MMY Monument Mining

Monument Begins Gold Concentrate Shipments at Selinsing Gold Mine

Monument Begins Gold Concentrate Shipments at Selinsing Gold Mine

VANCOUVER, British Columbia, June 23, 2023 (GLOBE NEWSWIRE) -- Monument Mining Limited (TSX-V: MMY and FSE: D7Q1) ("Monument" or the "Company") is pleased to announce the first gold concentrate shipments and sales from the newly constructed flotation plant at the Selinsing Gold Mine.

President and CEO Cathy Zhai commented, "This is a momentous occasion for us as we begin to ship and sell gold concentrates from the flotation plant. The initial offtake of 2,000 dry metric tonnes (“DMT”) of concentrate from Selinsing marks the beginning of a gold concentrate revenue stream and restores our operating cash flow. We would like to give thanks to our hard-working operation teams, backroom administration support personnel and our business partners to make this happen."

Figure 1. Loading Concentrate for Transport is available at 

Figure 2. Concentrate Shipment at Weighbridge is available at 

Gold Concentrate Shipments and Sales

Significant interest has been received from potential buyers of the Selinsing gold concentrate. All export and transport permits have been received and the first truckloads of concentrate were shipped from the Selinsing warehouse on June 18th, 2023 to Johor Free Trade Zone. To date 490 DMT of concentrate have been dispatched out of an initial offtake of 2,000 DMT. Weighing, sampling and moisture determination of the delivered concentrate is being conducted at the Johor Free Trade Zone by an appointed internationally recognized survey company.

An additional 3,000 DMT of concentrate is currently available for sale. The Company intends after a trial shipment to gradually increase the number of trucks to speed up the logistic process in selling backlogged product. In the future concentrates will be shipped to buyers on a routine basis. The backlog was caused by a lengthy initial administrative process for obtaining all relevant permits and organizing logistics. Over the last six months, the Company has built a logistic team and sales chain at the Selinsing Project.

Commercial Production Update

The flotation plant operation is improving with up to 99% of design capacity achieved during June 2023, and overall 83% capacity achieved for the 30 day period up to June 17th 2023. Torn filter cloths remained an issue with new cloths still awaited from the filter press supplier McLanahan. New HDPE pipework was received to upgrade the concentrate thickener underflow pipeline. A similar upgrade was planned for the flotation cleaner concentrate pipeline which emerged as a bottleneck with increasing flotation mass pull.

Figure 3: Selinsing Flotation Plant is available at 

Flotation recovery has shown a steady improvement as increasing proportions of newly mined transition and fresh ore were processed. Daily recoveries in excess of 80% have been recorded during June 2023, although an average of 68% recovery month to date was caused by some poorly performing old transition ore processed at the start of the month.

Construction of the concentrate shed continued with the main roof completed and the perimeter concrete wall approximately 50% done. Work continued extending the lean-to roof to the filter press building. The bagging system has been prepared for shipping to Malaysia.

Mining Update

Mining of Buffalo Reef Stage 1 BRC2 and BRC3 pits continued with both transition and fresh ore delivered to the ROM pad and maintained around one month’s supply of ore feed to the flotation processing plant. A new drill rig was delivered in June 2023 with nine grade control drilling rigs now operational; a tenth unit is scheduled for delivery in August 2023. The mining operation is aiming to achieve and maintain a three-month supply of ore at the ROM.

Construction of the explosive’s depot progressed well with delivery of the bulk emulsion gassing container and the connection to mains power completed. This is to remove dependency on explosives delivery from the sole dominant supplier in the country due to their shortfall of trucks over the past several months. The isotainer storage tanks are due for delivery in late June 2023 and the explosives depot will be commissioned in early July 2023.

Work started on the conversion of the old core shed to an expanded sample preparation facility capable of processing up to 700 grade control samples per day, which will remove another major bottleneck in the mining cycle.

Risks

Other operation risks in related to mining and processing processes are under continuous evaluation to improve the performance.

The Company closely monitors uncontrollable risk factors with building and operation of the flotation plant including but not limited to: change of market conditions, change of gold prices, operation risks including critical parts shortages which may cause a longer than expected ramp up period, and changes in regulatory restrictions in relation to arsenic level contained in gold concentrate.

About Monument

Monument Mining Limited (TSX-V: MMY, FSE: D7Q1) is an established Canadian gold producer that 100% owns and operates the Selinsing Gold Mine in Malaysia and the Murchison Gold Project in the Murchison area of Western Australia. It has 20% interest in Tuckanarra Gold Project jointly owned with Odyssey Gold Ltd in the same region. The Company employs approximately 200 people in both regions and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighboring communities.

Cathy Zhai, President and CEO

Monument Mining Limited

Suite 1580 -1100 Melville Street

Vancouver, BC V6E 4A6

FOR FURTHER INFORMATION visit the company web site at or contact:

Richard Cushing, MMY Vancouver T: x102

"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."

Disclaimer Regarding Forward-Looking Statements

This news release includes statements containing forward-looking information about Monument, its business and future plans ("forward-looking statements"). Forward-looking statements are statements that involve expectations, plans, objectives or future events that are not historical facts and include the Company's plans with respect to its mineral projects, expectations regarding the completion of the ramp-up period to target production level at Selinsing and the timing thereof, expectations regarding the Company’s continuing ability to source explosives from suppliers, expectations regarding completion of the proposed storage shed and ammonium nitrate depot and the timing thereof, and the timing and results of the other proposed programs and events referred to in this news release. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The forward-looking statements in this news release are subject to various risks, uncertainties and other factors that could cause actual results or achievements to differ materially from those expressed or implied by the forward-looking statements. These risks and certain other factors include, without limitation: risks related to general business, economic, competitive, geopolitical and social uncertainties; uncertainties regarding the results of current exploration activities; uncertainties in the progress and timing of development activities, including those related to the ramp-up process at Selinsing and the completion of the proposed storage shed and ammonium nitrate depot; uncertainties and risks related to the Company’s ability to source explosives from suppliers; foreign operations risks; other risks inherent in the mining industry and other risks described in the management discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at Material factors and assumptions used to develop forward-looking statements in this news release include: expectations regarding the estimated cash cost per ounce of gold production and the estimated cash flows which may be generated from the operations, general economic factors and other factors that may be beyond the control of Monument; assumptions and expectations regarding the results of exploration on the Company's projects; assumptions regarding the future price of gold of other minerals; the timing and amount of estimated future production; assumptions regarding the timing and results of development activities, including the ramp-up process at Selinsing and the completion of the proposed storage shed and ammonium nitrate depot; expectations that the Company will continue to be able to source explosives from suppliers in a timely manner; costs of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; exchange rates; and all of the factors and assumptions described in the management discussion and analysis of the Company and the technical reports on the Company's projects, all of which are available under the profile of the Company on SEDAR at Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statements, except in accordance with applicable securities laws.



EN
23/06/2023

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Monument Mining

 PRESS RELEASE

Monument schließt Kooperationsvertrag ab und gewährt Odyssey Zugang zu...

Monument schließt Kooperationsvertrag ab und gewährt Odyssey Zugang zur Burnakura-Mühle VANCOUVER, British Columbia, April 15, 2025 (GLOBE NEWSWIRE) -- Monument Mining Limited (TSX-V: MMY, FSE: D7Q1) („Monument“ oder das „Unternehmen“) freut sich, die Unterzeichnung einer Absichtserklärung („MOU“ oder „Kooperationsvertrag“) mit Odyssey Gold Limited (ASX: ODY) („Odyssey“) über ihre jeweiligen Tochtergesellschaften bekanntzugeben. Der Vertrag sieht eine Möglichkeit der Zusammenarbeit bei der Verarbeitung von Erz aus dem Tuckanarra-Goldprojekt („Tuckanarra“) durch die Burnakura-Mühle von Mon...

 PRESS RELEASE

Monument signe un accord de collaboration et donne à Odyssey l’accès à...

Monument signe un accord de collaboration et donne à Odyssey l’accès à l’usine de Burnakura VANCOUVER, Colombie-Britannique, 15 avr. 2025 (GLOBE NEWSWIRE) -- Monument Mining Limited (TSX-V : MMY, FSE : D7Q1) (« Monument » ou la « Société ») a le plaisir d’annoncer la signature d’un protocole d’accord (« Accord de collaboration », ou « Protocole d’accord ») avec Odyssey Gold Limited (ASX : ODY) (« Odyssey »), par lʼintermédiaire de ses filiales respectives. Cet accord décrit une opportunité de collaboration en vue de traiter le minerai du projet aurifère Tuckanarra (« Tuckanarra ») par le ...

 PRESS RELEASE

Monument Entered Into a Collaboration Agreement Gives Odyssey Access t...

Monument Entered Into a Collaboration Agreement Gives Odyssey Access to Burnakura Mill VANCOUVER, British Columbia, April 14, 2025 (GLOBE NEWSWIRE) -- Monument Mining Limited (TSX-V: MMY, FSE: D7Q1) (“Monument” or the “Company”) is pleased to announce the signing of a Memorandum of Understanding (“MOU” or “Collaboration Agreement”) with Odyssey Gold Limited (ASX: ODY) (“Odyssey”), through their respective subsidiaries. The agreement outlines a collaboration opportunity to process ore from the Tuckanarra Gold Project (“Tuckanarra”) through Monument’s Burnakura Mill, located near Meekatharr...

 PRESS RELEASE

Monument schließt Kooperationsvertrag ab, GBR erhält Zugang zur Mühle ...

Monument schließt Kooperationsvertrag ab, GBR erhält Zugang zur Mühle von Burnakura VANCOUVER, British Columbia, April 03, 2025 (GLOBE NEWSWIRE) -- Monument Mining Limited (TSX-V: MMY und FSE: D7Q1) („Monument” oder das „Unternehmen“) verkündete heute den Abschluss eines Memorandum of Understanding („Kooperationsvertrag“ oder „MOU”) mit Great Boulder Resources („Great Boulder“, ASX: „GBR“) in Bezug auf eine potenzielle Zusammenarbeit für die Aufbereitung von Erz aus dem Great Boulder Side Well Gold Projekt durch die Mühle von Burnakura von Monument in Meekatharra, Westaustralien. Pre...

 PRESS RELEASE

Monument signe un accord de collaboration et donne à GBR l’accès à l’u...

Monument signe un accord de collaboration et donne à GBR l’accès à l’usine de Burnakura VANCOUVER, Colombie-Britannique, 03 avr. 2025 (GLOBE NEWSWIRE) -- Monument Mining Limited (TSX-V : MMY et FSE : D7Q1) (« Monument » ou la « Société ») a le plaisir d’annoncer aujourd’hui la signature d’un protocole d’accord (« Accord de collaboration », ou « Protocole d’accord ») avec Great Boulder Resources (« Great Boulder », ASX : « GBR »). Cette collaboration permettra d’assurer le potentiel traitement du minerai du projet aurifère Side Well de Great Boulder par l’usine Burnakura de Monument à Meek...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch