SSO Scatec ASA

Scatec reaches financial close in Botswana and prepares for construction start

Scatec reaches financial close in Botswana and prepares for construction start

Oslo, 19 December 2024: Scatec ASA, a leading renewable energy provider, has reached financial close for the second 60 megawatt (MW) of the 120 MW Mmadinare Solar Complex in Botswana and is preparing for construction start.

In August 2022, Scatec, signed a binding 25-year power purchase agreement (PPA) with Botswana Power Corporation (BPC) for a 60 MW solar PV facility in the Mmadinare District. In the third quarter 2023, Scatec was awarded a 60 MW expansion of the project, taking the total capacity to 120 MW.

The estimated total capital expenditure for the 120 MW project is BWP 1.5 billion (USD 108 million) with an estimated engineering, procurement, and construction (EPC) contract value to Scatec of BWP 1.2 billion (USD 88 million). The solar power plants are estimated to be financed by BWP 1.0 billion (USD 73 million) of non-recourse project debt, and the remainder by equity from Scatec. Financing for the projects will be provided by the First National Bank of Botswana (acting through its Rand Merchant Bank division) and the World Bank’s International Finance Corporation (IFC).

Scatec owns 100% of the project and will be the designated EPC company, as well as asset manager (AM) and operations and maintenance (O&M) service provider. Construction and operation of the power plants will be managed by Scatec’s organisation in South Africa. Scatec is targeting to reduce its long-term economic interest in the project by inviting additional equity partners.

“We mark another achievement for our renewable energy journey in Botswana as we start construction of the second phase of the project. By doubling the total capacity of the solar power plant, we demonstrate the effectiveness of our strategy, robust business model and drive to contribute to the green energy transition in Africa,” says Scatec CEO Terje Pilskog.

The plant will be located near Mmadinare, close to the former mining town of Selebi-Phikwe, 400 kilometres Northeast of the capital Gaborone. The solar power plant will ensure that approximately 48,000 tons of COemissions will be avoided and can power approximately 20,000 households annually.



For further information, please contact:


For analysts and investors: Andreas Austrell, VP IR, phone: , For media: Meera Bhatia, SVP External Affairs & Communications, phone: , 



About Scatec 


Scatec is a leading renewable energy solutions provider, accelerating access to reliable and affordable clean energy emerging markets. As a long-term player, we develop, build, own, and operate renewable energy plants, with 4.8 GW in operation and under construction across four continents today. We are committed to grow our renewable energy capacity, delivered by our passionate employees and partners who are driven by a common vision of ‘Improving our Future’. Scatec is headquartered in Oslo, Norway and listed on the Oslo Stock Exchange under the ticker symbol ‘SCATC’. To learn more, visit  or connect with us on .

This information is considered to be inside information pursuant to the EU Market Abuse Regulation and is subject to the disclosure requirements pursuant to Section 5-12 the Norwegian Securities Trading Act.

This stock exchange announcement was published by Brage Krogsrud, IR Analyst at Scatec ASA, on 19 December 2024 at 07:34 CET 



EN
19/12/2024

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Scatec ASA

ABGSC Energy Research ... (+7)
  • ABGSC Energy Research
  • Åsne Holsen
  • Daniel Vårdal Haugland
  • Haakon Amundsen
  • John Olaisen
  • Oliver Dunvold
  • Stian Wibstad
 PRESS RELEASE

Scatec reaches financial close in Botswana and prepares for constructi...

Scatec reaches financial close in Botswana and prepares for construction start Oslo, 19 December 2024: Scatec ASA, a leading renewable energy provider, has reached financial close for the second 60 megawatt (MW) of the 120 MW Mmadinare Solar Complex in Botswana and is preparing for construction start. In August 2022, Scatec, signed a binding 25-year power purchase agreement (PPA) with Botswana Power Corporation (BPC) for a 60 MW solar PV facility in the Mmadinare District. In the third quarter 2023, Scatec was awarded a 60 MW expansion of the project, taking the total capacity to 120 MW. ...

ABGSC Renewable Energy Research ... (+7)
  • ABGSC Renewable Energy Research
  • Adrian Gilani
  • Åsne Holsen
  • Daniel Vårdal Haugland
  • Haakon Amundsen
  • John Olaisen
  • Stian Wibstad

Renewable Weekly – 28 Nov 2024

On aggregate, the R&C stocks underperformed (equal weight) the MSCI Nordic by ~4% throughout the reporting season (15 October to today).

 PRESS RELEASE

Scatec ASA: Mandatory notification of trade by primary insider

Scatec ASA: Mandatory notification of trade by primary insider Oslo, 26 November 2024: Jørgen Kildahl, board member of Scatec ASA, has on 26 November bought 3,000 shares in Scatec ASA at an average price per share of NOK 78.55. After the transaction Jørgen Kildahl owns 10,000 shares in Scatec ASA. Attached is the notification of the transaction in accordance with the Market Abuse Regulation Article 19. This information is subject to the disclosure requirements pursuant to the Market Abuse Regulation article 19 and section 5-12 of the Norwegian Securities Trading act. Attachment ...

 PRESS RELEASE

Scatec completes the Kalkbult, Linde, and Dreunberg transaction in Sou...

Scatec completes the Kalkbult, Linde, and Dreunberg transaction in South Africa Oslo, 20 November 2024: Scatec ASA, a leading renewable energy provider, has closed the second and final phase of the previously announced sale of parts of its ownership in the Kalkbult, Linde and Dreunberg solar power plants to Greenstreet 1 Proprietary Limited, a subsidiary of STANLIB Infrastructure Fund II, managed by STANLIB Asset Management Proprietary Limited (“STANLIB”). Scatec received ZAR 433 million (USD 24 million) in gross proceeds for its ownership sold in the second phase and has in total received...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch