Canyon Continues Rapid Advancement Toward Production

PERTH, Australia, Feb. 26, 2025 (GLOBE NEWSWIRE) -- Canyon Resources Limited (ASX: CAY) (‘Canyon’ or the ‘Company’) is pleased to provide an update on key development workstreams at the Company’s flagship Minim Martap Bauxite Project (‘Minim Martap’ or ‘the Project’), located in Cameroon, as the Company continues to make rapid progress toward production.

Minim Martap ranks among the world’s richest bauxite deposits, underpinned by an Ore Reserve of 109Mt at 51.1% total Al2O3 and 2.0% total SiO2 and a JORC Mineral Resource Estimate of 1,027Mt at 45.3% total Al2O3 and 2.7% total SiO2

The Definitive Feasibility Study (DFS) remains on schedule for completion in Q3 2025, with a focus on optimising operational efficiencies, ensuring sustainable economics and confirming the preferred pathway to production. The Company remains confident that the DFS will reinforce the viability of Minim Martap as a world-class bauxite project. Concurrently, discussions with select debt providers are progressing positively, as Canyon seeks to secure an optimal funding structure in alignment with strategic objectives and results from the DFS.

As part of the DFS, Canyon is currently evaluating the implementation of a two-stage development strategy, aimed at accelerating production through a phased ramp-up to enable a first bauxite shipment in 2026. This approach would enable earlier revenue generation, strengthen supply chain relationships and strategically position Minim Martap for future growth as rail capacity expands. In addition to this process, Canyon has engaged several internationally recognised consultants to refine and optimise the existing rail infrastructure required for the transport of the bauxite ore. Detailed assessments are now underway to enhance logistical efficiency and explore capacity expansion strategies that will support long-term operational growth.

As part of project execution planning, Canyon is working with leading mining equipment vendors to define procurement schedules and delivery timelines, ensuring timely access to critical mining equipment, which will be essential for meeting targeted production timelines and targets and maintaining operational efficiency. The Company remains focused on aligning equipment availability with its potential staged development strategy to support seamless project execution.

Discussions with potential offtake partners are advancing well, with negotiations reflecting strong market interest in Minim Martap’s high-quality bauxite product and supporting the Company’s efforts to secure long-term sales agreements. Establishing these strategic partnerships is a key step in de-risking the Project, working through the relevant financing discussions and ensuring an efficient pathway towards commencement of operations.

Bauxite market fundamentals and pricing has strengthened over the past 12 months, with the CIF China price for 45% Al203 and 3% total SiO2 ex Guinea reported to be approximately $US 100/DMT in February 2025. The product from Minim Martap with a proved or reserve grade 51.1% total Al203 and total SiO2 should achieve a considerable premium price compared to a 45% Al2O3 and SiO2 bauxite product.

Lastly, Canyon continues to focus on building out its project team and management team to ensure the Company is well-positioned during the next phase of development growth, as Canyon works toward becoming a near-term bauxite producer.

Mr Jean-Sebastien Boutet, Canyon Chief Executive Officer commented: “Progress at our world-class Minim Martap Project continues as planned, reinforcing our confidence in our timeline towards production. Notably, the analysis of a potential two-staged development strategy has been particularly promising, offering the opportunity for fast-tracked production and revenue generation, while strategically positioning the Company to capitalise on expanding rail capacity and the establishment of key supply chain relationships.

"Our team remains committed to transforming the Minim Martap Bauxite Project into a world-class operation that delivers sustainable, long-term value for shareholders and stakeholders alike. We will continue to provide timely updates as we achieve key milestones and advance toward production.”

This announcement has been approved for release by the Canyon Resources’ Board of Directors.

Enquiries: 
Jean-Sebastien BoutetCameron Gilenko
Chief Executive OfficerInvestor Relations & Media
Canyon Resources LimitedSodali & Co
T  T  
E:    



                                                        

                                                

                                                

                                        

              

                              



EN
27/02/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Canyon Resources

 PRESS RELEASE

Construction of IRF and Upgrade of Ore Haulage Access Road Underway

Construction of IRF and Upgrade of Ore Haulage Access Road Underway Highlights Groundbreaking ceremony kicks of the construction of the Inland Rail Facility (IRF) and upgrade of the ore haulage access roadThe IRF and road are critical infrastructure projects for the transfer bauxite from the Minim Martap Mine to the Port of Douala Engineering work for rail and port infrastructure to start soon, and Canyon remains on track for start of production in early 2026 and first shipment in 1H 2026 PERTH, Australia, July 16, 2025 (GLOBE NEWSWIRE) -- Leading bauxite developer C...

 PRESS RELEASE

Appointment of Non-Executive Director

Appointment of Non-Executive Director PERTH, Australia, July 15, 2025 (GLOBE NEWSWIRE) -- Canyon Resources Limited (ASX: CAY) (‘Canyon’ or the ‘Company’) is pleased to announce the appointment of Ms Adjou Ait Ben Idir as Non-Executive Director, as the Company continues to strengthen its team and work towards the commencement of operations at the flagship Minim Martap Bauxite Project, located in Cameroon, in early 2026. Based in Dubai, Ms Ait Ben Idir is a corporate finance and M&A lawyer, who brings more than 20 years of international experience across Europe, Middle-East, and Africa (EM...

 PRESS RELEASE

Commencement of Chief Executive Officer

Commencement of Chief Executive Officer PERTH, Australia, July 01, 2025 (GLOBE NEWSWIRE) -- Canyon Resources Limited (ASX: CAY) (‘Canyon’ or the ‘Company’) is pleased to announce that Mr Peter Secker has officially commenced his role as Chief Executive Officer (CEO), effective 1 July 2025. Canyon announced the leadership transition for Mr Secker and former CEO Mr Jean Sebastien Boutet on February 5, 2025, when Peter joined the Company as a strategic advisor. During this time, Peter has played an instrumental role in supporting the management team and Board, with a focus on optimising th...

 PRESS RELEASE

Project Financing and Key Long Lead Contracts Confirm Schedule for Fir...

Project Financing and Key Long Lead Contracts Confirm Schedule for First Bauxite Shipment in 1H 2026 Highlights Credit facility secured from AFG Bank Cameroon (~US$140M), together with proceeds from the recent option exercise by Eagle Eye Asset Holdings Pte Ltd (EEA) (A$15.8M), has paved the way for the purchase of long lead items and appointment of key contractors Canyon in a strong position to commence production at the flagship Minim Martap Bauxite Project in early 2026 and make first bauxite shipment in 1H 2026Locomotives order has been placed with CRRC Ziyang Co. Ltd (CRRC), with firs...

 PRESS RELEASE

~US$140M Credit Facility Secured for the Minim Martap Bauxite Project

~US$140M Credit Facility Secured for the Minim Martap Bauxite Project Project Credit Facility through AFG Bank Cameroon, along with Option Exercise by Eagle Eye Asset Holdings to Fund Stage One Operations PERTH, Australia, May 25, 2025 (GLOBE NEWSWIRE) -- Canyon Resources Limited (ASX: CAY) (‘Canyon’ or the ‘Company’) is pleased to announce that its wholly owned in-country subsidiary, Camalco Cameroon SA (‘Camalco’) has signed a binding agreement with AFG Bank Cameroon (‘AFG Bank CM’) for a medium-term syndicated credit facility of XAF 82,000,000,000 (~US$140M) (‘Credit Facility’). ...