COP.. Marimaca Copper

Marimaca Appoints Leonardo Hermosilla as Vice President, Projects; Provides Progress Update at the Marimaca Copper Project

Marimaca Appoints Leonardo Hermosilla as Vice President, Projects; Provides Progress Update at the Marimaca Copper Project

VANCOUVER, British Columbia, Aug. 22, 2022 (GLOBE NEWSWIRE) -- Marimaca Copper Corp. (“Marimaca Copper” or the “Company”) (TSX: MARI) is pleased to welcome Mr. Leonardo Hermosilla to the Team as Vice President, Projects. Mr. Hermosilla brings over 30 years of international mining development, construction, and operational experience to Marimaca. In addition, Marimaca announces an update on various project development workstreams at the Marimaca Copper Project (the “Project”).

Highlights

Leonardo Hermosilla Appointed as Vice President, Projects

  • Mr. Hermosilla will provide senior technical leadership as the Marimaca Project advances towards the 2023 Feasibility Study and a construction decision
    • Mr. Hermosilla will be based out of Marimaca’s Santiago, Chile office
  • Mr. Hermosilla is a global mining executive and brings over 30 years of experience in mine development and construction to Marimaca. He formerly held the roles of:
    • Director of Projects and Growth, South America for Barrick;
    • General Manager and SVP Copper for SNC Lavalin Chile;
    • Project Development Director at Hatch Engineering where he oversaw the development of the US$4 billion El Morro Project; and
    • VP Project Development for Kingsgate Consolidated

2022 Drilling Campaigns Now Complete

  • The 2022 Infill and MAMIX drilling campaigns were completed on August 18th 2022, with remaining results pending final assays
    • 2022 Infill and MAMIX programs totalled 38,570m across 177 drill holes
  • Geological interpretation and resource modelling is currently underway ahead of the planned 2022 Mineral Resource Update (“MRE”) expected in late Q3
    • The 2022 MRE will capture drilling data completed up to June 30th, 2022, with the balance of the infill drilling (targeting conversion to Measured and Indicated Resource categories) to be captured in a subsequent MRE planned for early 2023

Water Engagement Update

  • Significant progress has been made on negotiations with potential seawater suppliers located in the Bay of Mejillones (~20km from the Marimaca Project) to secure a seawater supply option for the Marimaca Project
  • Marimaca is targeting completion of the water supply option, which guarantees seawater supply for the Marimaca Project, by year-end 2022

MAMIX Transitional and Primary Copper Extraction Concept Study

  • Marimaca is currently completing a proof-of-concept study led by 5Q Technologies (“5Q”) (the “5Q Study”), a privately-help specialist mineral processing company based in Santiago, Chile ()
  • 5Q specializes in the extraction of copper from complex transitional and primary ores using their proprietary QX-Cu technology
  • The study aims to evaluate the potential for improving and optimizing the recovery of the deeper transitional material located in the MAMIX-zone, the depth extension to the Marimaca Oxide Deposit (“MOD”)
  • A proof-of-concept study is currently underway with initial laboratory results expected in the near term. Marimaca and 5Q may then elect to advance to a next phase of study with a larger sample size
  • The 5Q study will supplement the Phase 5 Metallurgical Program (see announcement dated June 15, 2022) which represents the culmination of a rigorous, bankable-level 5-phase metallurgical program at the MOD

Geotechnical and Condemnation Drilling

  • Marimaca has now completed the 2022 geotechnical diamond drilling campaign which was executed alongside the 2022 Infill and MAMIX campaigns
    • 2022 geotechnical and geological campaign totalled 3,000m across 13 diamond drill holes
  • Data from the 2022 geotechnical campaign will be used in the 2023 Feasibility Study and relevant permitting submissions planned for 2023
  • Planning and budgeting are currently underway for the condemnation drilling program across key infrastructure areas

Hayden Locke, President & CEO of Marimaca Copper, commented:

“I am very excited to welcome Leonardo to the team as we start our transition to developer and, eventually, operator of the Marimaca Oxide Deposit. He brings enormous experience in mine development and will provide important technical leadership as Marimaca moves toward production.

“The 2022 infill drilling campaign is now complete and we remain confident that the first mineral resource update, towards the end of September, will deliver a step change in the scale of the Marimaca Project. We continue to make good progress with the various work programs aimed at moving the project towards production, and we look forward to updating the market on these as they’re completed.”

Contact Information

For further information please visit or contact:

Tavistock

+44 (0) 207 920 3150

Emily Moss / Adam Baynes

Forward Looking Statements

This news release includes certain “forward-looking statements” under applicable Canadian securities legislation. There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements reflect the beliefs, opinions and projections on the date the statements are made and are based upon a number of assumptions and estimates that, while considered reasonable by Marimaca Copper, are inherently subject to significant business, economic, competitive, political and social uncertainties and contingencies. Many factors, both known and unknown, could cause actual results, performance or achievements to be materially different from the results, performance or achievements that are or may be expressed or implied by such forward-looking statements and the parties have made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: risks related to share price and market conditions, the inherent risks involved in the mining, exploration and development of mineral properties, the uncertainties involved in interpreting drilling results and other geological data, fluctuating metal prices, the possibility of project delays or cost overruns or unanticipated excessive operating costs and expenses, uncertainties related to the necessity of financing, the availability of and costs of financing needed in the future as well as those factors disclosed in the annual information form of the Company dated March 28, 2022, the final short form base prospectus and other filings made by the Company with the Canadian securities regulatory authorities (which may be viewed at ). Accordingly, readers should not place undue reliance on forward-looking statements. Marimaca Copper undertakes no obligation to update publicly or otherwise revise any forward-looking statements contained herein whether as a result of new information or future events or otherwise, except as may be required by law.

Neither the Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.



EN
22/08/2022

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Marimaca Copper

 PRESS RELEASE

Pampa Medina Drilling Continues to Validate Sedimentary-Hosted Copper ...

Pampa Medina Drilling Continues to Validate Sedimentary-Hosted Copper Manto Model VANCOUVER, British Columbia, Nov. 11, 2025 (GLOBE NEWSWIRE) -- Marimaca Copper Corp. (“Marimaca Copper” or the “Company”) (TSX:MARI, ASX:MC2) is pleased to announce the final results from it’s 10,000m discovery drilling campaign at the Pampa Medina deposit, located at low altitude approximately 28km east of the Company’s Marimaca Oxide Deposit (“MOD”) in a flat “pampa” valley within the Atacama Desert (Figure 1). The drilling results continue to demonstrate material extensions to the high-grade sedimentary-h...

 PRESS RELEASE

Marimaca Announces Receipt of Environmental Approval for the Marimaca ...

Marimaca Announces Receipt of Environmental Approval for the Marimaca Oxide Deposit  VANCOUVER, British Columbia, Nov. 11, 2025 (GLOBE NEWSWIRE) -- Marimaca Copper Corp. (“Marimaca Copper” or the “Company”) (TSX:MARI, ASX:MC2) is pleased to announce that its Chilean subsidiary, Marimaca NewCo Limitada (“Marimaca”), has received the formal Resolución de Calificación Ambiental (“RCA”) for its Marimaca Oxide Project (the “MOD” or “Project”), located in the low coastal cordillera of the Antofagasta region of Chile. The RCA represents the formal approval of the Company’s Declaración de Impacto...

 PRESS RELEASE

Marimaca Regretfully Announces the Passing of Colin Kinley

Marimaca Regretfully Announces the Passing of Colin Kinley VANCOUVER, British Columbia, Nov. 07, 2025 (GLOBE NEWSWIRE) -- It is with great sadness that Marimaca Copper Corp. (“Marimaca” or the “Company”) (TSX:MARI, ASX:MC2) announces the sudden passing of Mr. Colin Kinley, Director of the Company. The Board and Company express their sincere condolences to Karen, Cooper, and Claire, their extended family and friends. Colin joined Marimaca (formerly Coro Mining) as a Director in 2016, became Chairman from 2017-2018, and was most recently Chair of the Audit Committee. He was a well-respecte...

 PRESS RELEASE

Marimaca Copper Files NI 43-101 Technical Report for the Previously An...

Marimaca Copper Files NI 43-101 Technical Report for the Previously Announced Marimaca Oxide Deposit Feasibility Study VANCOUVER, British Columbia, Oct. 09, 2025 (GLOBE NEWSWIRE) -- Marimaca Copper Corp. (TSX: MARI) (ASX: MC2) (“Marimaca” or the “Company”) announces it has filed the Feasibility Study technical report for the Marimaca Oxide Deposit project located in the Antofagasta Region, Chile (the “Report”). The Report was prepared in accordance with National Instrument 43-101 standards of Disclosure for Mineral Projects. The Report supports the disclosure made in the Company’s news r...

 PRESS RELEASE

Marimaca Copper Announces Closing of A$80,000,000 Placement

Marimaca Copper Announces Closing of A$80,000,000 Placement Not for release to U.S. wire services or for distribution in the United States VANCOUVER, British Columbia, Sept. 11, 2025 (GLOBE NEWSWIRE) -- Marimaca Copper Corp. (TSX: MARI) (ASX: MC2) (“Marimaca” or the “Company”) is pleased to announce the closing of the previously announced brokered placement in Australia and select other jurisdictions, excluding Canada (the “Placement”). Pursuant to the closing of the Placement, the Company issued 8,247,423 Chess Depositary Interests (“CDI”) each at a price of A$9.70 for gross proceeds o...