CALGARY, Alberta, Feb. 01, 2023 (GLOBE NEWSWIRE) -- News Release – TC Energy Corporation (TSX, NYSE: TRP) (TC Energy or the Company) today announced updated cost estimates for the Coastal GasLink Project (the Project). The Project continues to face material cost pressures that include challenging conditions in the Western Canadian labour market; shortages of skilled labour; impacts of contractor underperformance and disputes; as well as other unexpected events like drought conditions and erosion and sediment control challenges.

A comprehensive cost and schedule risk analysis (CSRA) was conducted to assess current market conditions and potential risks and uncertainties facing the remaining project scope. As a result of the CSRA, TC Energy’s estimate of the costs to complete the Project has increased to approximately $14.5 billion. This estimate excludes potential cost recoveries and incorporates contingencies for certain factors that may be outside of the Company’s control such as labour conditions; contractor performance; and weather-related events.

TC Energy expects to fund the incremental revised project costs and is actively pursuing cost mitigants and recoveries that may partially offset a portion of these costs, some of which may not be conclusively determined until after the Project is in service. Coastal GasLink is working closely with its prime contractors on implementing productivity improvement strategies targeting mechanical completion by year-end 2023, with commissioning and clean-up work continuing into 2024 and 2025. The CSRA review also considered the potential impact of an extension of construction well into 2024. In that event, costs would increase further by up to $1.2 billion. Due to the increase in the expected cost of the Project and the additional funding required, TC Energy will recognize an impairment to its equity investment in Coastal GasLink LP in its fourth quarter 2022 financial results.

The Coastal GasLink Project continues to make significant progress having reached approximately 83 per cent overall completion. The entire route has been cleared, grading is more than 94 per cent complete and over 485 km of the approximately 670 km pipeline has been backfilled with restoration activities underway in many areas. The Wilde Lake Compressor Facility has commenced commissioning work with the introduction of natural gas expected in March, representing another significant milestone in reaching our targeted mechanical completion later this year. Once complete, Coastal GasLink will be Canada’s first direct link for LNG deliveries that will further support displacing 60 to 90 million tonnes of CO2 emissions annually, an important step along the energy transition.

TC Energy’s overall 2023 capital expenditure outlook has been revised to approximately $11.5 to $12.0 billion, reflecting the deferral of certain project spending, expected cost-saving initiatives and incremental funding requirements associated with Coastal GasLink.

“We are disappointed with the increase in the Coastal GasLink Project costs. We continue to be laser-focused on safely completing this critical piece of energy infrastructure at the lowest possible cost, which will enable Canada’s first direct path for LNG exports,” said TC Energy President and CEO François Poirier. “The Project will provide substantive benefits for Indigenous and local communities across the Project route, our customers, the Western Canadian Sedimentary Basin, as well as playing a vital role in enabling global energy security and emissions reduction contributing to global climate goals,” added Poirier.

The Company’s resilient portfolio of high-quality, utility-like assets continues to deliver consistent and sustainable cash flow growth. We remain committed to growing our dividend at an annual rate of three to five per cent and accelerating our deleveraging target from 2026.

As previously announced, we are advancing a $5+ billion asset divestiture program this year. We anticipate a combination of strong market interest and compelling valuations will support upsizing the program to fully fund our industry-leading secured capital program and achieve our deleveraging target. We maintain our intent to cease the discounted Dividend Reinvestment Plan following the dividend declarations for the quarter ending June 30, 2023.  

“Our strategic priorities for 2023 remain unchanged. Our focus is on safe project execution and operational excellence, strengthening our balance sheet and financial flexibility, enhancing returns on our assets, and advancing our decarbonization and low-carbon opportunities,” said Poirier.

About TC Energy

We’re a team of 7,000+ energy problem solvers working to move, generate and store the energy North America relies on. Today, we’re taking action to make that energy more sustainable and more secure. We’re innovating and modernizing to reduce emissions from our business. And, we’re delivering new energy solutions – from natural gas and renewables to carbon capture and hydrogen – to help other businesses and industries decarbonize too. Along the way, we invest in communities and partner with our neighbours, customers and governments to build the energy system of the future.

TC Energy’s common shares trade on the Toronto (TSX) and New York (NYSE) stock exchanges under the symbol TRP. To learn more, visit us at .

FORWARD-LOOKING INFORMATION

This release contains certain information that is forward-looking and is subject to important risks and uncertainties (such statements are usually accompanied by words such as “anticipate”, “expect”, “believe”, “may”, “will”, “should”, “estimate”, “intend” or other similar words). Forward-looking statements in this document may include, but are not limited to, statements regarding the Company’s expected schedules and costs of planned projects, expected cost recoveries, expected cash flows, expected future financing options available, expectations regarding the size, timing and outcome of the asset divestiture program, expected dividend growth, expected duration of discounted DRP issuance from treasury, and expected access to and cost of capital. Key assumptions on which our forward-looking information is based include, but are not limited to, assumptions about the realization of expected benefits from divestitures, anticipated construction costs, schedules and completion dates, access to capital markets, expected industry, market and economic conditions, inflation rates, foreign exchange and interest rates. Forward-looking statements in this document are intended to provide TC Energy security holders and potential investors with information regarding TC Energy and its subsidiaries, including management's assessment of TC Energy’s and its subsidiaries’ future plans and financial outlook. All forward-looking statements reflect TC Energy’s beliefs and assumptions based on information available at the time the statements were made and as such are not guarantees of future performance. As actual results could vary significantly from the forward-looking information, you should not put undue reliance on forward-looking information and should not use future-oriented information or financial outlooks for anything other than their intended purpose. We do not update our forward-looking information due to new information or future events, unless we are required to by law. For additional information on the assumptions made, and the risks and uncertainties which could cause actual results to differ from the anticipated results, refer to the most recent Quarterly Report to Shareholders and Annual Report filed under TC Energy’s profile on SEDAR at and with the U.S. Securities and Exchange Commission at .

-30-

Media Inquiries:

Stone Grissom / Suzanne Wilton



403-920-7859 or 800-608-7859

Investor & Analyst Inquiries:

Gavin Wylie / Hunter Mau



403-920-7911 or 800-361-6522

PDF available: 



EN
01/02/2023

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on TC Energy Corporation

 PRESS RELEASE

TC Energy declares quarterly dividends

TC Energy declares quarterly dividends CALGARY, Alberta, July 31, 2025 (GLOBE NEWSWIRE) -- News Release – TC Energy Corporation (TSX, NYSE: TRP) (TC Energy or the Company) announced that its Board of Directors (Board) has declared a quarterly dividend of $0.85 per common share for the quarter ending Sept. 30, 2025, on the Company’s outstanding common shares. The common share dividend is payable on Oct. 31, 2025, to shareholders of record at the close of business on Sept. 29, 2025. The Board also declared quarterly dividends on the outstanding Cumulative First Preferred Shares as fol...

 PRESS RELEASE

TC Energy reports strong second quarter 2025 operating and financial r...

TC Energy reports strong second quarter 2025 operating and financial results Solid execution and asset performance support higher 2025 financial outlook Market fundamentals drive customer demand for incremental capacity projects CALGARY, Alberta, July 31, 2025 (GLOBE NEWSWIRE) -- TC Energy Corporation (TSX, NYSE: TRP) (TC Energy or the Company) released its second quarter results today. François Poirier, TC Energy’s President and Chief Executive Officer commented, "Our commitment to safety and operational excellence continues to drive strong reliability, availability and financial perf...

 PRESS RELEASE

TC Energy to issue second quarter 2025 results on July 31

TC Energy to issue second quarter 2025 results on July 31 CALGARY, Alberta, July 10, 2025 (GLOBE NEWSWIRE) -- News Release – TC Energy Corporation (TSX, NYSE: TRP) (TC Energy or the Company) will hold a teleconference and webcast on Thursday, July 31, 2025, to discuss its second quarter financial results. François Poirier, TC Energy President and Chief Executive Officer, Sean O’Donnell, Executive Vice-President and Chief Financial Officer and other members of the executive leadership team will discuss the financial results and Company developments at 6:30 a.m. MT / 8:30 a.m. ET. Members...

 PRESS RELEASE

TC Energy commences collection of tolls on Southeast Gateway pipeline

TC Energy commences collection of tolls on Southeast Gateway pipeline Final project cost is approximately US$3.9 billion, 13 per cent under original cost estimateSupplies affordable, reliable and sustainable natural gas to fuel Mexico’s economic growth CALGARY, Alberta, June 27, 2025 (GLOBE NEWSWIRE) -- News Release – TC Energy Corporation (TSX, NYSE: TRP) (TC Energy or the Company) today announced that it has commenced the collection of tolls from the Comisión Federal de Electricidad (CFE) for the Southeast Gateway pipeline and has been paid by the CFE for the month of May, on time in a...

 PRESS RELEASE

TC Energy provides results of Series 3 and Series 4 conversion electio...

TC Energy provides results of Series 3 and Series 4 conversion elections CALGARY, Alberta, June 23, 2025 (GLOBE NEWSWIRE) -- News Release – TC Energy Corporation (TSX:TRP) (NYSE:TRP) (TC Energy or the Company) today announced that 104,778 of its 9,997,177 fixed rate Cumulative Redeemable First Preferred Shares, Series 3 (Series 3 Shares) have been elected for conversion on June 30, 2025, on a one-for-one basis, into floating rate Cumulative Redeemable First Preferred Shares, Series 4 (Series 4 Shares); and 1,822,829 of its 4,002,823 Series 4 Shares have been elected for conversion, on a ...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch