VANCOUVER, British Columbia, Jan. 23, 2019 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (the “Company”) (TSX:III) reports its 2018 metals production from all operations totaled 75.32 million pounds copper and 79,056 ounces gold.

Red Chris fourth quarter metal production was 15.57 million pounds copper and 12,366 ounces gold, an increase of 15% and 41% respectively from the 13.55 million pounds copper and 8,741 ounces gold produced in the third quarter of 2018. Mill throughput averaged 29,759 tonnes per calendar day during the 2018 fourth quarter, and averaged 29,228 for the year ended December 31, 2018. Metal recoveries were 76.21% copper and 50.57% gold, compared to 74.92% copper and 45.65% gold in the third quarter of 2018 and for the year averaged 75.60% copper and 47.13% gold.

Annual metal production for 2018 at Red Chris was 60.35 million pounds copper and 41,935 ounces gold, both 97% of the revised production targets. Annual metal production at Red Chris for 2019 are targeted to be in the range of 72-76 million pounds  copper and 36-38 thousand ounces gold.

Mount Polley metal production during the 2018 fourth quarter was 3.18 million pounds copper and 7,983 ounces gold, an increase of 22% and 3% respectively from the 2.60 million pounds copper and 7,748 ounces gold produced in the third quarter of 2018. Mill throughput averaged 17,467 tonnes per calendar day during the 2018 fourth quarter, and averaged 16,975 for the year ended December 31, 2018.  Metal recoveries were 39.05% copper and 59.71% gold, compared to 38.39% copper and 65.06% gold in the third quarter 2018, and for the year averaged 52.89% copper and 67.25% gold.

Annual metal production for 2018 at Mount Polley was 14.97 million pounds copper and 37,120 ounces gold, respectively 96% and 94% of the revised production targets.

Milling of low grade stockpiles at Mount Polley are targeted to continue to the end of May 2019, at which time the mine will be placed on care and maintenance until there is a sustained improvement in the price of copper. Mount Polley, production through to suspension of operations at the end of May 2019 is targeted to be in the range of 4-5 million pounds copper and 13-14 thousand ounces gold.                                                         

About Imperial

Imperial is a Vancouver exploration, mine development and operating company. The Company, through its subsidiaries, owns the Red Chris, Mount Polley and Huckleberry copper mines in British Columbia. Imperial also holds a 50% interest in the Ruddock Creek lead/zinc property.

Company Contacts

Brian Kynoch | President | 604.669.8959

Andre Deepwell | Chief Financial Officer | 604.488.2666

Sabine Goetz | Shareholder Communications | 604.488.2657 |

Cautionary Note Regarding Forward-Looking Statements

Forward-looking statements relate to future events or future performance and reflect Company management's expectations or beliefs regarding future events and include, but are not limited to statements relating to: 2019 metal production targets for the Red Chris and Mount Polley mines; and the planned milling of low grade stockpiles until Mount Polley is expected to be placed into care and maintenance after the end of May 2019 pending a sustained improvement in the price of copper.

In certain cases, forward-looking statements can be identified by the use of words such as “plans”, “expects” or “does not expect”, “is expected”, “outlook”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates” or “does not anticipate”, or “believes”, or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will be taken”, “occur” or “be achieved” or the negative of these terms or comparable terminology. In this document certain forward-looking statements are identified by words including “guidance”, “expectations”, “targeted”, “plan”, “planned”, “estimated”, “calls for” and “expected”.  Forward-looking statements are not based on historical facts, but rather on then current expectations, beliefs, assumptions, estimates and forecasts about the business and the industry and markets in which Imperial operates, including assumptions regarding Red Chris mine and Mount Polley mine operations being conducted in accordance with our current plans, and assumptions regarding receipts of any required approvals. Such statements are qualified in their entirety by the inherent risks and uncertainties surrounding future expectations.

We can give no assurance that the forward-looking statements will prove to be accurate. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, operational risks and hazards, including unanticipated environmental, industrial and geological events and developments and the inability to insure against all risks; risks of failure of plant, equipment, processes, transportation and other infrastructure to operate as anticipated; risks related to changes in project parameters as plans continue to be refined; future prices of mineral resources; possible variations in ore reserves, grade or recovery rates; accidents; dependence on key personnel; availability of drill rigs and other equipment and infrastructure required for the development of mining projects; accuracy of any mineral resources; delays in obtaining governmental approvals or financing or in the completion of development or construction activities; political stability, civil disobedience, the presence of protests and/or blockades; counterparty risks associated with sales of our metals; changes in general economic conditions; currency exchange rates and interest rates; increased operating and capital costs; changes to ownership structure; and other risks of the mining industry as well as those factors detailed from time to time in the Company's management's discussion and analysis of the interim and annual financial reports, available for review on imperialmetals.com and sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.  

EN
23/01/2019

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Imperial Metals

 PRESS RELEASE

Imperial Provides Update on Red Chris 2025 Production and Production G...

Imperial Provides Update on Red Chris 2025 Production and Production Guidance for 2026 VANCOUVER, British Columbia, Feb. 19, 2026 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (the “Company” or “Imperial”) (TSX:III) reports that 2025 metal production from Red Chris (100% basis) was 93,101,213 pounds of copper and 92,429 ounces of gold, up from 85,320,618 pounds of copper and 59,811 ounces of gold in 2024, on higher grades for both metals and higher recovery for gold. Red Chris exceeded its 2025 production guidance of 88 million pounds of copper and 86,000 ounces of gold for the calendar...

 PRESS RELEASE

Imperial Provides Update on Mount Polley 2025 Production and Explorati...

Imperial Provides Update on Mount Polley 2025 Production and Exploration VANCOUVER, British Columbia, Feb. 10, 2026 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (the “Company” or “Imperial”) (TSX:III) reports that 2025 metal production from Mount Polley mine was 30.715 million pounds of copper and 37,555 ounces of gold. The mine production exceeded the 2025 target of 25.0 – 27.0 million pounds for copper production and met the target of 35 - 40 thousand ounces for gold production. Mount Polley Mine – Production During 2025, 6,714,195 tonnes of ore were treated, which was flat compare...

Imperial Metals Corp: 1 director

A director at Imperial Metals Corp sold 20,000 shares at 0.000CAD and the significance rating of the trade was 75/100. Is that information sufficient for you to make an investment decision? This report gives details of those trades and adds context and analysis to them such that you can judge whether these trading decisions are ones worth following. Included in the report is a detailed share price chart which plots discretionary trades by all the company's directors over the last two years cle...

 PRESS RELEASE

Drilling at Mount Polley Intersects 11.0 Metres Grading 4.43% Copper, ...

Drilling at Mount Polley Intersects 11.0 Metres Grading 4.43% Copper, 1.53 g/t Gold and 41.7 g/t Silver VANCOUVER, British Columbia, Jan. 22, 2026 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (“Imperial” or the “Company”) (TSX:III) reports on the first diamond drill hole from the Mount Polley 2025 Phase 2 Diamond Drill Program which includes 11.0 metres with a grade of 4.43% copper, 1.53 g/t gold and 41.7 g/t silver. The nine hole Phase 2 program consisted of 3,718.3 metres. The Mount Polley 2025 Phase 2 program had three goals; to test a high-grade zone beneath the Wight Pit (See Fig...

 PRESS RELEASE

Imperial Provides Huckleberry Exploration Update

Imperial Provides Huckleberry Exploration Update VANCOUVER, British Columbia, Nov. 27, 2025 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (“Imperial” or the “Company”) (TSX:III) is pleased to report that all nine drillholes of the 2025 Huckleberry mine diamond drilling program, totalling 1,743 metres, intersected copper, molybdenum, silver, and gold mineralization. Drillhole MZ-25-1 intersected an elevated gold interval of 22.6 metres of 0.23 g/t gold from 73.7 to 96.3 metres. The Huckleberry mine (100% owned by Imperial) located in west-central British Columbia operated from 1997 to 2...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch