NVO Novo Resources

Novo Provides Update on Production Ramp-Up at Beatons Creek Gold Project

Novo Provides Update on Production Ramp-Up at Beatons Creek Gold Project

Not for Distribution to United States Newswire Services or for dissemination in the United States

VANCOUVER, British Columbia, April 29, 2021 (GLOBE NEWSWIRE) -- Novo Resources Corp. (“Novo” or the “Company”) (TSX: NVO & NVO.WT; OTCQX: NSRPF) is pleased to provide an update of the ramp-up of operations at the Beatons Creek conglomerate gold project in Western Australia (“Beatons Creek”).

Highlights

  • Commissioning and ramp up have progressed safely (no lost time injuries recorded to date) and within expectations amid a favourable gold price environment (Australian gold price currently above A$2,275 per oz)
  • Since commencement of processing operations on and pouring of Novo’s first gold bar on , a total of 7,375 fine oz Au and 1,158 fine oz Ag have been sold to date
  • Processing facility (the “Golden Eagle Mill”) operating at 1.5 Mt per annum throughput, as expected, with demonstrated higher capacity
  • Mining and haulage operations are progressing within expectations
  • In line with broader industry experience, significant delays have been experienced in third party assay turnaround with only around half of all grade control sample results returned to date. Novo geologists have compensated for these delays by successfully visually identifying mineralisation bands to guide selective mining operations
  • Mining and geological processes are continually being refined to optimize mining and processing operations and to minimize mineralization loss and dilution

“Novo is delighted to have assembled a high calibre team in such a short timeframe and in a buoyant commodity market,” commented Rob Humphryson, CEO and a director of Novo. “Considerable progress has been made to date and we continue to generate positive momentum as we ramp up production at Beatons Creek to steady state.”

Details and Outlook

  • Since pouring first gold on February 16, 2021, 29 further gold bars have been poured for a total of 7,375 fine troy oz Au, with gold production steadily increasing in line with the Company’s ramp-up schedule.
  • Throughput at the Golden Eagle Mill has been steadily increasing to an annualized production rate of approximately 1.5 Mt per annum as mill operating parameters are optimized. Novo plans to further increase throughput at the Golden Eagle Mill, noting that the Golden Eagle Mill has been test run successfully at instantaneous rates up to 2Mt per annum ().

Figure 1 is available at

  • Recoveries at the Golden Eagle Mill have varied between 87-98% since start-up. As steady state throughput is expected to be reached over the coming months, recoveries are expected to stabilize in the mid 90% range. The proportion of gold recovered by the gravity circuit is typically above 50%, in line with metallurgical test work for Beatons Creek.
  • Scheduling requirements associated with grade control trial areas and the establishment of waste landform locations necessitated commencement of mining in a lower grade area in the distal NW portion of Beatons Creek, with grade scheduled to increase as new areas of the resource are exposed.
  • Head grade at the Golden Eagle Mill has ranged from 0.6-3.5 gpt Au since start up, indicative of the nuggety nature of the Beatons Creek mineralization.
  • Since start-up, drill and blast techniques have been introduced to allow for effective loading and selective mining. Mining techniques will continue to be refined and adapted in response to the geometry and hardness of the mineralized horizons, to increase productivity and optimize operating costs ( and ).

Figure 2 is available at

Figure 3 is available at

  • Grade control and resource upgrade reverse circulation drilling at 20 x 20m spacing continues throughout the entire deposit. The initial focus is on mine scheduling priorities, and also to achieve a higher level of confidence in the resource at Beatons Creek. Infill grade control at 10 x 10m spacing will be undertaken in more geologically complex areas where more detail is required.
  • Whilst the PhotonAssay technique has proved ideally suited for the Beatons Creek grade control regime, significant delays have been experienced in third party assay turnaround with only around half of all grade control sample results returned to date. Novo geologists have compensated for these delays by continuing to develop visual techniques to guide selective mining operations. An example of the result of detailed bench and face mapping work being undertaken by the Novo team is evident in , which illustrates mark-up of four conglomerate beds in preparation for mining.

Figure 4 is available at  

  • Novo is pleased to note that Chrysos Corporation will soon be deploying additional PhotonAssay units into Western Australia, increasing the number of available machines (currently three units) to five units before the end of June. Novo expects to leverage this increased capacity to significantly improve assay turnaround times. Novo has utilized PhotonAssay technology extensively throughout its Pilbara projects.
  • Novo is currently establishing an internal sample preparation facility on site at the Golden Eagle Mill, producing samples for distribution to the increased capacity of photon assay facilities.

“Our team has rapidly developed visual grade control protocols to guide mining in the absence of full grade control assay results,” commented Quinton Hennigh, Chairman and President of Novo. “We are aggressively tackling the need to speed up assay returns by establishing our own sample preparation facility at site and leveraging the planned ramp up of photon assay capability in Western Australia by Chrysos Corporation. This will be critical as Novo moves to complete a 20 x 20 grade control and resource upgrade drill campaign across Beatons Creek over the coming months. Meanwhile, protocols for mining this unique type of mineralization are rapidly being refined to maximize mining rates and minimize dilution. We see ability to eventually operate the Golden Eagle Mill at a run rate of 1.9-2.0 Mt per annum, well above the anticipated run rate of 1.6 Mt per annum. The team is diligently working towards steady state operations over the coming months.”

Financing Update

On , the Company announced a C$22 million brokered private placement (the “Financing”), the net proceeds of which will be used, generally, to fund new exploration efforts in the Pilbara region of Western Australia, continue ramping up operations at Beatons Creek, the planned infill drilling campaign and the increased photon assay capacity in Western Australia, and for general corporate working capital purposes. The Company also plans to initiate expansive exploration programs in the East Pilbara region, particularly in the Nullagine area, to continue expanding Beatons Creek’s footprint and identify targets with potential to become near-to-medium term mill feed. The Company also plans to deploy the Steinert KSS 100F LIXT fine mechanical sorting unit to the Pilbara in Q2 2021.

Cautionary Statement

The decision by the Company to produce at Beatons Creek was not based on a feasibility study of mineral reserves demonstrating economic and technical viability and, as a result, there is an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure. There is no guarantee that that anticipated production costs will be achieved. Failure to achieve the anticipated production costs would have a material adverse impact on the Company’s cash flow and future profitability.

Dr. Quinton Hennigh (P.Geo.) is the qualified person pursuant to NI 43-101 responsible for, and having reviewed and approved, the technical information contained in this news release. Dr. Hennigh is President, Chairman, and a director of Novo.

About Novo Resources Corp.

Novo is commissioning its flagship Beatons Creek gold project while exploring and developing its highly prospective land package covering approximately 14,000 square kilometres in the Pilbara region of Western Australia. In addition to the Company’s primary focus, Novo seeks to leverage its internal geological expertise to deliver value-accretive opportunities to its shareholders. For more information, please contact Leo Karabelas at (416) 543-3120 or e-mail 

On Behalf of the Board of Directors,

Novo Resources Corp.

Quinton Hennigh

Quinton Hennigh

President and Chairman

Forward-looking information

Some statements in this news release contain forward-looking information (within the meaning of Canadian securities legislation). These include statements (the “forward-looking statements”) regarding Novo’s intent, or the beliefs or current expectations of Novo’s management. When used in this news release, words such as “will”, “would”, “expect”, “target”, “potential”, “objective”, “subject to”, “expected to” and similar words or expressions identify these forward-looking statements as well as phrases or statements that certain actions, events or results “may”, “could”, “would”, “should”, “occur” or “be achieved” or the negative connotation of such terms. Forward-looking statements in this news release include, without limitation, the ability to run the Golden Eagle Mill at up to 2.0 Mt per annum, the expected stabilization in the coming weeks of recovery rates around the mid 90% range, the ability to expedite sample preparation and laboratory throughput for its grade control drilling samples based on an increase in photon assay unit availability in Western Australia, the ability to achieve a higher level of confidence in the resource at Beatons Creek by utilizing 20 x 20 m grade control drilling, and the expected completion of the Financing and planned use of net proceeds of the Financing. Forward-looking statements address future events and conditions and, as such, involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, without limitation, receipt of Toronto Stock Exchange approval to the Financing, the risk factors identified in Novo’s annual information form for the 11-month financial year ended December 31, 2020 and Novo’s management’s discussion and analysis for the same period, both of which are available on SEDAR at  Forward-looking statements speak only as of the date those statements are made. Except as required by applicable law, Novo assumes no obligation to update or to publicly announce the results of any change to any forward-looking statement contained or incorporated by reference herein to reflect actual results, future events or developments, changes in assumptions or changes in other factors affecting the forward-looking statements. If Novo updates any forward-looking statement(s), no inference should be drawn that the Company will make additional updates with respect to those or other forward-looking statements.

The securities described in this news release have not been, and will not be, registered under the United States Securities Act of 1933, as amended (the "1933 Act"), or any U.S. state securities laws, and may not be offered or sold in the United States without registration under the 1933 Act and all applicable state securities laws or compliance with the requirements of an applicable exemption therefrom. This news release shall not constitute an offer to sell or the solicitation of an offer to buy securities in the United States, nor shall there be any sale of these securities in any jurisdiction in which such offer, solicitation or sale would be unlawful. 



EN
29/04/2021

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Novo Resources

 PRESS RELEASE

Novo Resources Releases Updated Corporate Presentation Highlighting St...

Novo Resources Releases Updated Corporate Presentation Highlighting Strategic Progress and Growth Initiatives PERTH, Western Australia, Aug. 05, 2025 (GLOBE NEWSWIRE) -- Novo Resources Corp. (“Novo” or the “Company”) (ASX: NVO) (TSX: NVO) (OTCQB: NSRPF) is pleased to announce the release of its updated corporate presentation, now available on the Company’s website at The refreshed presentation provides a comprehensive overview of Novo’s strategic priorities, recent exploration success, project developments, and near-term catalysts. It offers investors and stakeholders clear insights i...

 PRESS RELEASE

Highlights – June Quarter 2025

Highlights – June Quarter 2025 Novo completed its maiden RC drill program at the Clone prospect as part of the Tibooburra Gold Project in May 2025 testing 500 m of strike. Drilling produced significant high-grade gold intercepts including: 12 m @ 5.90 g/t Au from 16 m, including 5 m @ 13.74 g/t Au from 23 m (TBR0001)117 m @ 2.40 g/t Au from 59 m including 9 m @ 4.14 g/t Au from 59 m (TBR0014)1Grade and width continuity has been successfully demonstrated by the RC drilling and indicates a shallow north plunge to the near-surface shoot of high-grade gold mineralisation, now defined over 300 m...

 PRESS RELEASE

Significant Results from RC Drilling at Tibooburra Gold Project

Significant Results from RC Drilling at Tibooburra Gold Project HIGHLIGHTS Novo completed its maiden drill program at the Clone prospect as part of the Tibooburra Gold Project, in May 2025. The program comprised 14 RC holes for 1,984 m, testing 500 m of strike.Drilling produced significant high-grade gold intercepts including: 12 m @ 5.90 g/t Au from 16 m, including 5 m @ 13.74 g/t Au from 23 m (TBR0001)17 m @ 2.40 g/t Au from 59 m including 9 m @ 4.14 g/t Au from 59 m (TBR0014) The peak intercept in hole TBR001 (12 m @ 5.90 g/t Au) fills a 180 m gap in previous drilling by Manhattan Corpo...

 PRESS RELEASE

Novo Announces AGM Results

Novo Announces AGM Results PERTH, Western Australia, June 24, 2025 (GLOBE NEWSWIRE) -- Novo Resources Corp. (Novo or the Company) (ASX: NVO) (TSX: NVO) (OTCQX: NSRPF) reports that all resolutions proposed to shareholders at the annual general meeting of shareholders (held on June 23, 2025 (Vancouver, BC)/June 24, 2025 (Perth, WA) were approved, including the election of all of the director nominees listed in the management information circular for the meeting. Voting as to each of the director nominees was as follows: Name of NomineeVotes Cast FOR% Votes Cast FORVotes WITHHELD% of Votes W...

 PRESS RELEASE

Pilbara Exploration Update

Pilbara Exploration Update High-Grade Gold and Antimony Targets HIGHLIGHTS Novo has advanced Pilbara high-grade gold and gold-antimony prospects which will be the focus for exploration and drilling in H2 2025.Exploration at the Sherlock Crossing Au-Sb prospect has defined a coherent 1.5 km antimony in soil anomaly (at > 15 ppm Sb), with gold anomalism up to 85 ppb Au, with all heritage and compliance approvals now in place for exploration drilling.At the Southeast Wyloo Au-Sb-Ag-Cu Project, plans are in place to complete mapping and rock chip sampling in preparation for drill progr...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch