Project Financing and Key Long Lead Contracts Confirm Schedule for First Bauxite Shipment in 1H 2026

Project Financing and Key Long Lead Contracts Confirm Schedule for First Bauxite Shipment in 1H 2026

Highlights

  • Credit facility secured from AFG Bank Cameroon (~US$140M), together with proceeds from the recent option exercise by Eagle Eye Asset Holdings Pte Ltd (EEA) (A$15.8M), has paved the way for the purchase of long lead items and appointment of key contractors
  • Canyon in a strong position to commence production at the flagship Minim Martap Bauxite Project in early 2026 and make first bauxite shipment in 1H 2026
  • Locomotives order has been placed with CRRC Ziyang Co. Ltd (CRRC), with first deliveries scheduled for Q1 2026
  • Groundbreaking for the Inland Rail Facility (IRF) scheduled to commence in July 2025
  • Road construction contractor appointed with the haulage road upgrade works planned to commence in July 2025
  • Both the Mining Contractor and Ore Haulage contractor have been appointed and scheduled to mobilise to Minim Martap by end of CY2025 to commence mine production in Q1 2026
  • Remaining 124M options (A$8.7M) held by EEA expected to be converted in June
  • Updated JORC Compliant Mineral Resource and Mineral Reserve Estimates for Minim Martap scheduled for end of July 2025

PERTH, Australia, June 26, 2025 (GLOBE NEWSWIRE) -- Leading bauxite developer Canyon Resources Limited (ASX: CAY) (‘Canyon’ or the ‘Company’) is pleased to announce the purchase of key long lead items and appointment of contractors, as the Company works towards the commencement of production at its flagship Minim Martap Bauxite Project (‘Minim Martap’ or ‘the Project’), located in Cameroon, in early 2026.

Following the recently secured medium-term syndicated credit facility for ~US$140M with the AFG Bank Cameroon and the Company’s major shareholder and long-term supporter Eagle Eye Asset Holdings Pte Ltd exercising A$15.8M of its options, Canyon is now advancing critical site, port and rail development activities to ensure Stage One operations commence at Minim Martap in Q1, 2026.

The Company has ordered 22 locomotives from CRRC and expects the first delivery to arrive in Q1 2026, ahead of the scheduled first bauxite shipment in 1H 2026.

Canyon has appointed the main road construction contractor that will be responsible for upgrading the haulage road from Minim Martap, as well as supporting the development of the Inland Rail Facility (IRF) located in Ngaoundal.

Groundbreaking at the IRF is expected to commence during the month of July, marking another significant milestone in the Company’s Project development.

Mr Mark Hohnen, Canyon Executive Chairman commented: ”Since we received our Mining Licence in late 2024, we have moved quickly to deliver on our vision of moving the Minim Martap Bauxite Project into production, and today’s announcement is another big step forward in achieving this major goal.

“I am incredibly proud of the tireless effort and commitment displayed by our team in recent months to get to this point. The support from our strategic partner and major shareholder, Eagle Eye, has been critical in the progress we’ve made to date, and the ongoing support from key stakeholders and shareholders holds us in good stead as we continue to accelerate our work program and move towards production in 1H 2026.

“The loan agreement with AFG Bank Cameroon and the proceeds from Eagle Eye’s option exercise has put us in a strong position to advance critical workstreams for Stage One operations at Minim Martap. With the key contracts in place or close to being finalised, Canyon can now work towards finalising the Definitive Feasibility Study, which has a dedicated focus on a two stage ramp up strategy, positioning us for success upon the commencement of production.

“Progress across all key aspects of the development of Minim Martap is on schedule and we anticipate breaking ground at the Inland Rail Facility in the coming weeks. The IRF, which is situated near the existing Makor Railway Station, will serve as the loading station for wagons of bauxite ore brought by road from the Project. The construction of this key piece of infrastructure will secure our transport supply chain from the mine to the Port of Douala, where we will then ship to our offtake customers.

“In addition, we are also working towards updating Minim Martap’s Mineral Resource and Mineral Reserve Estimate and expect to release the results to the market very soon. These successive achievements underpin the strong recognition from the authorities in Cameroon, the local community, and our team in establishing Minim Martap as a key bauxite operation.

“We are excited to keep this momentum going and establish Canyon as a key supplier of high-quality bauxite ore into a market that urgently needs new sources of long-term supply.”



Image 1: Signing of the locomotive order with CRRC Ziyang Co. Ltd (CRRC)

This announcement has been approved for release by the Canyon’s Board of Directors.

Enquiries: 
Jean-Sebastien BoutetCameron Gilenko
Chief Executive OfficerInvestor Relations & Media
Canyon Resources Limited Sodali & Co
T T
E: E:
  

Forward looking statements

This announcement contains forward-looking statements. These statements can be identified by words such as “anticipate”, “may”, “will”, “expect”, “intend”, “estimate”, “opportunity”, “plan”, “potential”, “project”, “seek”, “believe”, “could”, “future” and other similar words that involve risks and uncertainties. These statements are based on an assessment of present economic and operating conditions, and on a number of assumptions regarding future events and actions that are expected to take place. Such forward-looking statements are not guarantees of future performance and involve known and unknown risks, uncertainties, assumptions and other important factors, many of which are beyond the control of the Company, its directors and management that could cause the Company’s actual results to differ materially from the results expressed or anticipated in these statements.

The Company cannot and does not give any assurance that the results, performance or achievements expressed or implied by the forward-looking statements contained in this announcement will actually occur and investors are cautioned not to place undue reliance on these forward-looking statements. The Company does not undertake to update or revise forward-looking statements, regardless of whether any new information, future events or any other factors affect the information contained in this announcement, except where required by applicable law and ASX requirements.

A photo accompanying this announcement is available at



EN
26/06/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Canyon Resources

 PRESS RELEASE

Minim Martap Project Development Update

Minim Martap Project Development Update Highlights Surface miner mobilised to site, with mining operations scheduled to commence in the coming weeks and first production targeted for early Q2, 2026.Updated financial cashflow modelling confirms that the Company’s current cash position along with AFG debt financing fully supports the Company’s CAPEX requirements for Stage 1 as outlined in the DFS, enabling first ore shipment in Q3, 2026, without the need for additional funding from EEA or Afriland.Discussions with CRRC remain ongoing, with current forecasts indicating the first locomotives...

 PRESS RELEASE

Minim Martap Development Update

Minim Martap Development Update Highlights The surface miner has arrived in Cameroon, with mining operations scheduled to commence in February 2026.Delivery of locomotives and wagons scheduled in Q1, 2026. Ore haulage from the Inland Rail Facility to the Port of Douala is planned for Q2, 2026, supporting first bauxite shipment targeted for late June 2026.Recruitment of the Mine Director and Port Manager has been finalised, with both appointees due to be in country this month.The alumina refinery Feasibility Study is progressing well and is 45% complete.Discussions with Camrail regarding th...

 PRESS RELEASE

Minim Martap Development Update

Minim Martap Development Update Highlights Construction of ore haulage access road ongoing and all clearing completed with focus now on IRF access and Danielle plateau access.First surface miner scheduled to arrive in Cameroon in January 2026 and commence mining on site in February 2026.Engineering designs for IRF have been completed and switchgear, tracks and sleepers for IRF, stations and port have been ordered with delivery scheduled for February 2026. IRF remains on track for completion by May 2026.Road haulage of first ore from mine to IRF scheduled for March 2026. Locomotives and wa...

 PRESS RELEASE

Minim Martap Project Update

Minim Martap Project Update Highlights Construction work ongoing on ore haulage access road, IRF and site access Locomotives delivery remains on schedule in first quarter 2026Mining contractor has visited site confirming mobilisation schedule with mine development to commence in first quarter 2026Project development timeline remains unchangedProject fully financed to Stage 1 production Incumbent President Paul Biya has been officially re-elected as the President of Cameroon PERTH, Australia, Nov. 06, 2025 (GLOBE NEWSWIRE) -- Canyon Resources Limited (ASX: CAY) (‘Canyon’ or the ‘Company’...

 PRESS RELEASE

Definitive Feasibility Study Results and Reserves Upgrade Confirms Min...

Definitive Feasibility Study Results and Reserves Upgrade Confirms Minim Martap as a Tier-One Bauxite Operation Canyon to Build Minim Martap into a Long-Life and Key Bauxite Operation, Underpinned by an NPV of US$835M, IRR of 29% and a 33% Increase in Ore Reserves PERTH, Australia, Sept. 02, 2025 (GLOBE NEWSWIRE) -- HIGHLIGHTS Ore Reserves Estimate Upgrade 33% increase in DSO (Direct Shipping Ore) grade Ore Reserves at Minim Martap to 144DMt of ore at 51.2% Al2O3 and 1.7% SiO2 over 20 year mine lifeHigh alumina grade of >51% and low silica content will command a long-term price prem...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch