Prosafe SE: Operational and financial update Q2 2020

Prosafe SE: Operational and financial update Q2 2020

Operational

The fleet utilisation rate in the second quarter of 2020 was 6.5 per cent (Q2 2019: 71.6 per cent).



Prosafe refers to the press release from 9 April 2020 regarding discussions with clients about current and upcoming contracts in light of COVID-19 and the oil price collapse. Certain discussions remain ongoing. Please see status and update per vessel below.



The Safe Zephyrus was ready to mobilize from Norway to support EnQuest’s Thistle project, but was instructed by EnQuest on 20 March 2020 not to mobilize. Prosafe has claimed the full contract value, ca. USD 2 million. Thereafter, Safe Zephyrus was scheduled to mobilise to Shell at Shearwater to commence a 110-day contract with a 30-day option in Q2 2020. Prosafe has been informed by Shell that this project will not be performed in 2020 and discussions with the client are ongoing. The vessel was currently laid up at Averøy yard in Norway.



Safe Caledonia was laid up in the UK. The vessel was initially prepared to commence a 162-day contract with a 30-day option for Total at the Elgin complex in the UK sector of the North Sea from mid-April 2020, but Prosafe and Total have agreed to defer this project by one year.



Safe Notos has been operating on a three-year and 222-day contract for Petrobras in Brazil since December 2016. Safe Eurus has been providing safety and maintenance support to Petrobras during a three-year contract since November 2019. On 21 March 2020, client personnel on both vessels were demobilised and the vessels were moved closer to shore. During this period, the vessels were on 95% stand-by day rate. From early April 2020, Prosafe has been requested to agree with a suspension of the contract for a period of up to 120 days during which period no income was recognised, but all logistical services, fuel and catering support will continue to be provided by Petrobras, and any days of suspension will be added to the firm period of the contract. Commercial and payment terms related to the recommencement are subject to ongoing discussions.



Safe Concordia completed the contract for Equinor at the Peregrino FPSO in the Campos Basin offshore Brazil on 11 May 2020 and is presently laid up in Brazil available for charter. The vessel was on full day rate during the operational period in the quarter.



Safe Scandinavia, Safe Boreas and Regalia were idle in the quarter and were laid up in Norway.  Regalia is being marketed for recycling.



Although the impact from Covid-19 on the macro environment has been challenging, the company has successfully implemented proper safety measurements at work places and vessels to protect people and assets, as well as a number of cost-saving initiatives to protect liquidity.



Financial

In light of the commercial discussions with clients as outlined above, there is uncertainty related to the extent to which the order backlog will materialize in 2020, as well as to the final outcome of these negotiations.



Please refer to separate press release from 31 July 2020 regarding the ongoing discussion with lenders about a long-term financial solution for the company.



Prosafe is a leading owner and operator of semi-submersible accommodation vessels. The company is listed on the Oslo Stock Exchange with ticker code PRS. For more information, please refer to



Stavanger, 3 August 2020

Prosafe SE



For further information, please contact:



Jesper K. Andresen, CEO

Phone: /  155



Stig Harry Christiansen, Deputy CEO and CFO

Phone: /  813



This information is subject to the disclosure requirements pursuant to Section 5-12 the Norwegian Securities Trading Act

EN
03/08/2020

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Prosafe

 PRESS RELEASE

Prosafe SE: Invitation to Q4 2025 Results and Webcast on February 26th

Prosafe SE: Invitation to Q4 2025 Results and Webcast on February 26th 12 February 2026 – Prosafe SE will release its fourth quarter 2025 results on 26 February 2026 at 07:00 a.m. CET. The quarterly earnings release and presentation will be available on () and Prosafe's website, (). Reese McNeel, CEO, and Halvdan Kielland, Interim CFO, will present the results at Pareto Securities, located at Dronning Mauds gate 3, 0115 Oslo, on 26 February 2026 at 12:00 CET. This presentation is open to the public and will be live-streamed on Prosafe's website. It will be possible to ask questions by u...

 PRESS RELEASE

Prosafe SE: Operational update – December 2025

Prosafe SE: Operational update – December 2025 21 January 2026 - Fleet utilisation for December 2025 was 100%. In Brazil, Safe Eurus, Safe Notos, and Safe Zephyrus continued to operate at full capacity in December, delivering near 100 % commercial uptime. Safe Caledonia maintained 100% commercial uptime at the Captain Field in the UK. The vessel is on contract to 22 February 2026 after Ithaca Energy exercised the remaining three weeks of options. The vessel has a Letter of Intent (LoI) from Ithaca Energy for 6 months firm and  3 months of options from the second quarter of 2027. Safe Bor...

 PRESS RELEASE

Prosafe SE: Company Presentation

Prosafe SE: Company Presentation Oslo, 13 January 2026: Prosafe SE ("Prosafe" or the "Company") has today published a company presentation in connection with a non-deal roadshow in January. The presentation is attached and will also be made available on the Company's webside . For further information, please contact: Reese McNeel, CEO Phone:   This information is subject to the disclosure requirements pursuant to Section 5-12 the Norwegian Securities Trading Act Attachment

 PRESS RELEASE

Prosafe SE: Safe Caledonia contract further extended at Captain

Prosafe SE: Safe Caledonia contract further extended at Captain 8 January 2026, Oslo - Ithaca Energy (UK) Limited (‘Ithaca’) has exercised all three (3) remaining weeks of options for the Safe Caledonia to continue providing accommodation support at the Captain field in the UK sector of the North Sea through to 22nd February 2026. Total value of this contract extension is approximately USD 2.73 million. Prosafe is a leading owner and operator of semi-submersible accommodation vessels. The company is listed on the Oslo Stock Exchange with ticker code PRS. For more information, please refer...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch