VANCOUVER, British Columbia, Oct. 15, 2020 (GLOBE NEWSWIRE) -- Novo Resources Corp. (“Novo” or the “Company”) (TSX-V: NVO; OTCQX: NSRPF) is pleased to provide an operational update, including from its Beatons Creek gold project (“Beatons Creek”) on which development activities have commenced, and from refurbishment works on infrastructure recently acquired pursuant to the acquisition of Millennium Minerals Limited (“Millennium”) which are proceeding on schedule (please see the Company’s news releases dated and for further details).

Refurbishment works on Millennium’s infrastructure is proceedings as follows:

Plant refurbishment works:

  • Novo has executed a contract with GR Engineering Services (ASX: GNG) (“GRES”) to undertake refurbishment of Millennium’s processing infrastructure at an estimated cost of AUD $8.3 million (see Figure 1 below).
  • The works substantially consist of the maintenance and refurbishment of the gold plant, existing CIL leach tanks, and a gravity circuit capacity upgrade. GRES are synonymous with gold plant construction and refurbishment throughout Australia and were selected based upon their experience and capacity to undertake these works safely, efficiently, and cost effectively.

Power restoration to site:

  • Kalgoorlie Power Systems (“KPS”) have restored power to the Millennium infrastructure, enabling GRES works to continue uninterrupted and for commissioning of the Millennium offices, camp, and other infrastructure over the coming months. KPS have demonstrated their intent to work constructively with Novo in regard to re-establishing full-scale power generation for the Millennium infrastructure, with commercial discussions ongoing.

Camp upgrade works:

  • Pilbara Resources Group (“PRG”) has been appointed to undertake a ‘camp readiness’ scope of work to ensure the camp is safe and ready for operations following 9 months of care and maintenance by undertaking the following work:
    • Testing and tagging of electrical equipment, servicing air conditioners and hot water systems
    • Replacement of unserviceable cooking facilities and damaged flooring in cooking and dining areas
    • Undertaking early camp management (cooking, cleaning, etc.) whilst the permanent scope is competitively tendered

Development activities at Beatons Creek are progressing as follows:

Commencement of development activities:

  • A contract has been awarded to Edwards Mining and Civil (“EMC”) to undertake initial Beatons Creek site establishment works (see Figure 2 below). EMC have demonstrated their credentials for this type of work over the past two field seasons at Novo’s Egina project, with the current Beatons Creek scope comprising:
    • Preparing sites for grade control drilling
    • Eradication of invasive and noxious Calotropis weed
    • Establishment of site access roads and haulage / light vehicle roads
    • Establishment of ROM pad
    • Clearing for office, lay down pad and equipment ‘go bay’

Grade Control Drilling works:

  • Castle Drilling (“Castle”) has been awarded the contract for initial grade control drilling works. Castle have worked previously at Beatons Creek and their knowledge of the conglomerate deposit will prove invaluable. Drilling and sampling activities will commence in the coming weeks.
  • MinAnalytical Laboratories (part of Perenti Global Limited – ASX: PRN) have been retained to undertake the assaying of the grade control samples, utilizing award winning Chrysos technology. This technology is capable of rapidly and accurately scanning up to 500g of material at a time, an important capability when dealing with coarse gold systems. Novo are in discussions with MinAnalytical with regard to establishing an on-site laboratory facility for Novo at Millennium’s plant.

Major tenders currently under negotiation:

  • The primary mining contract is currently being tendered by a select group of experienced mining contractors.
  • The Millennium camp management services contract is being tendered with strong interest from a group of service providers experienced in this style of work in the Pilbara region.

In addition, the Company is pleased to announce the following key personnel appointments and ongoing recruitment activity:

  • Trevor Eddie had been appointed Geology Manager. Mr. Eddie has operational geology experience in numerous styles of deposits across the West Australian gold mining industry. His specialist skills in the reconciliation of resources through the mining and processing cycle will be well utilized as Novo advances Beatons Creek towards production.
  • Leisa Nash has been appointed to the position of site-based Finance and Administration Manager. Ms. Nash has extensive site based commercial operational experience, including having worked previously for Millennium, experience which will be invaluable as Novo establishes local stakeholder relationships in an operational context.
  • Recruiting continues apace for other positions as required operationally, with very strong interest seen from experienced industry participants eager to be involved with the unique story surrounding the development of Pilbara conglomerate gold.

Novo CEO and Director Rob Humphryson commented, “Novo is delighted with the rapid progress being made at Beatons Creek and the recently acquired Millennium infrastructure. We are assembling an experienced and enthusiastic operational team who have a sense that they are integral to pioneering a new era of conglomerate gold production in Western Australia. This enthusiasm is being mirrored by our contracting partners, stakeholders and government regulators alike, with a growing awareness that this mineralization style has the potential to develop into a basin wide opportunity.”

About Novo Resources Corp.

Novo is advancing its flagship Beatons Creek gold project to production while exploring and developing its highly prospective land package covering approximately 14,000 square kilometres in the Pilbara region of Western Australia. In addition to the Company’s primary focus, Novo seeks to leverage its internal geological expertise to deliver value-accretive opportunities to its shareholders. For more information, please contact Leo Karabelas at (416) 543-3120 or e-mail 

On Behalf of the Board of Directors,

Novo Resources Corp.

“Quinton Hennigh”

Quinton Hennigh

President and Chairman

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

Forward-looking information

Some statements in this news release contain forward-looking information (within the meaning of Canadian securities legislation) including, without limitation, the successful completion of plant refurbishments works on time and on budget at the Beatons Creek and Millennium and that Novo’s board of directors will take the decision to commence production of Novo’s Beatons Creek property. Forward-looking statements address future events and conditions and, as such, involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the statements. Such factors include, without limitation, the successful completion of commercial discussions with KPS, the successful completion of the camp upgrade work currently being completed by PRG, the successful completion of site establishment works at Beatons Creek by EMC, the successful completion of grade control drilling works by Castle Drilling, MinAnalytical’s ability to assay the Company drill samples in a timely and cost-effective manner, the successful completion of commercial discussions with MinAnalytical regarding the establishment of an on-site laboratory at Millennium, the successful completion of mining and camp management services contracts, and customary risks of the resource industry.

PDFs accompanying this announcement are available at:

EN
15/10/2020

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Novo Resources

 PRESS RELEASE

Novo Resources Releases Updated Corporate Presentation

Novo Resources Releases Updated Corporate Presentation PERTH, Australia, Feb. 17, 2026 (GLOBE NEWSWIRE) -- Novo Resources Corp. (Novo or the Company) (ASX: NVO) (TSX: NVO) (OTCQB: NSRPF) is pleased to announce the release of its updated corporate presentation, now available on the Company’s website. The new presentation outlines Novo’s strategic priorities, exploration results, project advancements, and near-term catalysts. It offers investors a clear and current view of Novo’s evolving growth strategy and its portfolio of high-potential gold assets. “Our updated corporate presentation ...

 PRESS RELEASE

Novo Resources Business Update

Novo Resources Business Update HIGHLIGHTS The Exploration Target at the Belltopper Gold Project in Victoria, has been significantly increased following detailed review and assessment. Preliminary planning has commenced for potential drilling in H2 2026, aimed to provide further confidence in the updated 2026 Exploration Target.Successful exploration at Teichman in the Egina Gold Camp defined multiple prospects over an area of 1.3 x 2.5 km, with notable potential along two main shear corridors. Rock-chip assay results include peak values of 77.5 g/t Au and 51.4 g/t Au, with 11 of 87 samples...

 PRESS RELEASE

Novo Delivers Significant Increase to Belltopper Exploration Target

Novo Delivers Significant Increase to Belltopper Exploration Target HIGHLIGHTS The Exploration Target, which was defined in 2024, has been significantly increased following detailed review and assessment. The Belltopper Gold Project is located within the gold prolific Bendigo Tectonic Zone in Victoria and approximately 60 km SSW of the high-grade world-class Fosterville Gold Mine. The updated 2026 Exploration Target brings in the Western Domain Fault as a new reef and encapsulates strike and depth extensions on four of the seven priority reefs included in the 2024 Exploration Target. Th...

 PRESS RELEASE

New Targets at the Wyloo Gold – Silver – Antimony Project for Maiden D...

New Targets at the Wyloo Gold – Silver – Antimony Project for Maiden Drill Program HIGHLIGHTS Highly encouraging exploration results have been received from the Wyloo Project, confirming multiple high priority targets.A strong multielement soil anomaly has been defined over Wyloo SE, where a polymetallic vein system has previously been defined by Novo, including peak soil values of 57.2 ppm Ag, 142 ppm Sb, 1,440 ppm As, 2,180 ppm Zn and 1,530 ppm Pb. The anomaly remains open undercover to the SW and NE.Follow-up exploration on the high-order Sb stream anomaly at Wyloo SW has defin...

 PRESS RELEASE

Novo Resources Releases 2025 Sustainability Report Highlighting Commit...

Novo Resources Releases 2025 Sustainability Report Highlighting Commitment to Integrity, People and the Environment PERTH, Western Australia, Nov. 19, 2025 (GLOBE NEWSWIRE) -- Novo Resources Corp. (Novo or the Company) (ASX: NVO) (TSX: NVO) (OTCQB: NSRPF) is pleased to announce the publication of its 2025 Sustainability Report, detailing the Company’s ongoing commitment to responsible and sustainable business practices across all operations. The report highlights Novo’s focus on three core pillars: operating with integrity, valuing our people and communities, and respecting the environ...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch