as of June 30th, 2018. Mineralization is open at depth and along strike and the Company plans to further test the limits of the deposit.

On the larger land package, the Company has identified a prospective stratigraphic contact between volcanic rocks and black and grey pelagic sediments and cherts that has been traced by Atico geologists for ten kilometers. This contact has been determined to be an important control on VMS mineralization on which Atico has identified numerous target areas prospective for VMS type mineralization occurrence, which is the focus of the current surface drill program at El Roble.

Qualified Person

Mr. Thomas Kelly (SME Registered Member 1696580), advisor to the Company and a qualified person under National Instrument 43-101 standards, is responsible for ensuring that the technical information contained in this news release is an accurate summary of the original reports and data provided to or developed by Atico.

About Atico Mining Corporation

Atico is a growth-oriented Company, focused on exploring, developing and mining copper and gold projects in Latin America. The Company operates the El Roble mine and is pursuing additional acquisition opportunities. For more information, please visit . 

ON BEHALF OF THE BOARD

Fernando E. Ganoza

CEO

Atico Mining Corporation

Trading symbols: TSX.V: ATY | OTC: ATCMF

Investor Relations

Igor Dutina

Tel: +1.604.633.9022

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

No securities regulatory authority has either approved or disapproved of the contents of this news release. The securities being offered have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the "U.S. Securities Act", or any state securities laws, and may not be offered or sold in the United States, or to, or for the account or benefit of, a "U.S. person" (as defined in Regulation S of the U.S. Securities Act) unless pursuant to an exemption therefrom. This press release is for information purposes only and does not constitute an offer to sell or a solicitation of an offer to buy any securities of the Company in any jurisdiction.

Cautionary Note Regarding Forward Looking Statements

This announcement includes certain “forward-looking statements” within the meaning of Canadian securities legislation. All statements, other than statements of historical fact, included herein, without limitation the use of net proceeds, are forward-looking statements. Forward-looking statements involve various risks and uncertainties and are based on certain factors and assumptions. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from the Company’s expectations include uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs; the need to obtain additional financing to maintain its interest in and/or explore and develop the Company’s mineral projects; uncertainty of meeting anticipated program milestones for the Company’s mineral projects; and other risks and uncertainties disclosed under the heading “Risk Factors” in the prospectus of the Company dated March 2, 2012 filed with the Canadian securities regulatory authorities on the SEDAR website at

Non-GAAP Financial Measures

The items marked with a "(1)" are alternative performance measures and readers should refer to Non-GAAP Financial Measures in the Company's Management's Discussion and Analysis for the nine months ended September 30, 2016 as filed on SEDAR and as available on the Company's website for further details.

EN
15/04/2019

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Atico Mining Corp

 PRESS RELEASE

Atico Mining Update on Permitting Process for the La Plata Project in ...

Atico Mining Update on Permitting Process for the La Plata Project in Ecuador VANCOUVER, British Columbia, Feb. 09, 2026 (GLOBE NEWSWIRE) -- Atico Mining Corporation (the “Company” or “Atico”) (TSX.V: ATY | OTCID: ATCMF) is pleased to announce that the Ministry of Environment, Water and Ecological Transition (MAATE) (now the Ministry of Environment and Energy) has granted key additional permits and authorizations for the La Plata project. These include the Environmental License (EL), registration in the Waste and Waste Generator Registry (GDPR), and in the Chemical Substances Registry (RS...

 PRESS RELEASE

Atico Reports Multiple Higher-Grade Intercepts up to 10.20m of 6.26% C...

Atico Reports Multiple Higher-Grade Intercepts up to 10.20m of 6.26% Cu, 8.50 g/t Au and 10.0m of 6.77% Cu, 3.39 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia VANCOUVER, British Columbia, Jan. 28, 2026 (GLOBE NEWSWIRE) -- Atico Mining Corporation (TSX.V: ATY | OTCID: ATCMF) (“Atico” or the “Company”) is pleased to announce positive results from 21 drill holes completed in 2025 within an area of historical mining, successfully expanding the tonnage at the El Roble mine. The table below highlights some assay results in bold for drill core holes, which include 10.2...

 PRESS RELEASE

Atico Reports 2025 Fourth Quarter and Full Year Production Results

Atico Reports 2025 Fourth Quarter and Full Year Production Results VANCOUVER, British Columbia, Jan. 22, 2026 (GLOBE NEWSWIRE) -- Atico Mining Corporation (the “Company” or “Atico”) (TSX.V: ATY | OTCID: ATCMF) is pleased to announce operating results for the three months and year ended December 31, 2025 from its El Roble mine. Production totaled 2.6 million pounds of copper with 2,203 ounces of gold for the fourth quarter (“Q4 2025”) and 9.2 million pounds of copper with 8,013 ounces of gold in concentrates for the full year of 2025. “During 2025 El Roble went through a transitional year...

 PRESS RELEASE

Atico Mining Announces Proposed Debenture Amendment and Restatement wi...

Atico Mining Announces Proposed Debenture Amendment and Restatement with Dundee VANCOUVER, British Columbia, Dec. 16, 2025 (GLOBE NEWSWIRE) -- Atico Mining Corporation (the “Company” or “Atico”) (TSX.V: ATY | OTC: ATCMF) announces that it intends to amend and restate the Company’s existing debenture agreement (the “Debenture Agreement”) issued on December 16, 2020 to Dundee Corporation (the “Dundee”), of which US$6,612,192 in principal amount remains outstanding (the “Principal Amount”). Pursuant to the amendment and restatement, the maturity date will be extended to December 16, 2027 an...

 PRESS RELEASE

Atico Reports Multiple High-Grade Intercepts up to 8.70m of 11.44% Cu,...

Atico Reports Multiple High-Grade Intercepts up to 8.70m of 11.44% Cu, 14.65 g/t Au and 6.16m of 13.32% Cu, 2.79 g/t Au and Continues to Extend the Ore Body at El Roble Mine in Colombia VANCOUVER, British Columbia, Nov. 24, 2025 (GLOBE NEWSWIRE) -- Atico Mining Corporation (TSX.V: ATY | OTCQX: ATCMF) (“Atico” or the “Company”) is pleased to announce positive results for 19 drill holes completed during 2025 in an area of historical mining to expand tonnage at the El Roble mine. In addition, the Company reports the highlights from assay results for two drill core holes (see first table belo...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch