IGN AB Ignitis Grupe GDR

First three months 2024 interim report: continued Green Capacities Portfolio growth

First three months 2024 interim report: continued Green Capacities Portfolio growth

AB “Ignitis grupė” (hereinafter – the Group) publishes its first three months 2024 interim report, which is attached to this notice, and announces that the Group’s Adjusted EBITDA amounted to EUR 181.7 million (+21.2% YoY). Growth was recorded across all business segments, except Reserve Capacities. Customers & Solutions segment electricity B2C activities continued to be loss-making (EUR -8.2 million). The Green Capacities segment remains the largest contributor with a 42.4% share of the Group’s total Adjusted EBITDA.

We increased Investments by 73.4% YoY to EUR 209.5 million. Two thirds of the total Investments were directed towards the Green Capacities segment, and 90.5% to Lithuania. The Investments into Green Capacities have tripled and reached EUR 138.9 million, with the majority directed towards new onshore wind farms.

The Group’s leverage metrics remained strong, with FFO/Net Debt ratio at a solid level of 28.9% (compared to 29.4% as of 31 December 2023).

Business development

In 3M 2024, we increased our Green Capacities Portfolio to 7.4 GW (from 7.1 GW) and Installed Capacity to 1.4 GW (from 1.3 GW). Our Secured Capacity stood at 2.9 GW.

We reached a number of significant milestones in the expansion and development of our Green Capacities Portfolio, including the following:

– we, together with our partner CIP, won the second seabed site (Liivi 1) in the Estonian offshore wind tender and see the site as a natural extension of the Liivi 2 sea area (secured in December 2023);

– Silesia WF I (50 MW) in Poland has COD;

– we have secured grid capacity for the first BESS projects (<190 MW) in Lithuania;

– we have submitted a bid in the tender for the second 700 MW Lithuanian offshore wind project. However, due to the limited number of participants, the tender did not convene but is expected to take place in due course, following a review of the tender conditions.

In Networks, the total number of installed smart meters has exceeded 836 thousand.

In Customers & Solutions, we continue to expand the EV charging network in the Baltics, with multiple locations secured for the installation of 67 EV charging points.

Sustainability

Our Green Share of Generation decreased by 15.7 pp to 79.9% YoY due to proportionally higher electricity generation at CCGT (Reserve Capacities).

We reduced our GHG emissions by 60.4% in Scope 2, while our Scope 1 and Scope 3 emissions compared to 3M 2023 increased by 49.4% and 5.5% respectively. Total emissions amounted to 1.61 million t CO2-eq and increased by 12.5% YoY.

Carbon intensity of Scope 1 and 2 GHG emissions decreased by 33.8% YoY to 220 g CO2-eq/kWh due to higher electricity production from renewables and reduction of Scope 2 emissions.

No fatal accidents were recorded, and employee Total Recordable Injury Rate (TRIR) was 0.99, contractor TRIR – 0, both well below the targeted threshold. eNPS remained high at 65.5%.

Shareholder returns and 2024 outlook

In line with our Dividend Policy, a dividend of EUR 0.643 per share, corresponding to EUR 46.5 million, was distributed for H2 2023.

We maintain our full-year 2024 Adjusted EBITDA guidance of EUR 440–470 million and Investments guidance of EUR 850–1,000 million.

Key financial indicators (APM1)

EUR, millions 3M 2024 3M 2023 Change
Adjusted EBITDA 181.7 149.9 21.2%
Green Capacities2 77.1 70.0 10.1%
Networks 65.5 48.7 34.5%
Reserve Capacities 20.0 28.6 (30.1%)
Customers & Solutions 17.4 0.9 n/a
Other activities and eliminations3 1.7 1.7 -%
Adjusted EBITDA Margin 28.1% 17.0% 11.1 pp
EBITDA 188.9 195.3 (3.3%)
EBITDA Margin 28.9% 21.0% 7.9 pp
Adjusted Net Profit 112.6 88.7 26.9%
Net Profit 118.7 127.2 (6.7%)
Net Profit Margin 18.2% 13.7% 4.5 pp
Investments 209.5 120.8 73.4%
Green Capacities2 138.9 46.2 200.6%
Networks 63.7 71.6 (11.0%)
Reserve Capacities 0.2 0.3 (33.3%)
Customers & Solutions 2.6 0.6 333.3%
Other activities and eliminations3 4.1 2.1 95.2%
FFO 169.5 185.3 (8.5%)
FCF  5.0 208.0 (97.6%)
Adjusted ROE LTM 14.2% 13.9% 0.3 pp
ROE LTM 14.2% 18.4% (4.2 pp)
Adjusted ROCE LTM 11.1% 12.1% (1.0 pp)
ROCE LTM 10.7% 16.7% 6.0 pp
Basic earnings per share 1.64 1.76 6.8%
  31 Mar 2024 31 Dec 2023 Change
Net Debt 1,287.8 1,317.5 (2.3%)
Net Working Capital 144.4 175.2 (17.6%)
Net Debt/Adjusted EBITDA LTM, times 2.49 2.72 (8.5%)
FFO LTM/Net Debt 28.9% 29.4% (0.5 pp)

1 All, except Net profit, are Alternative Performance Measures (APMs). Definitions and formulas of the financial indicators are available on our .

2 Previously – Green Generation.

3 Other activities and eliminations – includes consolidation adjustments, related-party transactions, and the financial results of the parent company.





Earnings call

In relation to the announcement of the first three months 2024 interim report, an earnings call will be held on Wednesday, 15 May 2024, at 1:00 pm Vilnius / 11:00 am London time.

To join the earnings call, please register at:   

 

It will be also possible to join the earnings call by phone. To access the dial-in details, please register . After completing the registration, you will receive dial-in details on screen and via email. You will be able to dial in using the provided numbers and the unique pin or by selecting ‘Call me’ option and providing your phone details for the system to reach you automatically as the earnings call starts.

All questions can be directed in advance to the Group’s investor relations team after registering for the earnings call or live, during the call.

Presentation slides will be available prior to the call:

The interim report, including the fact sheet (in Excel), will be available for download at:

For additional information, please contact:

Communications

Artūras Ketlerius



Investor Relations

Ainė Riffel-Grinkevičienė

+370 643 14925

Attachment



EN
15/05/2024

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on AB Ignitis Grupe GDR

 PRESS RELEASE

Notification on managers‘ transactions

Notification on managers‘ transactions AB “Ignitis grupė” (hereinafter – the Group) informs that on 27 May 2024 it received a notice from the Member of the Management Board and CFO of the Group Jonas Rimavičius regarding the contract concluded to purchase shares of the Group (attached).  With this contract, Jonas Rimavičius, has purchased 500 shares of the Group and currently owns 1,000 shares of the Group in total. For more information please contact: Artūras Ketlerius Head of Corporate Communications at Ignitis Group Attachment ...

 PRESS RELEASE

Pranešimas apie vadovo sandorį

Pranešimas apie vadovo sandorį AB „Ignitis grupė“ (toliau – Grupė) informuoja, kad 2024 m. gegužės 27 d. gavo Grupės valdybos nario ir finansų vadovo Jono Rimavičiaus pranešimą apie sudarytą sandorį dėl Grupės akcijų įsigijimo (pridedama).  Šiuo sandoriu Jonas Rimavičius įsigijo 500 Grupės akcijų ir iš viso turi 1 000 Grupės akcijų. Daugiau informacijos: Artūras Ketlerius „Ignitis grupės“ korporatyvinės komunikacijos vadovas Priedas

 PRESS RELEASE

Notification on managers‘ transactions

Notification on managers‘ transactions AB “Ignitis grupė” (hereinafter – the Group) informs that on 27 May 2024 it received a notice from the Member of the Management Board and CFO of the Group Jonas Rimavičius regarding the contract concluded to purchase shares of the Group (attached).  With this contract, Jonas Rimavičius, has purchased 500 shares of the Group and currently owns 1,000 shares of the Group in total. For more information please contact: Artūras Ketlerius Head of Corporate Communications at Ignitis Group Attachment ...

 PRESS RELEASE

Vilnius CHP biomass unit has reached full COD

Vilnius CHP biomass unit has reached full COD AB “Ignitis grupė” (hereinafter – the Group) informs that its subsidiary Vilniaus Kogeneracinė Jėgainė (hereinafter – Vilnius CHP) has completed the construction project because all the necessary documents and permits were received to commence the operations of Vilnius CHP at full capacity. As reported in the Group’s Integrated Annual 2023, in December 2023 Vilnius CHP biomass unit has reached a partial (149 MWth, 50 MWe) COD for generating heat and electricity, in May 2024 it received certificates from the National Energy Regulatory C...

 PRESS RELEASE

Vilniaus kogeneracinės jėgainės biokuro blokas pasiekė visų pajėgumų k...

Vilniaus kogeneracinės jėgainės biokuro blokas pasiekė visų pajėgumų komercinės veiklos pradžią AB „Ignitis grupė“ (toliau – Grupė) informuoja, kad jos valdomos Vilniaus kogeneracinės jėgainės (toliau – Vilniaus KJ) statybų projektas baigtas, nes gauti visi reikalingi dokumentai, leidimai Vilniaus KJ veiklai vykdyti visa apimtimi. Kaip skelbta Grupės 2023 m. integruotame metiniame , Vilniaus KJ biokuro blokas 2023 m. gruodžio mėnesį pasiekė dalinę (149 MWth, 50 MWe) komercinės šilumos ir elektros energijos gamybos veiklos pradžią, o 2024 m. gegužę gavo Valstybinės energetikos regul...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch