Orezone Reports First Gold from Bomboré Hard Rock Expansion

Orezone Reports First Gold from Bomboré Hard Rock Expansion

VANCOUVER, British Columbia, Dec. 15, 2025 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) (the “Company” or “Orezone”) is pleased to announce that it has completed the first gold pour from the Company’s new 2.5Mtpa hard rock expansion.

Patrick Downey, President and CEO stated, "Commissioning of this plant is now complete, with mill throughput averaging 78% of nameplate capacity for the first 5 days of operations, resulting in first gold on December 15.

I want to extend my sincere gratitude to all involved in the construction and commissioning of the Bomboré hard rock expansion. Their dedication, hard work and commitment to excellence have safely delivered the stage 1 expansion on time and on budget over a construction period of approximately 12 months. This is a commendable achievement, reflecting an industry-leading level of project delivery.

Commercial production is expected to be declared in early Q1-2026, and will represent a major milestone for Orezone, with overall gold production at Bomboré set to increase by 45% to 170,000-185,000oz in 2026. This will mark a significant cash flow inflection point, underscored by the Company’s solid balance sheet and record high gold prices.”

Click to view the video which illustrates the timeline and progress from commencement of construction in November 2024 to first gold in December 2025.

About Orezone Gold Corporation

Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) is a West African gold producer engaged in mining, developing, and exploring the Bomboré Gold Mine in Burkina Faso. Combined production from the oxide and stage 1 hard rock operations is forecasted to total between 170,000 and 185,000 ounces in 2026. The Company is also advancing stage 2 of the hard rock expansion, which is forecasted to increase annual production to between 220,000 and 250,000 ounces.

Contact Information

Patrick Downey

President and Chief Executive Officer

Kevin MacKenzie

Vice President, Corporate Development and Investor Relations

Tel: 1 778 945 8977

/

For further information please contact Orezone at +1 (778) 945-8977 or visit the Company’s website at .

The Toronto Stock Exchange neither approves nor disapproves the information contained in this news release.

This announcement was authorized for release by Patrick Downey, Director, President & CEO.

Qualified Persons and Competent Person Statement

The scientific and technical information in this news release was reviewed and approved by Mr. Rob Henderson, P. Eng, Vice-President of Technical Services and Mr. Dale Tweed, P. Eng., Vice-President of Engineering, both of whom are Qualified Persons as defined under NI 43-101 - Standards of Disclosure for Mineral Projects and Competent Persons as defined under the JORC Code (2012 Edition). Each of Messrs. Henderson and Tweed have sufficient experience that is relevant to the scientific and technical information disclosed in this news release and to the type of activity undertaken to qualify as Competent Persons as defined in the JORC Code. Both are employees of the Company and have consented to the inclusion in this announcement of all technical information based on their work the form and context in which it appears.

Cautionary Note Regarding Forward-Looking Statements

This press release contains certain information that may constitute “forward-looking information” within the meaning of applicable Canadian Securities laws and “forward-looking statements” within the meaning of applicable U.S. securities laws (together, “forward-looking statements”). Forward-looking statements are frequently characterized by words such as “plan”, “expect”, “project”, “intend”, “believe”, “anticipate”, “estimate”, “potential”, “possible” and other similar words, or statements that certain events or conditions “may”, “will”, “could”, or “should” occur. Forward-looking statements in this press release include, but are not limited to, statements that commercial production at the stage 1 hard rock plant is expected to be declared in early Q1-2026 and overall gold production at Bomboré is set to increase by 45% to 170,000-185,000oz in 2026.

All such forward-looking statements are based on certain assumptions and analyses made by management in light of their experience and perception of historical trends, current conditions and expected future developments, as well as other factors management and the qualified persons believe are appropriate in the circumstances.

All forward-looking statements are subject to a variety of risks and uncertainties and other factors that could cause actual events or results to differ materially from those projected in the forward-looking statements including, but not limited to, delays caused by pandemics, terrorist or other violent attacks (including cyber security attacks), the failure of parties to contracts to honour contractual commitments, unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; social or labour unrest; changes in commodity prices; unexpected failure or inadequacy of infrastructure, the possibility of unanticipated costs and expenses, accidents and equipment breakdowns, political risk, unanticipated changes in key management personnel and general economic, market or business conditions, the failure of exploration programs, including drilling programs, to deliver anticipated results and the failure of ongoing and uncertainties relating to the availability and costs of financing needed in the future, and other factors described in the Company's most recent annual information form, management discussion and analysis and Section 4 of the ASX Prospectus dated July 11, 2025 filed on SEDAR+. Readers are cautioned not to place undue reliance on forward-looking statements.

Although the forward-looking statements contained in this press release are based upon what management of the Company believes are reasonable assumptions, the Company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this press release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the Company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this press release.



EN
15/12/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Orezone Gold Corp.

 PRESS RELEASE

Orezone Reports First Gold from Bomboré Hard Rock Expansion

Orezone Reports First Gold from Bomboré Hard Rock Expansion VANCOUVER, British Columbia, Dec. 15, 2025 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) (the “Company” or “Orezone”) is pleased to announce that it has completed the first gold pour from the Company’s new 2.5Mtpa hard rock expansion. Patrick Downey, President and CEO stated, "Commissioning of this plant is now complete, with mill throughput averaging 78% of nameplate capacity for the first 5 days of operations, resulting in first gold on December 15. I want to extend my sincere gratitude to...

 PRESS RELEASE

Orezone Intercepts 3.28 g/t Gold Over 26.00m and 5.55 g/t Gold Over 15...

Orezone Intercepts 3.28 g/t Gold Over 26.00m and 5.55 g/t Gold Over 15.00m at P17 Zone in Advance of Hard Rock First Gold VANCOUVER, British Columbia, Dec. 03, 2025 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) (the “Company” or “Orezone”) is pleased to report shallow, high-grade confirmatory grade control drill results from the P17 Zone at its flagship Bomboré Gold Mine. The P17 Zone is a high-grade hard rock deposit outcropping at surface located at the southern end of the Bomboré mining lease. In addition to several phased oxide pits, which have loca...

 PRESS RELEASE

Orezone Gold Reports Third Quarter 2025 Results

Orezone Gold Reports Third Quarter 2025 Results All dollar amounts are in USD unless otherwise indicated and abbreviation “M” means million. VANCOUVER, British Columbia, Nov. 12, 2025 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) (“Orezone” or “Company”) is pleased to report its operational and financial results for the three and nine months ended September 30, 2025. The Company will host a conference call and webcast today at 2:00pm PT / 5:00pm ET (November 13, 9:00am AEDT) to discuss the results. Details to join the conference call and webcast are pr...

 PRESS RELEASE

Orezone Provides Notice of Third Quarter 2025 Results

Orezone Provides Notice of Third Quarter 2025 Results VANCOUVER, British Columbia, Nov. 04, 2025 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) will announce its third quarter 2025 results on Wednesday, November 12, 2025, after TSX market close. The Company will host a conference call and audio webcast to discuss these results on the same day at 2:00 pm Pacific Time / 5:00 pm Eastern Time (Thursday, November 13, 2025, 9:00 am Australian Eastern Daylight Time). Q3-2025 Results Webcast and Conference Call Details Timing: November 12, 2025, 2:00 pm PT / 5...

 PRESS RELEASE

Orezone Reports Q3-2025 Production and Hard Rock Expansion Update

Orezone Reports Q3-2025 Production and Hard Rock Expansion Update VANCOUVER, British Columbia, Oct. 15, 2025 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE | ASX: ORE | OTCQX: ORZCF) (the “Company” or “Orezone”) is pleased to announce its Q3-2025 gold production results and construction progress on its stage 1 hard rock expansion at its Bomboré Gold Mine. All dollar amounts are in USD unless otherwise indicated and abbreviation “M” means million. Q3-2025 Production Results Gold production of 23,371 ouncesGold sales of 20,350 ounces at a realized price of $3,375 per ounce for re...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch