On 18 April 2024, PS MB.MEE, part of AS Merko Ehitus group, and SIA SP Venta, which sole shareholder and financier of the project development is UAB Ignitis renewables, entered into a contract to for the construction of solar panel power plant located in Vārme parish, Kuldīga district, Latvia.

The works include installation of solar panels with total capacity of 93.5 MW DC, 18 medium-voltage power stations, 232 combiner boxes, irradiance sensors, weather stations, construction of access roads, drainage systems, construction and connection of medium voltage cables, testing and commissioning of the solar power plant.

The value of the contract is approximately EUR 20 million, plus value added tax. Construction works are scheduled to be completed in August 2025.

PS MB.MEE is a joint venture established by SIA Merko Būve as a managing partner and AS Merko Ehitus Eesti, both fully owned subsidiaries of AS Merko Ehitus group.

Additional information: Board Member of SIA Merko Būve, Mr. Roberts Rēboks, e-mail: .

Urmas Somelar

Head of Finance

AS Merko Ehitus



AS Merko Ehitus () group companies develop real estate and construct buildings and infrastructure. We create a better living environment and build the future. We operate in Estonia, Latvia, Lithuania and Norway. As at the end of 2023, the group employed 635 people, and the group’s revenue for 2023 was EUR 466 million.



EN
19/04/2024

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Merko Ehitus (New)

 PRESS RELEASE

Changes in the management of groups’ Latvian subsidiaries

Changes in the management of groups’ Latvian subsidiaries The board of AS Merko Ehitus decided to appoint Egija Smila as the country head for the group's Latvian subsidiaries for a period of three years, with the term of authority beginning on 1 May 2024. The term of office of Andris Bišmeistars, the previous country head of the group's Latvian subsidiaries, ended on 31 March 2024 due to his resigning from the group. Ivo VolkovChairman of the Management BoardAS Merko EhitusPhone: E-mail: AS Merko Ehitus () group companies develop real estate and construct buildings and infrastructure...

 PRESS RELEASE

Muudatused kontserni Läti tütarettevõtete juhtimises

Muudatused kontserni Läti tütarettevõtete juhtimises ASi Merko Ehitus juhatus otsustas nimetada kolmeaastaseks perioodiks kontserni Läti tütarettevõtete juhiks Egija Smila, volituse tähtaja algusega 1. mai 2024. Senise kontserni Läti tütarettevõtete juhi Andris Bišmeistarsi ametiaeg lõppes 31. märtsil 2024 seoses tema lahkumisega kontsernist. Ivo VolkovJuhatuse esimeesAS Merko EhitusTelefon: E-post: AS Merko Ehitus () kontserni ettevõtted arendavad kinnisvara ning ehitavad hooneid ja infrastruktuuri. Loome paremat elukeskkonda ja ehitame tulevikku. Tegutseme Eestis, Lätis, Leedus ja N...

 PRESS RELEASE

Launch of the sixth stage of the Uus-Veerenni residential project (Tal...

Launch of the sixth stage of the Uus-Veerenni residential project (Tallinn, Estonia) OÜ Merko Kodud, part of AS Merko Ehitus group, has decided to launch the construction of the sixth stage of the Uus-Veerenni residential development project in the city centre of Tallinn. As part of this, an apartment building with a total of 63 apartments will be completed in the summer of 2026. The 8-storey energy class A building at Tiiu 14 () will have apartments ranging in size from 35 to 115 square metres, with prices starting from 4,744 euros per square metre. The apartments will have readiness for ...

 PRESS RELEASE

Construction contract in Latvia (solar panel power plant in Vārme pari...

Construction contract in Latvia (solar panel power plant in Vārme parish) On 18 April 2024, PS MB.MEE, part of AS Merko Ehitus group, and SIA SP Venta, which sole shareholder and financier of the project development is UAB Ignitis renewables, entered into a contract to for the construction of solar panel power plant located in Vārme parish, Kuldīga district, Latvia.The works include installation of solar panels with total capacity of 93.5 MW DC, 18 medium-voltage power stations, 232 combiner boxes, irradiance sensors, weather stations, construction of access roads, drainage systems, constru...

 PRESS RELEASE

Ehitusleping Lätis (päikeseelektripark Vārme vallas)

Ehitusleping Lätis (päikeseelektripark Vārme vallas) 18. aprillil 2024 sõlmisid AS Merko Ehitus kontserni kuuluv PS MB.MEE ja SIA SP Venta, mille ainuomanik ja projektifinantseerija on UAB Ignitis Renewables, lepingu päikeseelektripargi ehitamiseks Lätis, Kuldīga maakonnas, Vārme vallas.Tööd hõlmavad päikesepaneelide, alalisvoolu koguvõimsusega 93,5 MW, 18 keskpinge alajaama, 232 ühenduskilbi, kiirgusandurite ja ilmajaama paigaldamist ning juurdepääsuteede, drenaažisüsteemide ehitamist, keskpingekaabelduse ehitamist ja ühendamist, päikeseelektrijaama katsetamist ja kasutuselevõttu. ...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch