In March, Enefit Green produced 233.6 GWh or 60.4% more electricity than in the same period last year. In Q1 as a whole, Enefit Green's electricity production increased by 24.8% to 616.9 GWh, mainly due to the addition of new wind and solar farms to the portfolio.

March production result was mainly driven by 61% y-o-y increase in the volume of wind energy production (207.8 GWh). A significant contribution to the growth was provided by two new wind farms –Sopi-Tootsi wind farm in Estonia (59.9 GWh) and Kelme I in Lithuania (20.9 GWh).

Unlike in February, which was characterized by very calm weather, average wind speeds in March were noticeably better in Estonia and Finland (6.4 and 7.7 m/s, respectively, compared to 5.6 and 6.7 m/s last year) and broadly similar to last year's levels in Lithuania (6.8 m/s, 6.7 m/s last year). Portfolio-wide average wind speed was 6.7 m/s in March, with a +3.3 GWh impact on production.

Q1 as a whole was relatively calm due to February – the average wind speed in Estonia was 6.2 (-0.2 compared to last year) m/s and in Lithuania 6.6 (-0.8) m/s, which had a -57.4 GWh impact on production. In Tolpanvaara (Finland), the wind conditions were better – the average wind speed was 7.7 (+0.3) m/s - but curtailments caused by excessively low market prices resulted in a production decrease compared to last year's results. The overall impact of wind conditions on the production in the first quarter was -56.1 GWh. The availability impact of wind farms on Q1 production volumes was -10.8 GWh. System services and price related curtailments had -69.6 GWh impact on the production volumes.

Solar energy production increased by 158% y-o-y to 14 GWh in March and by 137% to 20 GWh in the first quarter as a whole. The growth is driven by increased installed capacity and the addition of new solar farms to the portfolio (the most important of which is the Sopi 74 MW solar park, which produced nearly 6 GWh in March).

March electricity and heat production of the Iru cogeneration plant increased by 8.8% and 6.6% y-o-y to 11.6 and 36.1 GWh, respectively. In Q1 as a whole, the production of electricity and heat in the combined heat and power segment decreased by 6% and 18.8% to 32.0 and 104.8 GWh, respectively. The first quarter of this year is the last period during which the y-o-y change of production levels is mainly driven by the sale of biomass assets completed in February last year.

Innar Kaasik, Member of the Management Board and COO of Enefit Green, comments Q1 production results: " The production result of the first quarter was largely driven by the exceptionally calm February, which was not compensated by the better wind conditions in January and March. In Lithuania and Finland, icing of wind turbine blades caused negative effects on availability as did anti-icing system repair works carried out in Tolpanvaara."



 March 2025 March 2024Change, %
Electricity production by countries, GWh   
Estonia133.656.9134.9%
Lithuania82.070.915.6%
Latvia1.2--
Poland3.32.339.7%
Finland13.615.5-12.4%
Total233.6145.660.4%
    
Electricity production by segment, GWh   
Wind207.8129.360.7%
incl. new wind farms126.552.5141.0%
Cogeneration11.610.78.8%
Solar14.05.4158.1%
incl. new solar farms11.23.4230.4%
Other0.20.2-17.0%
Total233.6145.660.4%
    
Heat energy, GWh36.133.96.6%
    
 Q1 2025 Q1 2024Change, %
Electricity production by countries, GWh   
Estonia346.7212.762.9%
Lithuania223.4234.1-4.6%
Latvia1.61.9-18.1%
Poland5.64.138.2%
Finland39.741.5-4.3%
Total616.9494.324.8%
    
Electricity production by segment, GWh   
Wind564.3451.425.0%
incl. new wind farms327.6163.3100.7%
Cogeneration32.034.0-6.0%
incl. assets sold0.04.1-100.0%
Solar20.08.5136.5%
incl. new solar farms15.75.2203.9%
Other0.60.442.3%
Total616.9494.324.8%
    
Heat energy, GWh104.8129.1-18.8%
incl. assets sold0.020.8-100.0%





Further information:

Sven Kunsing

Head of Finance Communications





EN
11/04/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on ENEFIT GREEN AS

 PRESS RELEASE

Enefit Green production data – March and Q1 2025

Enefit Green production data – March and Q1 2025 In March, Enefit Green produced 233.6 GWh or 60.4% more electricity than in the same period last year. In Q1 as a whole, Enefit Green's electricity production increased by 24.8% to 616.9 GWh, mainly due to the addition of new wind and solar farms to the portfolio. March production result was mainly driven by 61% y-o-y increase in the volume of wind energy production (207.8 GWh). A significant contribution to the growth was provided by two new wind farms –Sopi-Tootsi wind farm in Estonia (59.9 GWh) and Kelme I in Lithuania (20.9 GWh). Unlike...

 PRESS RELEASE

Enefit Greeni tootmisandmed – märts ja I kvartal 2025

Enefit Greeni tootmisandmed – märts ja I kvartal 2025 Enefit Green tootis märtsis 233,6 GWh ehk 60,4% võrra rohkem elektrienergiat eelmise aasta sama perioodiga võrreldes. Esimese kvartali kokkuvõttes kasvas Enefit Greeni elektritoodang 24,8% võrra 616,9 GWh tasemele peamiselt tänu uute tuule- ja päikeseparkide lisandumisele tootmisportfelli. Märtsi tootmistulemust mõjutas võrreldes mullusega enim tuuleenergia toodangu mahu kasv 61% võrra 207,8 GWh-ni. Tuuleenergia toodangu kasvu andsid olulise panuse uued tuulepargid – Sopi-Tootsi tuulepark Eestis (59,9 GWh) ja Kelme I Leedus (20,9 GWh). ...

 PRESS RELEASE

NOTIFICATION OF VOLUNTARY TAKEOVER BID REGARDING THE SHARES OF ENEFIT ...

NOTIFICATION OF VOLUNTARY TAKEOVER BID REGARDING THE SHARES OF ENEFIT GREEN AS Today, on 7 April 2025, a shareholder of Enefit Green AS, Eesti Energia AS (registry code: 10421629, “Offeror”), has notified of making a voluntary takeover bid to acquire all shares of Enefit Green AS not yet belonging to the Offeror with a price of EUR 3.40 per share. Below we publish the Offeror’s notice regarding the voluntary takeover offer together with the prospect annexed to it without any amendments. _____________________________________________________________________________ NOTICE OF VOLUNTARY TAKE...

 PRESS RELEASE

TEAVITUS VABATAHTLIKUST ÜLEVÕTMISPAKKUMISEST SEOSES ENEFIT GREEN AS-I ...

TEAVITUS VABATAHTLIKUST ÜLEVÕTMISPAKKUMISEST SEOSES ENEFIT GREEN AS-I AKTSIATEGA Enefit Green AS-i aktsionär Eesti Energia AS (registrikood: 10421629, edaspidi „Ülevõtja“) teavitas täna, 7. aprillil 2025 vabatahtlikust ülevõtmispakkumisest kõigi veel Ülevõtjale mitte kuuluvate Enefit Green AS aktsiate omandamiseks ostuhinnaga 3,40 eurot aktsia kohta. Alljärgnevalt avaldame Ülevõtja teate vabatahtliku ülevõtmispakkumise kohta koos selle lisaks oleva prospektiga muutmata kujul. _____________________________________________________________________________ TEADE VABATAHTLIKUST ÜLEVÕTMISPAKKUM...

 PRESS RELEASE

Enefit Green 2024 audited annual report and profit allocation proposal

Enefit Green 2024 audited annual report and profit allocation proposal At its meeting on 31 March, the Supervisory Board of Enefit Green approved the 2024 audited annual report of the Company and will submit it to the Annual General Meeting of shareholders for approval.  The annual report with included independent auditor's report (translations from Estonian originals) is attached to this notice and will be made available on Enefit Green's website at Profit allocation proposal  Enefit Green's dividend policy (approved in 2021) foresees the intention to distribute 50% of the net profi...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch