Alphamin Resources Corp. Provides Project Update, Releases Interim Results

Alphamin Resources Corp. Provides Project Update, Releases Interim Results

NOT FOR DISTRIBUTION TO U.S. NEWSWIRE SERVICES OR FOR PUBLICATION, RELEASE OR DISSEMINATION, DIRECTLY OR INDIRECTLY, IN WHOLE OR IN PART, IN THE UNITED STATES, AUSTRALIA, JAPAN, OR ANY OTHER JURISDICTION IN WHICH IT WOULD BE UNLAWFUL TO DO SO. ANY FAILURE TO COMPLY WITH THIS RESTRICTION MAY CONSTITUTE A VIOLATION OF THE SECURITIES LAWS OF SUCH JURISDICTIONS.

GRAND BAIE, Mauritius, Aug. 29, 2018 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (TSXV:AFM) (“Alphamin” or the “Company”) is pleased to announce an update on progress at its Bisie Tin Project.

Construction of the Company’s 80.75% owned Bisie Tin Project is currently on schedule and 75% complete. Commissioning of the process plant is scheduled for Q1 2019. Equity financing raised to date together with the US$80m credit facility is currently projected to take the Company through to commercial production.

Key project highlights include:

Safety Over 1 million-man hours worked by over 600 employees with no

lost time injuries reported.
Mine construction Progressing ahead of schedule with 1709 development meters

complete out of a total of 2,700.
Process plant Construction ahead of schedule with 256 tons of steel erected with

majority of kit required now on site.
Infrastructure Construction of the Company’s 36Km access road to site and

airstrip is now complete with project deliveries getting through to site

without difficulty.
Logistics and procurement 73% of project loads have been delivered to the mine site. 

Procurement is 90% complete.
Social and community  Social development investments targeting over 1500 households for

livelihoods and community infrastructure projects continue. Site

security and community relations have been strengthened further by

the peaceful and voluntary migration of the remaining 500 artisanal

miners from Alphamin’s concession in late 2017 and early 2018.

The recent Ebola outbreak in the North Kivu province is being monitored closely and strict protocols have been put in place to reduce the risk of transmission at Bisie. The outbreak is located some 1,200km from Bisie by road. To date there has been no impact on the Company’s operations.

The Company has also filed its interim financial statements for the three and six months ended June 30, 2018 and Management Discussion and Analysis – quarterly highlights, which are available on SEDAR.com.

Further information, videos and photographs of the Project’s progress are available on the Alphamin Resources Corp. website at

EDITORS NOTES:

FOR MORE INFORMATION, PLEASE CONTACT:

Boris Kamstra Alphamin Resources Corp.   
Chief Executive Officer    Tel: +230 269 4166
  E-mail:

Neither the TSX Venture Exchange nor its regulation services provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this News Release.

ISSUED ON BEHALF OF THE BOARD OF DIRECTORS OF ALPHAMIN RESOURCES CORP. BY:

Boris Kamstra, Chief Executive Officer 

Tel:

Grand Baie, Mauritius

CAUTION REGARDING FORWARD LOOKING STATEMENTS

Information in this news release that is not a statement of historical fact constitutes forward-looking information. Forward-looking statements contained herein include, without limitation, statements relating to the intended completion of additional financing and the anticipated use of funds from such financing, the participation of Tremont and other stakeholders, the satisfaction of conditions precedent under the Credit Facility, the Company’s intentions to raise the balance of funding required to complete construction of the Project and the sources thereof, additional subscription by IDC, costs of production, success of mining operations, the ranking of the project in terms of cash cost and production, economic return estimates, social, community and environmental impacts, and continued positive discussions and relationships with local communities and stakeholders. Forward-looking statements are based on assumptions management believes to be reasonable at the time such statements are made. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Although Alphamin has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. Factors that may cause actual results to differ materially from expected results described in forward-looking statements include, but are not limited to: Alphamin’s ability to secure sufficient financing to advance and complete the Project, uncertainties associated with Alphamin’s resource and reserve estimates, uncertainties regarding the estimation of future costs, uncertainties regarding global supply and demand for tin and market and sales prices, uncertainties associated with securing off-take agreements and customer contracts, uncertainties with respect to social, community and environmental impacts, adverse political events, uncertainties with respect to optimization opportunities for the Project, as well as those risk factors set out in the Company’s Management Discussion and Analysis and other disclosure documents available under the Company’s profile at . Forward-looking statements contained herein are made as of the date of this news release and Alphamin disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws.

EN
29/08/2018

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Alphamin Resources Corp.

 PRESS RELEASE

ALPHAMIN ANNOUNCES RECORD FY2025 TIN PRODUCTION /FY2026 PRODUCTION GUI...

ALPHAMIN ANNOUNCES RECORD FY2025 TIN PRODUCTION /FY2026 PRODUCTION GUIDANCE/ EXPLORATION UPDATE/ SENIOR MANAGEMENT CHANGES Grand Baie, MAURITIUS, Jan. 19, 2026 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX)( “Alphamin” or the “Company”) is pleased to provide the following update for the year and quarter ended 31 December 2025:      FY2025 tin production of 18,576 tonnes, up 7% from the prior year     Q4 tin production of 5,008 tonnes (Q3: 5,190 tonnes)     FY2025 EBITDA2,3 guidance of US$341m, an estimated increase of 25% from actual FY2024 at a tin price of US$34...

 PRESS RELEASE

ALPHAMIN ANNOUNCES RESIGNATION OF DIRECTOR

ALPHAMIN ANNOUNCES RESIGNATION OF DIRECTOR Grand Baie, MAURITIUS, Jan. 05, 2026 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX) (the “Company” or “Alphamin”) announced today that Mr. Paul Baloyi has resigned as a director of the Company effective January 31, 2026. Mr. Baloyi has served on the board since April 2017 as an appointee of the Industrial Development Corporation of South Africa Ltd. (IDC) and the board of directors wishes to thank him for his contributions to Alphamin during his tenure. FOR MORE INFORMATION, PLEASE CONTACT: Charles Needham              ...

 PRESS RELEASE

ALPHAMIN REPORTS FATALITY AT MPAMA SOUTH UNDERGROUND MINE

ALPHAMIN REPORTS FATALITY AT MPAMA SOUTH UNDERGROUND MINE Grand Baie, Mauritius                               , Dec. 25, 2025 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX) (the “Company” or “Alphamin”) deeply regrets to report that an employee of operating subsidiary Alphamin Bisie Mining S.A. (“ABM”) was fatally injured at its Mpama South underground mine in east-central Democratic Republic of the Congo.On 24 December at approximately 18:00 local time, following the scheduled evacuation of the underground areas for the planned night shift blast, an incident occurr...

 PRESS RELEASE

ALPHAMIN ANNOUNCES CAD $0.04 PER SHARE SECOND INTERIM FY2025 DIVIDEND ...

ALPHAMIN ANNOUNCES CAD $0.04 PER SHARE SECOND INTERIM FY2025 DIVIDEND / FILES Q3 2025 FINANCIAL STATEMENTS AND MD&A Grand Baie, MAURITIUS, Nov. 03, 2025 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX)( “Alphamin” or the “Company”) announced today the declaration of a second interim FY2025 dividend and the filing of its unaudited condensed consolidated financial statements and accompanying Management’s Discussion and Analysis (“MD&A”) for the three and nine months ended 30 September 2025 on SEDAR+ at . Second Interim FY2025 Dividend Declared The Board has declar...

 PRESS RELEASE

ALPHAMIN PROVIDES Q3 2025 OPERATIONAL UPDATE

ALPHAMIN PROVIDES Q3 2025 OPERATIONAL UPDATE Grand Baie, MAURITIUS, Oct. 07, 2025 (GLOBE NEWSWIRE) -- Alphamin Resources Corp. (AFM:TSXV, APH:JSE AltX)( “Alphamin” or the “Company”) is pleased to provide an operational update as follows: Q3 2025 contained tin production of 5,190 tonnes, up 26% from the previous quarter (Q2 2025: 4,106 tonnes (period from phased restart on April 15 to June 30))FY2025 contained tin production guidance increased to between 18,000 and 18,500 tonnes (17,500 tonnes previously)Contained tin sales of 5,143 tonnes for the quarter, up 12% from the prior periodQ3 2...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch