Oslo, 18 August 2023: In the second quarter 2023, Scatec’s proportionate revenues jumped to NOK 5.87 billion (932), with an all-time high EBITDA of NOK 1.38 billion (517) compared to the second quarter last year. Power production EBITDA was NOK 959 million (617) and the company reported development and construction revenues of NOK 4.59 billion, with a gross margin of 12 percent.

“It has been a busy quarter with a lot of advancement for our business and I am pleased to see construction activities on all three of our large projects continue to progress according to plan. During the quarter, we continued to execute on our strategy that we presented to the market almost a year ago. We closed the NOK 546 million divestment of the Upington solar plants in South Africa and reached financial close for the NOK 2.9 billion Grootfontein solar project in the Western Cape of South Africa. We also maintained our focus on efficiency initiatives and finalised a major part of our cost control programme launched in May this year,” says Scatec CEO Terje Pilskog.

Power Production and Development & Construction

Power Production was 873 GWh (916) and proportionate revenues in the Power Production segment increased by NOK 352 million to NOK 1.17 billion compared to the same quarter last year, mainly driven by the NOK 315 million gain related to the Upington solar power plant sale, NOK 76 million in increased revenues in Ukraine and foreign currency effects.  

The sharp increase in development and construction revenues in the second quarter was due to high accumulated progress of the projects under construction in South Africa, Brazil, and Pakistan. During the first half of 2023 Scatec discontinued development of projects in Brazil, Oman and Madagascar and recognised an impairment charge of NOK 55 million.

Delivering on strategy

During the quarter, Scatec continued to progress on several strategic initiatives, including the divestment of the Upington plants and further high grading of the pipeline with focus on project location, timeline, maturity, and value creation. In addition, Scatec implemented the efficiency programme with a target to reduce operating expenses by NOK 150 million from the first quarter 2024 compared to the first quarter 2023 level.

After the end of the second quarter, Scatec signed an agreement to sell its 52.5% equity share in the 40 MW Mocuba solar power plant in Mozambique. Also, in July 2023, Scatec reached a major milestone by signing an agreement to raise USD 102 million in funding for Release from Climate Fund Managers to accelerate its growth ambitions.

“We are pleased with the progress we have made during the last few months. We have reached some key milestones and now look forward to continuing delivering on our strategy,” adds Pilskog. “At the heart of our strategy is our role as a long-term player in the markets where we operate – developing, building, owning, and operating renewable energy plants with 4.4 GW in operation and under construction across four continents.”

Impairment, sales process, and consolidated profit 

Scatec recognised an impairment charge of NOK 350 million for its joint venture project with Equinor in Argentina in the quarter. The project was partly funded with a bridge loan that has not been possible to re-finance due to the worsening political and economic situation. Therefore, a sales process has been initiated, and current offers are significantly below the total book value of the project (further details in the quarterly report on p. 5).

Consolidated revenues for the second quarter were NOK 1,230 million (836), while EBIT was NOK 686 million (336) and profit attributable to Scatec NOK 302 million (-97).

ESG performance

Scatec published its first Transparency Act Statement detailing the Company’s governance around human rights, approach to due diligence, salient human rights risks within its own operations and supply chain, and work undertaken during 2022. In addition, Scatec continued its preparatory work towards the requirements of the EU’s Corporate Sustainability Reporting Directive (CSRD), applicable to the Company from FY 2024.

Outlook

The full year 2023 EBITDA estimate has increased by NOK 250 million from 2.85 – 3.15 billion to NOK 3.1 – 3.4 billion, reflection actual second quarter performance, including the gain from the sale of Upington, and revised estimates for the second half of 2023.

Additional information

Proportionate historical financial information on a country-by-country level is attached to the stock exchange notice.

A presentation of the results, followed by a Q&A session will be held at Scatec’s headquarters at Skøyen Atrium III (1st floor), Askekroken 11, 0277 Oslo, today at 09:00 am CEST. You can also follow the presentation and Q&A session from our website, or this direct link: .

For further information, please contact:

For analysts and investors: Andreas Austrell, VP Investor Relations, phone: ,  

For media: Meera Bhatia, SVP Communications & Government Affairs, phone: , 

About Scatec  

Scatec is a leading renewable energy solutions provider, accelerating access to reliable and affordable clean energy emerging markets. As a long-term player, we develop, build, own, and operate renewable energy plants, with 4.4 GW in operation and under construction across four continents today. We are committed to grow our renewable energy capacity, delivered by our passionate employees and partners who are driven by a common vision of ‘Improving our Future’. Scatec is headquartered in Oslo, Norway and listed on the Oslo Stock Exchange under the ticker symbol ‘SCATC’. To learn more, visit  or connect with us on .  

This information is subject to the disclosure requirements pursuant to Section 5-12 the Norwegian Securities Trading Act

Attachments



EN
18/08/2023

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Scatec ASA

 PRESS RELEASE

Scatec secures long-term project financing for Rio Urucuia in Brazil

Scatec secures long-term project financing for Rio Urucuia in Brazil Oslo/Sao Paulo, 6 August 2025: Scatec ASA has reached financial close for its 142 megawatt (MW) solar PV plant currently under construction in Minas Gerais in Brazil. The non-recourse project financing comprises BRL 150 million (USD 27 million), to be provided by Banco de Nordeste do Brasil (“BNB”). The financing amount corresponds to 30% of the total estimated capital expenditure of BRL 506 million (USD 91 million). The solar plant is expected to reach Commercial Operation Date (“COD”) in the first half of 2026. “Secur...

ABGSC Renewable Energy Research ... (+3)
  • ABGSC Renewable Energy Research
  • Åsne Holsen
  • Daniel Vårdal Haugland
 PRESS RELEASE

Invitation to presentation of Scatec ASA’s second quarter results 2025

Invitation to presentation of Scatec ASA’s second quarter results 2025 Oslo, 04 August 2025: Scatec ASA will release its second quarter and first half 2025 results on Tuesday 19 August 2025 at 07:00 CEST. A presentation of the results followed by a Q&A session will be held on the same day at 09:00 CEST at Scatec’s headquarters at Skøyen Atrium III (1st floor), Askekroken 11, 0277 Oslo. The presentation and the Q&A session can be followed through a live webcast from our website , or . For further information, please contact:For analysts and investors:Andreas Austrell, SVP IR For media:Me...

 PRESS RELEASE

Scatec receives approval for ancillary services rate in the Philippine...

Scatec receives approval for ancillary services rate in the Philippines with retroactive effect Oslo/Manila, 29 July 2025: Scatec ASA’s joint venture with Aboitiz Power (SNAP) in the Philippines has received formal regulatory approval by the Energy Regulatory Commission (ERC) for the previously awarded rate related to the contingency reserve long-term ancillary services (AS) contracts in the Philippines. The awarded contract rate of 2.25 PHP/kWh (previously 1.5 PHP/kWh) will be effective from July 2025, with a retroactive effect of approximately NOK 231 million proportionate to Scatec. The...

ABGSC Energy Research ... (+6)
  • ABGSC Energy Research
  • Daniel Vårdal Haugland
  • John Olaisen
  • Njål Kleiven
  • Oliver Dunvold
  • Stian Wibstad

ResearchPool Subscriptions

Get the most out of your insights

Get in touch