MONTREAL, Sept. 06, 2024 (GLOBE NEWSWIRE) -- Aya Gold & Silver Inc. (TSX: AYA; OTCQX: AYASF) (“Aya” or the “Corporation”) today provided an update on construction progress at its Zgounder Silver Mine in the Kingdom of Morocco. The expansion project was 98% complete as at August 30, fully funded, and on budget.

The Corporation’s engineering, procurement, and construction partner, Duro Felguera (“DF”), encountered issues during commissioning of the hydraulic unit of the ball mill. As a result of these issues, DF recently advised Aya that a rework of the hydraulic unit piping is required. This does not impact the integrity of the ball mill, the hydraulic unit or other equipment. Commissioning of other subsystems is proceeding steadily, and the crushing circuit is now operational.

As a result of the necessary rework, DF has requested and obtained from Aya a two-month extension for hot commissioning and ramp-up of the Zgounder expanded plant. All other critical areas of the Zgounder expansion project are progressing to plan or are in commissioning:

  • Commissioning of other areas of the plant continues to progress: ore has been crushed throughout the entire crushing circuit and sent to the silo.
  • Work has begun on the underground ramp from the 1,925m to 1,900m levels and will continue to lower levels.
  • The entire mining site is now powered with renewable energy from the newly built 60kV power line.
  • The new underground mobile workshop is in use.
  • The primary underground ventilation is working on all levels.
  • The on-surface cemented backfill mixing station and piping on all sublevels are mechanically complete and will shortly be commissioned.
  • All four underground electrical substations have been deployed.
  • The water dams and other water storage infrastructures are operational.
  • The new tailings dam is in use.
  • Water is being recovered from the tailing dam.
  • The base camp is complete.
  • The new assay laboratory is near-complete with commissioning planned end of September 2024.

Given the delay in hot-commissioning and ramp-up of the Zgounder expanded plant, the Corporation’s 2024 production guidance is under review. Aya expects to revisit its production guidance based on construction progress and operational results by latest November 14, 2024, when it will publish its third-quarter 2024 financial results.

"While there has been a slight delay in hot commissioning, all critical aspects of the Zgounder Mine expansion are advancing as planned, and the project remains on budget,” said Benoit La Salle, President & CEO. “We are on track for a strong finish to the year with additional operational milestones and exploration drill results expected to further enhance stakeholder value. We are confident that 2025 will be an exceptional year following completion of the plant ramp-up.”

The technical information in this news release has been reviewed and approved by Raphaël Beaudoin, P. Eng, Vice-President, Operations for Aya, and a “Qualified Person” as defined under NI 43-101.

About Aya Gold & Silver Inc.

Aya Gold & Silver Inc. is a rapidly growing, Canada-based silver producer with operations in the Kingdom of Morocco.

The only TSX-listed pure silver mining company, Aya operates the high-grade Zgounder Silver Mine and is exploring its properties along the prospective South-Atlas Fault, several of which have hosted past-producing mines and historical resources. Aya’s Moroccan mining assets are complemented by its Tijirit Gold Project in Mauritania, which is being advanced to feasibility.

Aya’s management team has been focused on maximising shareholder value by anchoring sustainability at the heart of its operations, governance, and financial growth plans.

For additional information, please visit Aya’s website at .

Or contact

Benoit La Salle, FCPA, MBA



President & CEO







Alex Ball



VP, Corporate Development & IR



Forward-Looking Statements

This press release contains certain statements that constitute forward-looking information within the meaning of applicable securities laws (“forward-looking statements”), which reflects management’s expectations regarding Aya’s future growth and business prospects (including the timing and development of new deposits and the success of exploration activities) and other opportunities. Wherever possible, words such as “plan”, “update”, “progress”, “on budget”, “continue”, “expects”, “advancing”, “remains”, “on track”, “confident”, “exceptional”, and similar expressions or statements that certain actions, events or results “may”, “could”, “would”, “might”, “will”, or are “likely” to be taken, occur or be achieved, have been used to identify such forward-looking information. Specific forward-looking statements in this press release include, but are not limited to, statements and information with respect to advancement of the commissioning work according to Aya’s plan, expected dates of hot commissioning, ramp up and commercial production, capacities of production until the company reaches commercial production, capacities of production in 2024 and statements with respect to Aya’s guidance for production. Although the forward-looking information contained in this press release reflect management’s current beliefs based upon information currently available to management and based upon what management believes to be reasonable assumptions, Aya cannot be certain that actual results will be consistent with such forward-looking information. Such forward-looking statements are based upon assumptions, opinions and analysis made by management in light of its experience, current conditions, and its expectations of future developments that management believe to be reasonable and relevant but that may prove to be incorrect. These assumptions include, among other things, the ability to execute on the commissioning plan, the ability to increase the resource at Zgounder, the ability of these results to translate into an increase of resource, the ability to obtain any requisite governmental approvals, obtaining regulatory permits for on-site work, importing goods and machinery and employment permits, the accuracy of Mineral Reserve and Mineral Resource Estimates (including, but not limited to, ore tonnage and ore grade estimates), the price of silver, the price of gold, exchange rates, fuel and energy costs, future economic conditions, anticipated future estimates of free cash flow, and courses of action. Aya cautions you not to place undue reliance upon any such forward-looking statements.

The risks and uncertainties that may affect forward-looking statements include, among others: the inherent risks involved in exploration and development of mineral properties, including government approvals and permitting, changes in economic conditions, changes in the worldwide price of silver gold and other key inputs, changes in mine plans (including, but not limited to, throughput and recoveries being affected by metallurgical characteristics) and other factors, such as project execution delays, many of which are beyond the control of Aya, as well as other risks and uncertainties which are more fully described in Aya’s 2023 Annual Information Form dated March 28, 2024, and in other filings of Aya with securities and regulatory authorities which are available on SEDAR+ at Aya does not undertake any obligation to update forward-looking statements should assumptions related to these plans, estimates, projections, beliefs, and opinions change. Nothing in this document should be construed as either an offer to sell or a solicitation to buy or sell Aya securities. All references to Aya include its subsidiaries unless the context requires otherwise.



EN
06/09/2024

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Aya Gold and Silver

 PRESS RELEASE

Mx2 Mining Announces $15M Brokered Private Placement and Board Appoint...

Mx2 Mining Announces $15M Brokered Private Placement and Board Appointments NOT FOR DISTRIBUTION TO U.S. NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES OF AMERICA Highlights: Exploration at high-grade Amizmiz gold property in Morocco planned to begin in OctoberFinancing increased from C$7.5M to C$15M due to strong investor demandDirectors and officers investing C$2.2M in financing; Aya to invest C$1MAya will own 44% of Mx2 following completion of financing and acquisitionStrong leadership and board comprised of key personnel from Aya, Red Back, Orca and Montage TORONTO, Oct....

 PRESS RELEASE

Aya Gold & Silver Extends Boumadine Main Zone to 5.4km and Reports Hig...

Aya Gold & Silver Extends Boumadine Main Zone to 5.4km and Reports High-Grade Drill Results MONTREAL, Sept. 16, 2024 (GLOBE NEWSWIRE) -- Aya Gold & Silver Inc. (TSX: AYA; OTCQX: AYASF) (“Aya” or the “Corporation”) is pleased to announce new high-grade drill exploration results from its 2024 program of 120,000 meters (“m”) at Boumadine in the Kingdom of Morocco. Today’s results extend the main mineralized trend by 400m and continue to demonstrate continuity of the Boumadine Main Zone, which remains open in all directions. Key Highlights1 Extension of Boumadine strike length to 5....

 PRESS RELEASE

Aya Or & Argent augmente l’étendue de la zone Principale à Boumadine à...

Aya Or & Argent augmente l’étendue de la zone Principale à Boumadine à 5,4 km et publie des résultats de forage à haute teneur MONTRÉAL, 16 sept. 2024 (GLOBE NEWSWIRE) -- Aya Or & Argent Inc. (TSX : AYA; OTCQX : AYASF) (« Aya » ou la « Société ») a le plaisir d’annoncer de nouveaux résultats de forage d’exploration à haute teneur issus de son programme 2024 totalisant 120 000 mètres (« m ») à Boumadine dans le Royaume du Maroc. Les résultats annoncés aujourd’hui permettent d’augmenter l’étendue du corridor minéralisé principal de 400 m et continuent de démontrer la continuité de la zone P...

 PRESS RELEASE

Aya Gold & Silver Announces Spinout and Creation of Growth-Focused Gol...

Aya Gold & Silver Announces Spinout and Creation of Growth-Focused Gold Venture MONTREAL, Sept. 12, 2024 (GLOBE NEWSWIRE) -- Aya Gold & Silver Inc. (TSX: AYA; OTCQX: AYASF) (“Aya” or the “Corporation”) is pleased to report that it has entered into non-binding term sheets for the spinout of its Amizmiz Gold Project (the “Amizmiz Property”) in the Kingdom of Morocco and the granting of an option on its Tijirit Project in the Islamic Republic of Mauritania to Mx2 Mining (“Mx2” or “SpinCo”), a new North Africa-dedicated gold growth company backed by Aya with the participation of Richard Clark...

 PRESS RELEASE

Aya Gold & Silver Updates on Expansion of Zgounder

Aya Gold & Silver Updates on Expansion of Zgounder MONTREAL, Sept. 06, 2024 (GLOBE NEWSWIRE) -- Aya Gold & Silver Inc. (TSX: AYA; OTCQX: AYASF) (“Aya” or the “Corporation”) today provided an update on construction progress at its Zgounder Silver Mine in the Kingdom of Morocco. The expansion project was 98% complete as at August 30, fully funded, and on budget. The Corporation’s engineering, procurement, and construction partner, Duro Felguera (“DF”), encountered issues during commissioning of the hydraulic unit of the ball mill. As a result of these issues, DF recently advised Aya ...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch