III. Imperial Metals

Imperial Reports Production Update for 2025 First Quarter and Petition Filed Relating to the Mount Polley Tailings Storage Facility Raise

Imperial Reports Production Update for 2025 First Quarter and Petition Filed Relating to the Mount Polley Tailings Storage Facility Raise

VANCOUVER, British Columbia, April 23, 2025 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (“Imperial”) (TSX:III) reports copper and gold production for the first quarter 2025 from Mount Polley and Red Chris mines. Imperial’s production was 15.8 million pounds copper and 17,120 ounces gold, with 8.9 million pounds copper and 10,621 ounces gold coming from Mount Polley and 6.9 million pounds copper and 6,499 ounces gold from its 30% share of Red Chris mine production. Both copper and gold production were up compared with the first quarter of 2024, with copper production up 28% and gold production up 33%.

Mount Polley metal production (100%) for the first quarter of 2025 was 8.904 million pounds copper and 10,621 ounces gold, compared to 7.355 million pounds copper and 10,009 ounces gold produced during the first quarter of 2024.

Mount Polley Mine Production Three Months Ended March 31
  20252024
Ore milled - tonnes 1,721,7691,671,505
Ore milled per calendar day - tonnes 19,13118,368
Grade %  - copper 0.2820.251
Grade g/t  - gold 0.2750.282
Recovery %  - copper 83.379.4
Recovery %  - gold 69.866.0
Copper - million pounds 8.904 7.355
Gold - ounces 10,621 10,009



Mill throughput was up 3%, with 1,721,769 million tonnes being treated compared with 1.671 million tonnes treated in the first quarter of 2024. Copper production in the first quarter 2025 was up 21% because of increased grade, recovery and throughput compared to first quarter 2024. Gold production in the first quarter 2025 was up 6% with increased recovery and throughput offsetting lower gold grades compared to first quarter 2024.

Most of the mill feed for the first quarter of 2025 came from the material mined from near the bottom of the Phase 4 pit. Stripping for the Phase 5 pushback of the Springer pit continued with approximately 3,584,917 million tonnes of waste from this pushback mined in the first quarter of 2025. Approximately 1,806,705 tonnes of non-acid generating rock from the Phase 5 stripping was hauled to the tailing facility to buttress the tailings storage embankment.

Red Chris metal production (100%) for the first quarter of 2025 was 23.126 million pounds copper and 21,663 ounces gold, compared to 16.660 million pounds copper and 9,507 ounces gold produced during the same quarter of 2024.

Red Chris Mine Production (100%)  Three Months Ended March 31
   20252024
Ore milled - tonnes                    2,049,4752,100,354
Ore milled per calendar day - tonnes  22,52223,081
Grade %  - copper  0.620.43
Grade g/t  - gold  0.540.26
Recovery %  - copper  82.683.4
Recovery %  - gold  60.553.6
Copper - million pounds  23.12616.660
Gold - ounces  21,6639,507



The 2025 first quarter Red Chris copper production was up 39% and gold production was up 128% compared to the first quarter of 2024. The increase in copper production was a result of a 44% increase in copper grade (0.62% vs 0.43%) offset by slightly lower recovery and throughput. Gold production in the first quarter of 2025 at Red Chris was up as a result of much better gold grade in the mill feed (0.54 g/t gold versus 0.26 g/t gold) and better gold recovery (60.5% versus 53.6%) compared to the same quarter last year.

Brian Kynoch, P. Eng., Imperial’s President has reviewed the above disclosures contained in this news release and is the designated Qualified Person as defined by National Instrument 43-101 (“NI 43-101”).

Xatśūll Petition

Imperial also announces that Xatśūll First Nation (“Xatśūll”) has recently filed a Petition in the Supreme Court of British Columbia, naming the Province of British Columbia’s Minister of Mining and Critical Minerals, Minister of Environment and Parks, Deputy Chief Permitting Officer, Major Mines Offices, and Imperial’s wholly-owned subsidiary, Mount Polley Mining Corporation (“MPMC”).

Xatśūll is seeking a judicial review of two provincial decisions that authorize MPMC to increase the height of the dam at the Tailings Storage Facility. Xatśūll alleges that the provincial decision-makers approved this work using a process that did not include what it considers to be a legally required environmental assessment, and that the decisions were made in breach of alleged duties owed to Xatśūll as an Indigenous people. Xatśūll is seeking the decisions be declared without effect, or alternatively, be re-considered by the provincial decision-makers. The decisions were made after a lengthy and transparent process that included Xatśūll, and using a process that has been consistently used with respect to decisions regarding the Mount Polley Mine.

Both Imperial and MPMC remain committed to building and maintaining strong relationships with Indigenous communities. Throughout the permitting process, they have actively engaged with Xatśūll and the Williams Lake First Nation, including providing funding for independent reviews and implementing recommendations to enhance operations. The Williams Lake First Nation and MPMC have maintained a positive working relationship for over a decade, formalized through a Participation Agreement which was renewed in 2022, and the Williams Lake First Nation are supportive of the provincial decisions and Mount Polley’s current permitting applications under review. Imperial and MPMC will continue to prioritize meaningful engagement and work alongside Indigenous communities to support sustainable and responsible development.

---

About Imperial

Imperial is a Vancouver based exploration, mine development and operating company with holdings that include the Mount Polley mine (100%), the Huckleberry mine (100%), and the Red Chris mine (30%). Imperial also holds a portfolio of 23 greenfield exploration properties in British Columbia.

Company Contacts

Brian Kynoch | President | 604.669.8959

Darb S. Dhillon | Chief Financial Officer | 604. 669.8959

Cautionary Note Regarding Forward-Looking Statements

Certain information contained in this news release are not statements of historical fact and are “forward-looking” statements. Forward-looking statements relate to future events or future performance and reflect Imperial management’s expectations or beliefs regarding future events and include, but are not limited to, statements regarding Imperial’s expectations and timing with respect to the anticipated progress of the judicial review process; the judicial review process taking longer than anticipated; the possibility that the outcome of the judicial review could result in material changes to the provincial permitting process; the potential for the injunction to restrict both construction and production activities for an extended period or indefinitely; the Company’s and MPMC’s expectations regarding their relationships with Indigenous communities, including Xatśūll; expectations regarding the ongoing engagement with Xatśūll and other Indigenous communities during the permitting process; and other risks outlined in statements made by Imperial from time to time in the filings made by Imperial with securities regulators. Imperial disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events, or otherwise, except as otherwise required by applicable securities legislation.

In certain cases, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "outlook", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" or the negative of these terms or comparable terminology. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Imperial to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements.

In making the forward-looking statements in this news release, Imperial has applied certain factors and assumptions that are based on information currently available to Imperial as well as Imperial’s current beliefs and assumptions. These factors and assumptions and beliefs and assumptions include, the risk factors detailed from time to time in Imperial’s interim and annual financial statements and management’s discussion and analysis of those statements, all of which are filed and available for review on SEDAR+ at Although Imperial has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, imperialmetals.com events or results not to be as anticipated, estimated or intended, many of which are beyond Imperial’s ability to control or predict. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements and all forward-looking statements in this news release are qualified by these cautionary statements.



EN
23/04/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Imperial Metals

 PRESS RELEASE

Imperial Reports Production Update for 2025 First Quarter and Petition...

Imperial Reports Production Update for 2025 First Quarter and Petition Filed Relating to the Mount Polley Tailings Storage Facility Raise VANCOUVER, British Columbia, April 23, 2025 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (“Imperial”) (TSX:III) reports copper and gold production for the first quarter 2025 from Mount Polley and Red Chris mines. Imperial’s production was 15.8 million pounds copper and 17,120 ounces gold, with 8.9 million pounds copper and 10,621 ounces gold coming from Mount Polley and 6.9 million pounds copper and 6,499 ounces gold from its 30% share of Red Chris m...

 PRESS RELEASE

Imperial Reports 2024 Financial Results

Imperial Reports 2024 Financial Results VANCOUVER, British Columbia, March 26, 2025 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (the “Company”) (TSX:III) reports financial results for its fiscal year ended December 31, 2024. “Operationally, the 2024 year was aligned with guidance. Copper production was higher at Mount Polley driven largely by higher through-put and copper grades, and both copper and gold production were higher at Red Chris due to higher copper and gold grades,“ said Brian Kynoch, President. “Consolidated production totalled 61,296,423 pounds copper and 57,051 ounces ...

 PRESS RELEASE

Imperial Provides Update on Red Chris 2024 Production and Production G...

Imperial Provides Update on Red Chris 2024 Production and Production Guidance for 2025 VANCOUVER, British Columbia, Feb. 20, 2025 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (the “Company” or “Imperial”) (TSX:III) reports that 2024 metal production from Red Chris (100% basis) was 85,320,618 pounds of copper and 59,811 ounces of gold, up from 57,051,467 pounds of copper and 46,046 ounces of gold in 2023, on higher grades and recoveries for both metals. Red Chris met its 2024 production guidance of 85.0 million pounds of copper and 57,000 ounces of gold for the calendar year 2024. Im...

 PRESS RELEASE

Imperial Provides Update on Mount Polley

Imperial Provides Update on Mount Polley VANCOUVER, British Columbia, Jan. 29, 2025 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (the “Company” or “Imperial”) (TSX:III) reports that 2024 metal production from Mount Polley was 35.7 million pounds of copper and 39,108 ounces of gold. The mine met its targets of 34–37 million pounds for copper production and 37-41 thousand ounces for gold production. Red Chris production will be released when the reconciled information is received from Newmont Corporation. Mount Polley Mine – Production During the fourth quarter 1,660,937 t...

 PRESS RELEASE

Imperial Metals and Mount Polley Served with Notice of Charges Allegin...

Imperial Metals and Mount Polley Served with Notice of Charges Alleging Violations of the Fisheries Act VANCOUVER, British Columbia, Dec. 09, 2024 (GLOBE NEWSWIRE) -- Imperial Metals Corporation (the “Company”) (TSX:III) and its subsidiary Mount Polley Mining Corporation, along with engineering firm Wood Canada Limited, have been charged with alleged violations of the federal Fisheries Act, arising from the failure of the Tailings Storage Facility at the Mount Polley Mine more than 10 years ago in August of 2014. The charges are outlined in an indictment filed with the Supreme Court of Br...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch