Start of construction of residential projects (Uus-Veerenni third stage in Tallinn)

Start of construction of residential projects (Uus-Veerenni third stage in Tallinn)

On 23 March 2020 the group informed via a stock exchange announcement () about the continuing construction activities until completion of all apartment development projects that were currently in construction phase, and not initiating construction works of any new development projects within three months due to the pandemic.

  

As three months have passed, the group informs as follows:

1) The construction of the apartment development projects in construction phase in Estonia, Latvia and Lithuania has proceeded as planned.

2) AS Merko Ehitus Eesti, part of the group, starts the construction of the third stage of the Uus-Veerenni residential project (Uus-Veerenni Park, ) in July of this year (earlier stock exchange announcement about the launch of the project: ). Three apartment buildings with 59 apartments will be completed by the end of 2021.

  

Andres Trink

Chairman of the Management Board

AS Merko Ehitus





  

AS Merko Ehitus () group consists of AS Merko Ehitus Eesti in Estonia, SIA Merks in Latvia, UAB Merko Statyba in Lithuania and Peritus Entreprenør AS in Norway. Besides providing construction service as a main contractor, the group’s other major area of activity is apartment development. As at the end of 2019, the group employed 694 people, and the group’s revenue for 2019 was EUR 327 million.

EN
02/07/2020

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Merko Ehitus (New)

 PRESS RELEASE

Investor calendar 2026

Investor calendar 2026 In 2026 AS Merko Ehitus will publish its consolidated financial results according to the schedule below:   DateEvent  5 February 2026  2025 12 months and 4th quarter unaudited interim report   6 April 2026  Audited Annual Report 2025  7 May 2026  2026 3 months unaudited interim report  6 August 2026  2026 6 months and 2nd quarter unaudited interim report  5 November 2026  2026 9 months and 3rd quarter unaudited interim report     The annual general meeting of shareholders for approval of 2025 annual report will take place in the second quarter of 2026. Exact time and...

 PRESS RELEASE

Investorkalender 2026

Investorkalender 2026 2026. aastal avaldab AS Merko Ehitus konsolideeritud majandustulemused alljärgnevalt:    KuupäevSündmus   5. veebruar 2026  2025. aasta 12 kuu ja IV kvartali auditeerimata vahearuanne     6. aprill 2026  2025. aasta auditeeritud majandusaasta aruanne     7. mai 2026  2026. aasta 3 kuu auditeerimata vahearuanne     6. august 2026  2026. aasta 6 kuu ja II kvartali auditeerimata vahearuanne     5. november 2026  2026. aasta 9 kuu ja III kvartali auditeerimata vahearuanne         Aktsionäride korraline üldkoosolek 2025. aasta majandusaasta aruande kinnitamiseks toimub 2026...

 PRESS RELEASE

Comment on the Verslo Žinios article in Lithuania (Rudninkai Polygon P...

Comment on the Verslo Žinios article in Lithuania (Rudninkai Polygon Public Procurement) Lithuanian business newspaper Verslo Žinios has reported that UAB Merko Statyba, part of the AS Merko Ehitus group, has submitted the best bid for parts B and C in the public procurement "Development of the military infrastructure of the Rūdninkai polygon through a public-private partnership (PPP)". To the knowledge of AS Merko Ehitus, the Lithuanian Ministry of Defence has not officially published the decision on the selection of the best bidders or made a proposal to the participants in the tender to...

 PRESS RELEASE

Kommentaar Verslo Žinios artiklile Leedus (Rudninkai polügooni riigiha...

Kommentaar Verslo Žinios artiklile Leedus (Rudninkai polügooni riigihange) Leedu ärileht Verslo Žinios on teavitanud, et riigihankel „Rūdninkai polügooni sõjaväetaristu arendamine avaliku ja erasektori partnerluse (PPP) kaudu“ on osadele B ja C teinud parima pakkumise AS Merko Ehitus kontserni kuuluv UAB Merko Statyba. AS Merko Ehitusele teadaolevalt ei ole Leedu kaitseministeerium ametlikult parimate pakkujate valiku otsust avaldanud ega teinud pakkumises osalejatele ettepanekut lepingu sõlmimiseks. Leedu kaitseministeerium on teavitanud (/rudininku-karinio-miestelio-ii-etapo-konkursas-fi...

 PRESS RELEASE

Ehitusleping Eestis (büroohoone Tallinnas)

Ehitusleping Eestis (büroohoone Tallinnas) 28. novembril 2025 sõlmisid AS Merko Ehitus kontserni kuuluv AS Merko Ehitus Eesti ja Mainor Ülemiste AS projekteerimis- ja ehituslepingu büroohoone rajamiseks Tallinnas aadressil Lõõtsa 1 B/C. Leping hõlmab 13-korruselise ja kahe korpusega büroohoone ehitust. Viktor Masingu nime kandma hakkava ehitise brutopind on 27 300 m2. A-energiaklassiga hoonele taotletakse energiatõhusa ehitise sertifikaat LEED Gold. Lepingu maksumus on ligikaudu 35 miljonit eurot, millele lisandub käibemaks. Ehitustööd valmivad 2027. aasta novembris. AS Merko...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch