PRS Prosafe

Prosafe SE: Operational and financial update Q3 2020

Prosafe SE: Operational and financial update Q3 2020

Operational

The fleet utilisation rate in the third quarter of 2020 was 16.4 per cent (Q3 2019: 48.2 per cent).



Prosafe has been in discussions with several clients about existing contracts in light of Covid-19 and the oil price collapse, and has managed to protect its order book by moving contracts from 2020 to 2021 with some further extensions. Please see the update per vessel below.



Prosafe continues to claim full contract value from EnQuest relating to the planned Thistle project for the Safe Zephyrus.



Prosafe has agreed with Shell to defer and amend the contract for the Safe Zephyrus at the Shearwater platform. The revised firm duration of the contract is 115 days and the contract is scheduled to commence in March 2021. Shell has the option of adding 30 or 45 days to the front end, resulting in a possible earlier commencement date. In addition, Shell retains the option to extend the contract after the firm duration by up to 30 days. The Safe Zephyrus is currently laid up at Averøy yard in Norway preparing to conduct her five-yearly special periodic survey.



Safe Caledonia is currently laid up in the UK. The vessel is scheduled to commence a 162-day contract with a 30-day option for Total at Elgin in the UK from Q1 2021. This contract was originally scheduled to commence in 2020.



Safe Eurus has been providing safety and maintenance support to Petrobras during a three-year contract since November 2019. From April 2020, the Safe Eurus was suspended for 120 days at zero rate. The vessel has been on standby rate since early August and recommenced operations on 24 September 2020.



The original three-year and 222-day firm contract for the Safe Notos that was due to complete in July 2020 was suspended for 120 days at zero rate from April 2020. The vessel was back on standby rate in early August 2020 and resumed operations in early October 2020.



Safe Concordia was idle in the quarter and is laid up in Brazil. Safe Scandinavia, Safe Boreas and Regalia were idle in the quarter and are laid up in Norway. Regalia has been marketed for recycling with possible commencement of recycling in Q1 2021.



Although the impact from Covid-19 on the macro environment has been challenging, the company has successfully implemented proper safety measurements at workplaces and vessels to protect people and assets, as well as several cost-saving initiatives to protect liquidity.



Financial

Please refer to separate press release from 1 October 2020 regarding the ongoing discussion with lenders about a long-term financial solution for the company.



Prosafe is a leading owner and operator of semi-submersible accommodation vessels. The company is listed on the Oslo Stock Exchange with ticker code PRS. For more information, please refer to  



Stavanger, 20 October 2020

Prosafe SE



For further information, please contact:



Jesper K. Andresen, CEO

Phone: /  155



Stig Harry Christiansen, Deputy CEO and CFO

Phone: /  813



This information is subject to the disclosure requirements pursuant to Section 5-12 the Norwegian Securities Trading Act

EN
20/10/2020

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Prosafe

 PRESS RELEASE

Prosafe SE: Reese McNeel appointed as CEO in Prosafe SE

Prosafe SE: Reese McNeel appointed as CEO in Prosafe SE Oslo, 6 November 2025 - The Board of Directors of Prosafe has appointed Reese McNeel as permanent chief executive officer (CEO) of Prosafe. Reese will continue to perform the CFO duties until a successor is appointed. Reese has more than 20 years of leadership experience from the offshore energy industry and publicly listed companies, including executive management and CEO level tenure at Atlantica Tender Drilling Ltd. and Sevan Marine ASA. He has already demonstrated his strong leadership and dedication to Prosafe as interim CEO sin...

ABGSC Energy Research ... (+7)
  • ABGSC Energy Research
  • Daniel Vårdal Haugland
  • John Olaisen
  • Lars Trongaard Brattli
  • Martin Mauseth
  • Njål Kleiven
  • Stian Wibstad
 PRESS RELEASE

Prosafe SE: Safe Caledonia Extended at Captain

Prosafe SE: Safe Caledonia Extended at Captain 30 October 2025 - Ithaca Energy (UK) Limited (‘Ithaca’) has exercised two (2) weeks of options for the Safe Caledonia to continue providing accommodation support at the Captain field in the UK sector of the North Sea through to mid-December 2025. Ithaca has a further ten (10) weeks of options available.Total value of the contract extension is approximately USD 1.8 million.Prosafe is a leading owner and operator of semi-submersible accommodation vessels. The company is listed on the Oslo Stock Exchange with ticker code PRS. For more information,...

 PRESS RELEASE

Prosafe SE: Invitation to Q3 2025 results and webcast on 13 November

Prosafe SE: Invitation to Q3 2025 results and webcast on 13 November 30 October 2025 - Prosafe SE will release its third quarter 2025 results on 13 November 2025 at 7:00 a.m. CET. The quarterly earnings release and presentation will be made available on and Prosafe’s website, . Reese McNeel, Interim CEO and CFO, will on the same day at 10:00 a.m. CET host a webcast and Q&A, which can be followed at . It will be possible to ask questions by using the Q&A tool embedded in the webcast. A replay of the webcast will be made available on Prosafe’s website shortly after the presentation.Prosaf...

 PRESS RELEASE

Prosafe SE: Operational update – September 2025

Prosafe SE: Operational update – September 2025 16 October 2025 - Fleet utilisation for September 2025 was 100% and utilisation for the third quarter of 2025 was 86%. With Safe Boreas on standby rate from 1 September 2025, all Prosafe vessels are currently in operation, supporting increased earnings. In Brazil, Safe Eurus, Safe Notos, and Safe Zephyrus operated at full capacity, with average 99% commercial uptime in September and 99% in the quarter. Safe Caledonia has maintained 100% commercial uptime at the Captain Field in the UK since contract commencement in June 2025. There are up t...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch