IGN AB Ignitis Grupe GDR

Ignitis Group addresses public discussions on offshore wind development

Ignitis Group addresses public discussions on offshore wind development

AB “Ignitis grupė” (hereinafter – the Group), in response to public discussions and aiming to protect the investment environment as well as project partners, reminds about the development status of Lithuania’s first offshore wind project, Curonian Nord: 

  • the project development continues; 
  • to date, around EUR 50 million has been invested by the Group. Of this, EUR 20 million has been paid as a development fee and EUR 30 million has been allocated for environmental impact assessment, wind speed, water and meteorological measurements, various seabed surveys and other necessary works, which for the most part may also be flexibly used in the future without time constraints; 
  • final investment decision is expected after completion of development and obtaining construction permit in 2027; 
  • however, there might be a need to delay the project COD until there is more visibility on the electrolysis demand and/or the interconnector with Germany (to ensure long-term power offtake and in turn financing). The previous Group on this matter is available on page 36 of the Integrated Annual Report 2024 (). 

Should there be any material changes, the Group will announce them accordingly.  



For additional information, please contact: 

Communications 

Marius Zelenius 

 

 





EN
18/03/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on AB Ignitis Grupe GDR

 PRESS RELEASE

72.5 MW Stelpe solar farm I in Latvia reaches the commercial operation...

72.5 MW Stelpe solar farm I in Latvia reaches the commercial operation date AB “Ignitis grupė” (hereinafter – the Group) informs that Stelpe solar farm I, controlled by its subsidiary UAB “Ignitis renewables” (hereinafter – Ignitis Renewables), has reached the commercial operation date (hereinafter – COD). The project is in the southern part of Latvia, Bauska municipality. Covering 85 hectares, the solar farm is equipped with 121 thousand solar panels with a total installed capacity of 72.5 MW. The total investments in the solar farm, including acquisition and construction, will amount up ...

 PRESS RELEASE

72,5 MW galios Stelpės saulės parkas I Latvijoje pasiekė komercinės ve...

72,5 MW galios Stelpės saulės parkas I Latvijoje pasiekė komercinės veiklos pradžią AB „Ignitis grupė“ (toliau – Grupė) informuoja, kad Stelpės saulės parkas I, kurį valdo jos dukterinė įmonė UAB „Ignitis renewables“ (toliau – „Ignitis renewables“), pasiekė komercinės veiklos pradžią (angl. commercial operation date, COD). Projektas įgyvendintas pietinėje Latvijos dalyje, Bauskės savivaldybėje. 72,5 MW galios saulės elektrinė, išsidėsčiusi 85 hektarų plote, sudaryta iš 121 tūkstančio saulės modulių. Investicijos į saulės parką, įskaitant įsigijimo kainą ir statybų išlaidas, turėtų siekti...

 PRESS RELEASE

72.5 MW Stelpe solar farm I in Latvia reaches the commercial operation...

72.5 MW Stelpe solar farm I in Latvia reaches the commercial operation date AB “Ignitis grupė” (hereinafter – the Group) informs that Stelpe solar farm I, controlled by its subsidiary UAB “Ignitis renewables” (hereinafter – Ignitis Renewables), has reached the commercial operation date (hereinafter – COD). The project is in the southern part of Latvia, Bauska municipality. Covering 85 hectares, the solar farm is equipped with 121 thousand solar panels with a total installed capacity of 72.5 MW. The total investments in the solar farm, including acquisition and construction, will amount up ...

 PRESS RELEASE

Ministry of Finance announces the selection of members from among civi...

Ministry of Finance announces the selection of members from among civil servants to the new Supervisory Board of AB “Ignitis grupė” AB “Ignitis grupė” (hereinafter – the Group) informs that on the 1st of August 2025 the Ministry of Finance of the Republic of Lithuania (hereinafter – the Ministry of Finance), which exercises the rights of the majority shareholder, announced the selection of three members from among civil servants to the Group’s Supervisory Board, in the areas of public policy and governance, regulatory, accounting and audit competences. Candidates may apply until the 21st of...

 PRESS RELEASE

Finansų ministerija skelbia iš valstybės tarnautojų parenkamų naujos k...

Finansų ministerija skelbia iš valstybės tarnautojų parenkamų naujos kadencijos AB „Ignitis grupė“ stebėtojų tarybos narių atranką AB „Ignitis grupė“ (toliau – Grupė) informuoja, kad daugumos akcininko teises įgyvendinanti Lietuvos Respublikos finansų ministerija (toliau - Finansų ministerija) 2025 m. rugpjūčio 1 d. paskelbė trijų Grupės stebėtojų tarybos narių, Finansų ministerijos parenkamų iš valstybės tarnautojų, atranką į viešosios politikos ir valdymo, reguliavimo ir apskaitos ir audito sričių kompetencijas. Kandidatuoti į pozicijas galima iki 2025 m. rugpjūčio 21 d. (imtinai). Veiki...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch