SOC Subsea 7 S.A.

Subsea7 awarded contract offshore Norway

Subsea7 awarded contract offshore Norway

Luxembourg – 31 March 2025 - Subsea 7 S.A. (Oslo Børs: SUBC, ADR: SUBCY) today announced the award of a sizeable1 contract by Equinor as technical service provider (TSP) for the Northern Lights Phase 2 project, offshore Norway.

Subsea7’s scope includes engineering, procurement, construction and installation of a five kilometre CO2 pipeline, as well as installation of integrated satellite structures, umbilicals, tie-in and pre-commissioning activities.

Project management and engineering will commence immediately at Subsea7’s office in Stavanger, Norway. Fabrication of the pipeline will take place at Subsea7’s spoolbase at Vigra, Norway and offshore operations will be executed in 2026 and 2027.

Erik Femsteinevik, Vice President for Subsea7 Norway said: “We are excited to continue our collaboration with Equinor TSP and the Northern Lights’ owners Equinor, Shell and TotalEnergies on phase 2 of this ambitious and pioneering project. We look forward to working together to increase the development’s carbon storage capacity to a minimum of five million tonnes per year, and to support the continued development of a new value chain for Norway and Europe.”

Northern Lights phase 2 is enabled by a grant from the Connecting Europe Facility for Energy (CEF Energy) funding scheme. 

  1. Subsea7 defines a sizeable contract as being between $50 million and $150 million.



*******************************************************************************

Subsea7 is a global leader in the delivery of offshore projects and services for the evolving energy industry, creating sustainable value by being the industry’s partner and employer of choice in delivering the efficient offshore solutions the world needs.

Subsea7 is listed on the Oslo Børs (SUBC), ISIN LU0075646355, LEI 222100AIF0CBCY80AH62.

*******************************************************************************

Contact for investment community enquiries:

Katherine Tonks

Investor Relations Director

Tel 8

Contact for media enquiries:

Jan Roger Moksnes

Communications Manager

Tel



Forward-Looking Statements: This document may contain ‘forward-looking statements’ (within the meaning of the safe harbour provisions of the U.S. Private Securities Litigation Reform Act of 1995). These statements relate to our current expectations, beliefs, intentions, assumptions or strategies regarding the future and are subject to known and unknown risks that could cause actual results, performance or events to differ materially from those expressed or implied in these statements. Forward-looking statements may be identified by the use of words such as ‘anticipate’, ‘believe’, ‘estimate’, ‘expect’, ‘future’, ‘goal’, ‘intend’, ‘likely’ ‘may’, ‘plan’, ‘project’, ‘seek’, ‘should’, ‘strategy’ ‘will’, and similar expressions. The principal risks which could affect future operations of the Group are described in the ‘Risk Management’ section of the Group’s Annual Report and Consolidated Financial Statements. Factors that may cause actual and future results and trends to differ materially from our forward-looking statements include (but are not limited to): (i) our ability to deliver fixed price projects in accordance with client expectations and within the parameters of our bids, and to avoid cost overruns; (ii) our ability to collect receivables, negotiate variation orders and collect the related revenue; (iii) our ability to recover costs on significant projects; (iv) capital expenditure by oil and gas companies, which is affected by fluctuations in the price of, and demand for, crude oil and natural gas; (v) unanticipated delays or cancellation of projects included in our backlog; (vi) competition and price fluctuations in the markets and businesses in which we operate; (vii) the loss of, or deterioration in our relationship with, any significant clients; (viii) the outcome of legal proceedings or governmental inquiries; (ix) uncertainties inherent in operating internationally, including economic, political and social instability, boycotts or embargoes, labour unrest, changes in foreign governmental regulations, corruption and currency fluctuations; (x) the effects of a pandemic or epidemic or a natural disaster; (xi) liability to third parties for the failure of our joint venture partners to fulfil their obligations; (xii) changes in, or our failure to comply with, applicable laws and regulations (including regulatory measures addressing climate change); (xiii) operating hazards, including spills, environmental damage, personal or property damage and business interruptions caused by adverse weather; (xiv) equipment or mechanical failures, which could increase costs, impair revenue and result in penalties for failure to meet project completion requirements; (xv) the timely delivery of vessels on order and the timely completion of ship conversion programmes; (xvi) our ability to keep pace with technological changes and the impact of potential information technology, cyber security or data security breaches; (xvii) global availability at scale and commercially viability of suitable alternative vessel fuels; and (xviii) the effectiveness of our disclosure controls and procedures and internal control over financial reporting. Many of these factors are beyond our ability to control or predict. Given these uncertainties, you should not place undue reliance on the forward-looking statements. Each forward-looking statement speaks only as of the date of this document. We undertake no obligation to update publicly or revise any forward-looking statements, whether as a result of new information, future events or otherwise.

This information is considered to be inside information pursuant to the EU Market Abuse Regulation and is subject to the disclosure requirements pursuant to Section 5-12 the Norwegian Securities Trading Act.

This stock exchange release was published by Katherine Tonks, Investor Relations, Subsea7, on 31 March 2025 at 12:15 CET.

Attachment



EN
31/03/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Subsea 7 S.A.

ABGSC Energy Research ... (+6)
  • ABGSC Energy Research
  • Daniel Vårdal Haugland
  • John Olaisen
  • Njål Kleiven
  • Oliver Dunvold
  • Stian Wibstad
 PRESS RELEASE

Subsea7 awarded contract offshore Norway

Subsea7 awarded contract offshore Norway Luxembourg – 31 March 2025 - Subsea 7 S.A. (Oslo Børs: SUBC, ADR: SUBCY) today announced the award of a sizeable1 contract by Equinor as technical service provider (TSP) for the Northern Lights Phase 2 project, offshore Norway. Subsea7’s scope includes engineering, procurement, construction and installation of a five kilometre CO2 pipeline, as well as installation of integrated satellite structures, umbilicals, tie-in and pre-commissioning activities. Project management and engineering will commence immediately at Subsea7’s office in Stavanger, No...

 PRESS RELEASE

Subsea 7 S.A. announces proposed nominations to the Company’s Board of...

Subsea 7 S.A. announces proposed nominations to the Company’s Board of Directors Luxembourg – 25 March 2025 – Subsea 7 S.A. (Oslo Børs: SUBC, ADR: SUBCY) today announced that at the AGM on 8 May 2025, the Board of Directors will ask shareholders to approve the following nominations to the Board of Directors: The election as Independent Director of Ms Lucia de Andrade The re-election as Independent Directors of Mr Eldar Sætre and Ms Elisabeth Proust van Heeswijk The re-election as Directors of Ms Louisa Siem and Treveri S.à r.l., a Luxembourg company, with Mr Kristian Siem, its 100% owner, ...

 PRESS RELEASE

Subsea 7 S.A. Notice of Annual General Meeting and Extraordinary Gener...

Subsea 7 S.A. Notice of Annual General Meeting and Extraordinary General Meeting Luxembourg – 25 March 2025 – Subsea 7 S.A. (Oslo Børs: SUBC, ADR: SUBCY) today published and distributed to eligible holders of Common Shares and American Depositary Receipts the Notice of Meeting and supporting materials for the Annual General Meeting of Shareholders (the AGM) and the Extraordinary General Meeting of Shareholders (the EGM). The AGM is scheduled to take place at 15:00 (local time) on 8 May 2025 at the Company's registered office, 412F, route d'Esch, L-1471 Luxembourg and the EGM will take pla...

 PRESS RELEASE

Subsea 7 S.A. - 1Q25 earnings call notification

Subsea 7 S.A. - 1Q25 earnings call notification Luxembourg –24 March 2025 – Subsea 7 S.A. (Oslo Børs: SUBC, ADR: SUBCY) will publish its first quarter 2025 results for the period ended 31 March 2025 on Wednesday 30 April 2025 at 08:00 CET. A conference call and simultaneous webcast for the investment community will be held on Wednesday 30 April 2025 at 12:00 UK / 13:00 CET. From 08:00 CET the results announcement and the presentation to be reviewed during the conference call and webcast will be available on the Subsea7 website: Conference call registration:Phone: -conf.media-server.com/...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch