MTHH MT Hojgaard Holding

MT Højgaard Holding A/S: MT Højgaard Danmark wins Energinet tender

MT Højgaard Holding A/S: MT Højgaard Danmark wins Energinet tender

MT Højgaard Holding’s business unit MT Højgaard Danmark has been awarded several work scopes related to state-owned Energinet’s construction of the new high-voltage station AC Lindehøj at Solhøj in the municipality of Høje-Taastrup. The contract sum is DKK 241 million.

The work comprises a turnkey contract for buildings that will contain the station’s high-voltage equipment, terrain work on 71 hectares surrounding the station and establishment of the construction site. The work is expected to commence in early 2026 when environmental approval has been granted for the project and the current archeological excavations have been completed. The buildings are scheduled for completion in the spring of 2027.

The new 400 kV high-voltage station will be a central part of the expansion of the electricity grid on Zealand and Lolland-Falster. The expansion will ensure that large quantities of green power from offshore wind turbines in the Baltic Sea will be distributed to areas with higher consumption in the vicinity of Copenhagen and Northern Zealand.

MT Højgaard Danmark has previously completed critical infrastructure work for Energinet and is currently engaged in a multi-year partnership for the expansion of the electricity grid in western Denmark.

”The energy area is very interesting for us, and we have good experience collaborating with Energinet, so we have made a targeted effort to secure this work scope. The Lindehøj project has a high level of technical complexity, and it calls for close coordination and attention to detail together with the technical supplier, Hitachi. We are looking forward to this,” says Hasse Stouby Jensen, project director at MT Højgaard Danmark.

The order does not affect MT Højgaard Holding’s 2025 outlook, which is unchanged with revenue expected at a level of DKK 10-10.5 billion and an operating profit (EBIT) of DKK 400-450 million.

Further information:

CEO Rasmus Untidt and CFO Dennis Nørgaard can be contacted on telephone .

Attachment



EN
02/07/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on MT Hojgaard Holding

 PRESS RELEASE

MT Højgaard Holding A/S: MT Højgaard Danmark vinder udbud fra Energine...

MT Højgaard Holding A/S: MT Højgaard Danmark vinder udbud fra Energinet MT Højgaard Holdings forretningsenhed MT Højgaard Danmark er blevet tildelt opgaver ved etableringen af det statslige Energinets nye højspændingsstation AC Lindehøj ved Solhøj i Høje-Taastrup Kommune. Ordren har en værdi på 241 mio. kr. Opgaverne omfatter en totalentreprise på de bygninger, der skal huse stationens højspændingsudstyr, terrænarbejder på 71 hektar omkringliggende arealer og etablering af en byggeplads. Arbejderne ventes indledt i starten af 2026, når der er givet miljøtilladelse til projektet, og de igan...

 PRESS RELEASE

MT Højgaard Holding A/S: MT Højgaard Danmark wins Energinet tender

MT Højgaard Holding A/S: MT Højgaard Danmark wins Energinet tender MT Højgaard Holding’s business unit MT Højgaard Danmark has been awarded several work scopes related to state-owned Energinet’s construction of the new high-voltage station AC Lindehøj at Solhøj in the municipality of Høje-Taastrup. The contract sum is DKK 241 million. The work comprises a turnkey contract for buildings that will contain the station’s high-voltage equipment, terrain work on 71 hectares surrounding the station and establishment of the construction site. The work is expected to commence in early 2026 when env...

 PRESS RELEASE

MT Højgaard Holding A/S: MT Højgaard Danmark erects innovative buildin...

MT Højgaard Holding A/S: MT Højgaard Danmark erects innovative building for Nrep MT Højgaard Holding’s business unit MT Højgaard Danmark will build an office property at Trælastholmen in Copenhagen for Urban Partners through their property investment team Nrep. The project is comprised of 13,700 square meters of floor space across 6 stories and a green town garden, which will be open to the public. The building will be erected as a hybrid construction in which parts of the concrete will be replaced by wood-based modules to significantly reduce the CO2 footprint. The building is expected to...

 PRESS RELEASE

MT Højgaard Holding A/S: MT Højgaard Danmark opfører nyskabende bygger...

MT Højgaard Holding A/S: MT Højgaard Danmark opfører nyskabende byggeri for Nrep MT Højgaard Holdings forretningsenhed MT Højgaard Danmark skal på Trælastholmen i København opføre en kontorejendom for Urban Partners via deres ejendomsinvesteringsteam Nrep. Projektet omfatter 13.700 etagemeter fordelt på 6 etager samt en grøn byhave, der vil være åben for offentligheden. Byggeriet opføres i en hybridkonstruktion, hvor dele af betonen erstattes af træbaserede moduler, hvilket reducerer CO2-aftrykket væsentligt. Byggeriet ventes certificeret til både DGNB Guld og den frivillige lavemissionskl...

 PRESS RELEASE

MT Højgaard Holding A/S: MT Højgaard Danmark skal opføre nyt verdensla...

MT Højgaard Holding A/S: MT Højgaard Danmark skal opføre nyt verdenslager for UNICEF MT Højgaard Holdings forretningsenhed MT Højgaard Danmark har vundet det faseopdelte udbud på at opføre verdens største centrallager for humanitær hjælp til FN’s børnefond UNICEF. Opgaven har en samlet værdi på 1,66 mia. kr. Tildelingen er først endelig, når standstill er udløbet, og projektøkonomien skal godkendes af Folketingets Finansudvalg. Bygherre er udviklingsselskabet By & Havn. CAMPUS 4 i Københavns Nordhavn bliver et bygningskompleks på 63.000 etagemeter, og MT Højgaard Danmark skal udføre opgave...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch