AB “Ignitis grupė” (hereinafter – the Group) informs that, after the approval of the Group’s Management Board, on 6 September the Group’s subsidiary UAB “Ignitis renewables” signed a conditional agreement to acquire 100% shares of a Latvian company which is developing a wind and solar project in Latvia (hereinafter – the Agreement).

Targeted total capacity of the project under development is around 200 MW. The project is in the early stage of development with estimated start of construction in around 2025–2026 and commercial operation date in around 2027–2028. The completed project will operate under market conditions.

Total preliminary investments amount up to EUR 270 million, which includes the project acquisition price and other CAPEX. The payment of the acquisition price depends on achievement of development milestones established in the Agreement. It must be noted that the estimated total return on equity of the project is equal to the levels of similar projects communicated earlier. The expected return is in line with our target return range, i.e., high single-digit to low double-digit on a levered equity basis.

The Group reminds that the objective of Ignitis Group companies to consistently increase Green Generation portfolio and reach 4 GW of installed capacity by 2030 is set out in the Ignitis Group strategy (). Thus, implementation of agreements contributes to the implementation of strategic objectives.

For more information please contact:

Artūras Ketlerius

Head of Public Relations at Ignitis Group





EN
06/09/2022

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on AB Ignitis Grupe GDR

 PRESS RELEASE

Ignitis Group to present full-year 2025 results on 25 February

Ignitis Group to present full-year 2025 results on 25 February AB “Ignitis grupė” (hereinafter – the Group) will release its full-year 2025 results on Wednesday, 25 February 2026. It will be followed by an earnings call for investors and analysts, which will be held on the same day at 1:00 pm Vilnius / 11:00 am London time. To join the earnings call online or by phone, please register at: It will be also possible to join the earnings call by phone. To access the dial-in details, please register . After completing the registration, you will receive dial-in details on screen and via email. ...

 PRESS RELEASE

„Ignitis grupė“ vasario 25 d. pristatys 2025 m. rezultatus

„Ignitis grupė“ vasario 25 d. pristatys 2025 m. rezultatus AB „Ignitis grupė“ (toliau – Grupė) 2026 m. vasario 25 d., trečiadienį paskelbs 2025 m. rezultatus, kuriuos investuotojams ir analitikams pristatys tą pačią dieną 13:00 val. Vilniaus / 11:00 val. Londono laiku. Norėdami prie pristatymo prisijungti internetu arba telefonu, prašome užsiregistruoti čia: Taip pat prie pristatymo galėsite prisijungti ir telefonu. Norėdami gauti prisijungimo telefonu detales, prašome užsiregistruoti . Užbaigę registraciją, prisijungimo detales matysite savo įrenginio ekrane, jas gausite ir nurodytu ...

 PRESS RELEASE

Ignitis Group to present full-year 2025 results on 25 February

Ignitis Group to present full-year 2025 results on 25 February AB “Ignitis grupė” (hereinafter – the Group) will release its full-year 2025 results on Wednesday, 25 February 2026. It will be followed by an earnings call for investors and analysts, which will be held on the same day at 1:00 pm Vilnius / 11:00 am London time. To join the earnings call online or by phone, please register at: It will be also possible to join the earnings call by phone. To access the dial-in details, please register . After completing the registration, you will receive dial-in details on screen and via email. ...

 PRESS RELEASE

On the tentative award of a Polish capacity mechanism quarterly auctio...

On the tentative award of a Polish capacity mechanism quarterly auction for 2030 to Ignitis Gamyba AB “Ignitis grupė” (hereinafter – the Group) informs that its subsidiary AB “Ignitis gamyba” (hereinafter – the Company) is to ensure the availability of at least 148 MW capacity in the market in 2030 for around EUR 14.7 million in accordance with the preliminary results of the Polish capacity mechanism quarterly auction for ensuring capacity availability in 2030 (hereinafter – the Auction), conducted by the Polish transmission system operator Polskie Sieci Elektroenergetyczne (hereinafter – P...

 PRESS RELEASE

Dėl „Ignitis gamybos“ preliminariai laimėto Lenkijos galios mechanizmų...

Dėl „Ignitis gamybos“ preliminariai laimėto Lenkijos galios mechanizmų ketvirtinio aukciono 2030 m. AB „Ignitis grupė“ (toliau – Grupė) informuoja, kad jos dukterinė bendrovė AB „Ignitis gamyba“ (toliau – Bendrovė), pagal Lenkijos perdavimo sistemos operatoriaus „Polskie Sieci Elektroenergetyczne“ (toliau – PSE) paskelbtus preliminarius Lenkijos galios mechanizmų ketvirtinio aukciono, skirto galios pateikimui 2030 m., rezultatus (toliau – Aukcionas), turėtų 2030 m. užtikrinti rinkoje prieinamą ne mažesnę nei 148 MW galią už maždaug 14,7 mln. EUR. Grupė atkreipia dėmesį, kad aukciono rezult...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch