IGN AB Ignitis Grupe GDR

114.1 MW Kelmė wind farm I in Lithuania has reached the commercial operation date

114.1 MW Kelmė wind farm I in Lithuania has reached the commercial operation date

AB “Ignitis grupė” (hereinafter – the Group) informs that Kelmė wind farm I, controlled by its subsidiary UABIgnitis renewables” (hereinafter – Ignitis Renewables), has reached the commercial operation date (hereinafter – COD). 

The project is located in central Lithuania, Kelmė district, and consists of 16 Nordex N163/6.X wind turbines with a total installed capacity of 114.1 MW. The total investments in the wind farm will reach around EUR 190 million. 

The installed capacity was adjusted in accordance with the current regulations, resulting in an increase from 105.4 MW, as previously reported, to 114.1 MW. 

Kelmė wind farm I, together with Kelmė wind farm II, which is set to reach COD later this year, is a part of the largest wind project currently under construction in the Baltics, Kelmė wind farm. The project will have a combined installed capacity of 313.7 MW (up from 300 MW). The wind farm will be able to cover the electricity demand of 250 thousand Lithuanian households. The expected total investments in the 313.7 MW Kelmė wind farm, including the acquisition price and construction costs, should reach around EUR 550 million. 

Since the COD of Kelmė wind farm I, the Group’s installed Green Capacities have increased to 1.5 GW (from 1.4 GW). 

The Group reminds that its objective is to increase its Green Capacities from 1.4 GW in 2024 to 4–5 GW by 2030. For further details, see the Group’s strategy (). 

The information provided in this announcement does not affect the Group’s Adjusted EBITDA and Investments guidance for 2025.



For additional information, please contact:

Communication

Valdas Lopeta

+370 621 77993

 



EN
17/04/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on AB Ignitis Grupe GDR

 PRESS RELEASE

Ignitis Group concluded a EUR 77.5 million financing agreement with Sw...

Ignitis Group concluded a EUR 77.5 million financing agreement with Swedbank AB “Ignitis grupė” (hereinafter – the Group) informs that on 16 May 2025 a subsidiary of the Group, SP Venta SIA, concluded a EUR 77.5 million project financing agreement (hereinafter – the Loan) with Swedbank AS (Latvia) and “Swedbank” AB (Lithuania) regarding a Stelpe solar farm and Vārme solar farm with a total capacity of 239 MW.The Loan will be granted by two creditors, divided equally equal, for a period of 15 years. Other terms and conditions of the Loan are standard for project financing transactions.The 94...

 PRESS RELEASE

„Ignitis grupė“ sudarė 77,5 mln. Eur finansavimo sutartį su „Swedbank“

„Ignitis grupė“ sudarė 77,5 mln. Eur finansavimo sutartį su „Swedbank“ AB „Ignitis grupė“ (toliau – Grupė) informuoja, kad 2025 m. gegužės 16 d. Grupės dukterinė įmonė SP Venta SIA pasirašė 77,5 mln. eurų projektinio finansavimo sutartį (toliau – Paskola) su Swedbank AS (Latvija) ir „Swedbank“, AB (Lietuva) dėl 239 MW bendros galios Stelpės saulės parko ir Varmės saulės parko Latvijoje.Paskola suteikiama dviejų kreditorių lygiomis dalimis 15 metų laikotarpiui. Kitos Paskolos sąlygos yra standartinės, taikomos projektiniam finansavimui.94 MW Varmės saulės parkas yra Kuldygos savivaldybėje ir...

 PRESS RELEASE

Ignitis Group concluded a EUR 77.5 million financing agreement with Sw...

Ignitis Group concluded a EUR 77.5 million financing agreement with Swedbank AB “Ignitis grupė” (hereinafter – the Group) informs that on 16 May 2025 a subsidiary of the Group, SP Venta SIA, concluded a EUR 77.5 million project financing agreement (hereinafter – the Loan) with Swedbank AS (Latvia) and “Swedbank” AB (Lithuania) regarding a Stelpe solar farm and Vārme solar farm with a total capacity of 239 MW.The Loan will be granted by two creditors, divided equally equal, for a period of 15 years. Other terms and conditions of the Loan are standard for project financing transactions.The 94...

 PRESS RELEASE

AB “Ignitis grupė” Strategic Plan 2025–2028: paving the way towards 10...

AB “Ignitis grupė” Strategic Plan 2025–2028: paving the way towards 100% green and secure energy ecosystem AB “Ignitis grupė” (hereinafter – the Group) publishes its Strategic Plan 2025–2028, which is attached to this notice. The Group remains committed to executing its ambitious strategy with the purpose to create a 100% green and secure energy ecosystem for current and future generations.We are continuing to expand the Group’s Green Capacities Portfolio to reach 4–5 GW of installed Green Capacities by 2030, thus strengthening the energy security and contributing to the surplus green energ...

 PRESS RELEASE

AB “Ignitis grupė” Strategic Plan 2025–2028: paving the way towards 10...

AB “Ignitis grupė” Strategic Plan 2025–2028: paving the way towards 100% green and secure energy ecosystem AB “Ignitis grupė” (hereinafter – the Group) publishes its Strategic Plan 2025–2028, which is attached to this notice. The Group remains committed to executing its ambitious strategy with the purpose to create a 100% green and secure energy ecosystem for current and future generations.We are continuing to expand the Group’s Green Capacities Portfolio to reach 4–5 GW of installed Green Capacities by 2030, thus strengthening the energy security and contributing to the surplus green energ...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch