KNF1L Klaipedos Nafta AB

AB Klaipėdos nafta unaudited financial information for 2022

AB Klaipėdos nafta unaudited financial information for 2022

AB Klaipėdos nafta (hereinafter – KN, the Company) announces the unaudited consolidated (hereinafter – the Group) and separate financial results for 2022.

Key financial indicators:

EUR millionsGroupCompany
 2022202120222021
Revenue77.861.874.758.6
EBITDA35.526.134.224.6
Net profit (loss)(5.5)(64.0)(6.3)(64.9)
Adjusted net profit (loss)9.3(47.2)8.5(48.1)

Management comment:

Revenue from oil terminals for 2022 amounts to EUR 27.8 million and is higher by 29.9% compared to 2021 (EUR 21.4 million). The increase of revenue was due to 16.9% or 616 thousand tones higher transhipment of oil products. Transhipment quantities in the Company's oil terminals were affected by continuous initiatives to explore new transhipment routes which allowed KN to become a part of the logistics chain of fuel supply to new customers in southwest directions. Also, in 2022 KN oil terminal was in demand as oil products import hub, notably fuel oil, which – in response to all-time highs of gas prices - was used as alternative heating generation fuel source in Vilnius city heating infrastructure at the start of the winter season of 2022.  

Regulated LNG activities revenue for 2022 reached EUR 44.6 million and is higher by EUR 9.8 million or 28.2% compared to 2021 (EUR 34.8 million). The main reasons: (1) higher regasification revenue by EUR 26.7 million due to increased demand and regasification tariff from 0.41 EUR/MWh to 1.19 EUR/MWh; (2) received revenue related to the natural gas consumer’s liability for previous periods after the court decision in amount of EUR 1.1 million; (3) higher revenue from AB Amber Grid by EUR 0.5 million due to recalculated actual consumption capacities of previous period (2022 – EUR 1.1 million, 2021 – EUR 0.6 million); (4) lower revenue from the fixed part of LNG regasification service fee by EUR 18.5 million due to implemented LNG terminal capacity allocation and tariffication model when KN part in security supplement from May 2022 was decreased to 0 EUR/MWh/day/year.

Revenue from commercial LNG activities for 2022 amounts to EUR 5.4 million and is lower by 3.5% compared to 2021 (EUR 5.6 million). Commercial LNG activities consist of business development projects including LNG terminal operator services provided at the Port of Açu terminal in Brazil and LNG reloading station in Klaipėda.

During 2022, the same as during 2021, the Group‘s and the Company‘s net profit (loss) was significantly affected by unrealized currency exchange losses and by the reduction of LNG security supplement from 1 January 2020 by EUR 26.8 million per annum. The unrealized impact of exchange rates arose from the 1 January 2019 under the requirements of IFRS 16 “Lease”, according to which the Company recognizes finance lease obligations and the major part of them is denominated in US dollars. Whereas all US dollar denominated lease liabilities relate to LNG terminal, the effect of unrealized exchange rate is reflected in the regulated segment.

Enclosed:

  1. Condensed Consolidated and Separate Financial Statements of AB Klaipėdos nafta for 2022.
  2. Presentation of the unaudited financial results of the Group for 2022.



Mindaugas Kvekšas, Chief Financial Officer,



Attachments



EN
27/02/2023

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Klaipedos Nafta AB

 PRESS RELEASE

The Letter of Expectations of the Majority Shareholder has been update...

The Letter of Expectations of the Majority Shareholder has been updated Please be informed that the Ministry of Energy of the Republic of Lithuania, which owns 72,47 percent of shares of AB KN Energies, has issued a Letter of Expectations outlining strategic directions and performance goals for the Company and its subsidiaries. This document serves as a guiding framework for short, medium, and long-term planning and is aligned with national energy policy and corporate governance standards. Strategic Priorities Energy Security: Ensure uninterrupted operation of the Klaipėda LNG terminal un...

 PRESS RELEASE

Atnaujintas daugumos akcininko lūkesčių raštas

Atnaujintas daugumos akcininko lūkesčių raštas Informuojame, kad Lietuvos Respublikos energetikos ministerija, valdanti 72,47 procentus AB „KN Energies“ akcijų, pateikė lūkesčių raštą, kuriame išdėstytos strateginės kryptys ir veiklos tikslai, taikomi bendrovei ir jos dukterinėms įmonėms. Šis dokumentas yra gairės trumpalaikiam, vidutinės trukmės ir ilgalaikiam planavimui, atitinkančios nacionalinę energetikos politiką ir gerosios valdysenos standartus. Strateginiai prioritetai Energetinis saugumas: užtikrinti nepertraukiamą Klaipėdos SGD terminalo veiklą iki 2044 m., saugoti valstybės s...

 PRESS RELEASE

Notice on the convened Extraordinary General Meeting of Shareholders o...

Notice on the convened Extraordinary General Meeting of Shareholders of AB “KN Energies” We hereby inform you that on the initiative and by the decision of the Board of AB “KN Energies”, legal entity code 110648893, registered address at Burių str. 19, Klaipėda (hereinafter – the Company), an Extraordinary General Meeting of Shareholders of the Company was convened on 18 August 2025 at 1:00 p.m. The meeting was held in the administrative premises of the Company at J. Janonio str. 6B, Klaipėda. Extraordinary General Meeting of Shareholders of the Company, held on 18 August 2025, adopted the...

 PRESS RELEASE

Pranešimas apie įvykusį AB „KN Energies“ neeilinį visuotinį akcininkų ...

Pranešimas apie įvykusį AB „KN Energies“ neeilinį visuotinį akcininkų susirinkimą Pranešame, kad AB „KN Energies“, juridinio asmens kodas 110648893, registruota buveinė adresu Burių g. 19, Klaipėda (toliau – Bendrovė), valdybos iniciatyva ir sprendimu 2025 m. rugpjūčio 18 d. 13:00 val. buvo sušauktas Bendrovės neeilinis visuotinis akcininkų susirinkimas. Susirinkimas įvyko adresu J. Janonio g. 6B, Klaipėda, Bendrovės administracijos patalpose. 2025 m. rugpjūčio 18 d. Bendrovės neeiliniame visuotiniame akcininkų susirinkime priimti šie sprendimai:       1.      Dėl AB „KN Energies“ stebėto...

 PRESS RELEASE

500 kW solar power plant to be installed at KN Energies’ Klaipėda liqu...

500 kW solar power plant to be installed at KN Energies’ Klaipėda liquid energy products terminal On 14 August 2025, AB KN Energies and UAB Elmitra, the contractor selected through a public procurement procedure, signed a contract for the installation of a 500 kW solar power plant at the Klaipėda liquid energy products terminal.  The project covers all installation stages – from design to grid connection. Photovoltaic modules will be installed on the rooftops of buildings and throughout the terminal’s territory.  It is estimated that the plant will generate nearly half a gigawatt-hour of...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch