Troilus Surpasses 85% Completion of Basic Engineering With BBA; Project on Schedule and Advancing Towards Construction Readiness

Troilus Surpasses 85% Completion of Basic Engineering With BBA; Project on Schedule and Advancing Towards Construction Readiness

MONTREAL, Oct. 15, 2025 (GLOBE NEWSWIRE) -- Troilus Gold Corp. (TSX: TLG; OTCQX: CHXMF; FSE: CM5R) (“Troilus” or the “Company”) is pleased to report continued progress on the basic and detailed engineering of its copper-gold Troilus Project (the “Project”) led by engineering partner BBA Inc. (“BBA”) based in Montreal, Quebec.

Basic engineering of the Project has now surpassed 85% completion, marking significant progress since the last engineering update provided on . Following the completion of trade-off studies and process flowsheet definition earlier this year, the focus shifted to cost estimation, procurement, and execution planning. Major deliverables - including capital cost estimates, vendor evaluations, and project execution plans - are now well advanced, supporting a targeted construction decision in 2026.

Highlights of Engineering Progress to Date:

Procurement and Technical Evaluations

  • All Requests for Quotations (“RFQs”) have been issued to the market, supporting the transition towards execution planning as the Project advances to cost definition and construction readiness.
  • Technical and commercial assessments of major equipment and construction packages are nearing completion, with firm bids now received for key items, supporting vendor selection and refinement of capital cost estimates.
  • Comprehensive project execution plans have been developed, outlining the framework for project delivery, including contracting strategy and construction sequencing.



Construction Readiness and Commissioning Preparation 

  • Layouts of construction facilities have been developed to optimize logistics and cost planning.
  • Review of 3D models for the Project’s process plant, dry comminution circuit, and site infrastructure is over 30% complete.
  • Commissioning systems have been identified and sequenced to ensure a structured transition from construction to operations.



Justin Reid, CEO of Troilus, commented “We continue to make disciplined and measurable progress thanks to the expertise of our in-house team and BBA Consultants. Surpassing 85% completion of basic engineering marks an important step towards construction readiness and reflects the steady de-risking of the Troilus Project. With all RFQs issued and execution plans in place, we continue to advance and refine definitions around scope, costs and delivery strategy. We remain on track to complete basic engineering before year-end, positioning Troilus to advance seamlessly into detailed execution and towards a 2026 construction decision. BBA’s deep knowledge of the Troilus site and our collaborative approach continue to be key drivers of this progress.”



Figure 1. Troilus Project - 3D Model of Processing Circuit

About BBA Consultants

BBA has been providing a wide range of consulting engineering services for over 45 years. Strategic advisory, environmental, engineering and field experts team up to quickly and accurately pinpoint the needs of industrial and institutional clients. Known for its innovative, sustainable and reliable solutions, the firm’s expertise is recognized in the energy and natural resources industry. BBA has over 20 offices across Canada and abroad (Chile and the United States), offering clients local support and increased field presence. 

About Troilus Gold Corp.

Troilus Gold Corp. is a Canadian development-stage mining company focused on the systematic advancement of the former gold and copper Troilus Mine towards production. Troilus is located in the tier-one mining jurisdiction of Quebec, Canada, where it holds a large land position of 435 km² in the Frôtet-Evans Greenstone Belt. A Feasibility Study completed in May 2024 supports a large-scale 22-year, 50ktpd open-pit mining operation, positioning it as a cornerstone project in North America.

For more information:

Caroline Arsenault

VP Corporate Communications

+1 (647) 276-0050

 

Cautionary Note Regarding Forward-Looking Statements and Information

This press release contains “forward-looking statements” within the meaning of applicable Canadian securities legislation. Forward-looking statements include, but are not limited to, statements regarding, the impact of the BBA mandate and progress to completion on the Company and the likelihood that the mandate will progress on the timeline and budget projected and result in a construction decision on the timeline projected or at all. Generally, forward-looking statements can be identified by the use of forward-looking terminology such as “plans”, “expects” or “does not expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “continue”, “anticipates” or “does not anticipate”, or “believes”, or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “will”, “might” or “will be taken”, “occur” or “be achieved”. Forward-looking statements are made based upon certain assumptions and other important facts that, if untrue, could cause the actual results, performances or achievements of Troilus to be materially different from future results, performances or achievements expressed or implied by such statements. Such statements and information are based on numerous assumptions regarding present and future business strategies and the environment in which Troilus will operate in the future. Certain important factors that could cause actual results, performances or achievements to differ materially from those in the forward-looking statements include, amongst others, currency fluctuations, the global economic climate, dilution, share price volatility and competition. Forward-looking statements are subject to known and unknown risks, uncertainties and other important factors that may cause the actual results, level of activity, performance or achievements of Troilus to be materially different from those expressed or implied by such forward-looking statements, including but not limited to: there being no assurance Troilus will meet all conditions for further draw downs under the Loan; uncertainties with respect to additional warrants being exercised; there being no assurance that the exploration program or programs of the Company will result in expanded mineral resources; risks and uncertainties inherent to mineral resource and reserve estimates; the high degree of uncertainties inherent to feasibility studies and other mining and economic studies which are based to a significant extent on various assumptions; variations in gold prices and other metals, exchange rate fluctuations; variations in cost of supplies and labour; receipt of necessary approvals; availability of financing for project development; uncertainties and risks with respect to developing mining projects; general business, economic, competitive, political and social uncertainties; future gold and other metal prices; accidents, labour disputes and shortages; environmental and other risks of the mining industry, including without limitation, risks and uncertainties discussed in the Company’s latest Annual Information Form, its technical reports and other continuous disclosure documents of the Company available under the Company’s profile at Although Troilus has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Troilus does not undertake to update any forward-looking statements, except in accordance with applicable securities laws.

A photo accompanying this announcement is available at



EN
15/10/2025

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Troilus Gold

 PRESS RELEASE

Troilus Provides Overview of Its 2025 Exploration Program and Initial ...

Troilus Provides Overview of Its 2025 Exploration Program and Initial Results Confirming Mineral Resource Upside Near Pit and Across Property MONTREAL, Jan. 22, 2026 (GLOBE NEWSWIRE) -- Troilus Mining Corp. (formerly Troilus Gold Corp.) (“Troilus” or the “Company”; TSX: TLG, OTCQX: CHXMF; FSE: CM5) is pleased to provide an overview of its completed 2025 exploration program at the Troilus copper-gold Project (the “Project”) in north-central Québec, in addition to providing initial results that demonstrate near-mine growth potential and broader upside across the Company’s 435 km2 land packa...

 PRESS RELEASE

Troilus présente un aperçu de son programme d’exploration 2025 et des ...

Troilus présente un aperçu de son programme d’exploration 2025 et des résultats initiaux confirmant un potentiel d’augmentation des ressources à proximité des fosses et à l’échelle de la propriété MONTREAL, 22 janv. 2026 (GLOBE NEWSWIRE) -- Corporation Minière Troilus (TSX : TLG; OTCQX : CHXMF; FSE : CM5) (« Troilus » ou la « Société ») a le plaisir de présenter un aperçu de son programme d’exploration complété en 2025 sur le projet cuivre-or Troilus (le « Projet »), situé dans le centre-nord du Québec, ainsi que des résultats initiaux démontrant un potentiel de croissance des ressources ...

 PRESS RELEASE

Troilus Delivers on Key Development Milestones in 2025 and Enters a Pi...

Troilus Delivers on Key Development Milestones in 2025 and Enters a Pivotal Transition Year in 2026 MONTREAL, Jan. 08, 2026 (GLOBE NEWSWIRE) -- Troilus Mining Corp. (TSX: TLG; OTCQX: CHXMF; FRA: CM5) (“Troilus” or the “Company”), is pleased to provide a review of its key accomplishments in 2025 and an outlook for 2026, as the Company advances its flagship Troilus copper-gold project (the “Project”) through critical development milestones and positions it for the next phase of execution, in this open letter to shareholders from Chief Executive Officer, Justin Reid. To our valued shareholde...

 PRESS RELEASE

Troilus franchit des étapes clés en 2025 et aborde une année de transi...

Troilus franchit des étapes clés en 2025 et aborde une année de transition déterminante en 2026 MONTRÉAL, 08 janv. 2026 (GLOBE NEWSWIRE) -- Corporation minière Troilus (TSX : TLG; OTCQX : CHXMF; FSE : CM5) (« Troilus » ou la « Société ») a le plaisir de présenter un bilan de ses principales réalisations en 2025 ainsi qu’une perspective pour 2026, alors que la Société fait progresser son projet phare de cuivre-or Troilus (le « Projet ») à travers des étapes clés de développement et le positionne pour la prochaine phase d’exécution, dans cette lettre ouverte aux actionnaires du chef de la d...

 PRESS RELEASE

Troilus Announces Completion of Name Change to Troilus Mining Corp. an...

Troilus Announces Completion of Name Change to Troilus Mining Corp. and Annual & Special Meeting Results MONTRÉAL, Dec. 05, 2025 (GLOBE NEWSWIRE) -- Troilus Mining Corp., formerly Troilus Gold Corp., (“Troilus” or the “Company”, TSX: TLG, OTCQX: CHXMF; FSE: CM5R) is pleased to announce that it has completed its name change from Troilus Gold Corp. to Troilus Mining Corp. and « Corporation minière Troilus » in French, following receipt of shareholder approval at its Annual and Special Meeting of Shareholders held on December 4, 2025 (the “Meeting”). The name change is intended to better re...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch