136.8 MW Silesia wind farm II in Poland reached the commercial operation date

136.8 MW Silesia wind farm II in Poland reached the commercial operation date

AB “Ignitis grupė” (hereinafter – the Group) informs that Silesia wind farm II, a wind farm controlled by its subsidiary UAB “Ignitis renewables” (hereinafter – Ignitis Renewables), has reached the commercial operation date (hereinafter – COD).

Silesia wind farm II is located in the south of Poland, Opole voivodeship, and is equipped with 38 Nordex N117/3600 wind turbines with a total installed capacity of 136.8 MW. The wind farm can meet the annual electricity demand of around 177 thousand households. It is one of the largest wind farms operating in Poland.

The total investment in the wind farm, including the acquisition price and construction costs, is expected to reach up to EUR 240 million.

With Silesia wind farm II reaching COD, the Group’s installed Green Capacities have increased to 2.1 GW (from 1.9 GW).

The Group reminds that its strategic priority is to increase its Green Capacities from 1.4 GW in 2024 to 4–5 GW by 2030. For further details, see the Group’s strategy ().

The information provided in this notice does not affect the Group’s Adjusted EBITDA and Investments guidance for 2025.

For additional information, please contact:

Communication

Valdas Lopeta





EN
25/08/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on AB Ignitis Grupe GDR

 PRESS RELEASE

Resolutions of the General Meeting of Shareholders of AB “Ignitis grup...

Resolutions of the General Meeting of Shareholders of AB “Ignitis grupė” The General Meeting of Shareholders of AB “Ignitis grupė” (hereinafter – the Group), legal entity code: 301844044, registered office address: Laisvės Ave. 10, Vilnius, which was held on 10 September 2025, passed the following resolutions: 1. Agreement to AB “Ignitis grupė” consolidated interim management report for the six-month period ended 30 June 2025.1.1. To agree to AB “Ignitis grupė” consolidated interim management report for the six-month period ended 30 June 2025. 2. Approval of the set of interim condensed f...

 PRESS RELEASE

AB „Ignitis grupė“ visuotinio akcininkų susirinkimo sprendimai

AB „Ignitis grupė“ visuotinio akcininkų susirinkimo sprendimai AB „Ignitis grupė“ (toliau – Grupė), juridinio asmens kodas: 301844044, registruotos buveinės adresas: Laisvės pr. 10, Vilnius, visuotiniame akcininkų susirinkime, kuris įvyko 2025 m. rugsėjo 10 d., buvo priimti šie sprendimai: 1. Dėl pritarimo AB „Ignitis grupė“ konsoliduotajai tarpinei vadovybės ataskaitai už šešių mėnesių laikotarpį, pasibaigusį 2025 m. birželio 30 d.1.1. Pritarti AB „Ignitis grupė“ konsoliduotajai tarpinei vadovybės ataskaitai už šešių mėnesių laikotarpį, pasibaigusį 2025 m. birželio 30 d. 2. Dėl AB „Ignit...

 PRESS RELEASE

Resolutions of the General Meeting of Shareholders of AB “Ignitis grup...

Resolutions of the General Meeting of Shareholders of AB “Ignitis grupė” The General Meeting of Shareholders of AB “Ignitis grupė” (hereinafter – the Group), legal entity code: 301844044, registered office address: Laisvės Ave. 10, Vilnius, which was held on 10 September 2025, passed the following resolutions: 1. Agreement to AB “Ignitis grupė” consolidated interim management report for the six-month period ended 30 June 2025.1.1. To agree to AB “Ignitis grupė” consolidated interim management report for the six-month period ended 30 June 2025. 2. Approval of the set of interim condensed f...

 PRESS RELEASE

136.8 MW Silesia wind farm II in Poland reached the commercial operati...

136.8 MW Silesia wind farm II in Poland reached the commercial operation date AB “Ignitis grupė” (hereinafter – the Group) informs that Silesia wind farm II, a wind farm controlled by its subsidiary UAB “Ignitis renewables” (hereinafter – Ignitis Renewables), has reached the commercial operation date (hereinafter – COD). Silesia wind farm II is located in the south of Poland, Opole voivodeship, and is equipped with 38 Nordex N117/3600 wind turbines with a total installed capacity of 136.8 MW. The wind farm can meet the annual electricity demand of around 177 thousand households. It is one ...

 PRESS RELEASE

136,8 MW galios Silezijos vėjo parkas II Lenkijoje pasiekė komercinės ...

136,8 MW galios Silezijos vėjo parkas II Lenkijoje pasiekė komercinės veiklos pradžią AB „Ignitis grupė“ (toliau – Grupė) informuoja, kad Silezijos vėjo parkas II, kurį valdo jos patronuojamoji įmonė UAB „Ignitis renewables“ (toliau – „Ignitis renewables“), pasiekė komercinės veiklos pradžią (angl. commercial operation date, COD). Pietų Lenkijoje, Opolės vaivadijoje, esantį Silezijos vėjo parką II sudaro 38 vėjo elektrinės „Nordex“ N117/3600, o bendra jų instaliuota galia siekia 136,8 MW. Šio vėjo parko pagaminta elektros energija patenkins apie 177 tūkst. namų ūkių poreikius. Tai – vienas...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch