VGM. MINERA ALAMOS

Minera Alamos Announces Stock Option Grant with Vesting Tied to Production Milestones

Toronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - March 18, 2021) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") The Board of Directors of Minera Alamos has approved the issuance of up to 7,250,000 options to Management, Directors, Employees and Consultants pursuant to its stock option plan. The options are exercisable at a price of $0.72 and expire in five years and are subject to certain vesting provisions based on attaining specific production milestones.

"It is approaching two years since the Company has provided a group wide option grant. These options represent a way of rewarding the exceptional efforts of the team in executing on our development strategy during difficult circumstances," stated Doug Ramshaw, President. "Notwithstanding the past value creation, we felt it important to tie vesting of the options to future execution. As such the team will need to continue to deliver for its shareholders by meeting certain production related milestones for the options to fully vest."

For Further Information Please Contact:

Minera Alamos Inc.
Doug Ramshaw, President
Tel: 604-600-4423
Email:  
Website: 

Victoria Vargas de Szarzynski, VP Investor Relations
Tel: 289-242-3599
Email: 

About Minera Alamos Inc.

Minera Alamos is a gold development company poised to join the ranks of gold producers in 2021. The Company has a portfolio of high-quality Mexican assets, including the 100%-owned Santana open-pit, heap-leach development project in Sonora that is currently under construction, and which is expected to have its first gold production in the first half of 2021. The newly acquired 100%-owned Cerro de Oro oxide gold project in northern Zacatecas that has considerable past drilling and metallurgical work completed and could enter the permitting process rapidly. The La Fortuna open pit gold project in Durango (100%-owned) has an extremely robust and positive preliminary economic assessment (PEA) completed and the main Federal permits in hand. Minera Alamos is built around its operating team that together brought 3 mines into production in Mexico over the last 13 years.

The Company's strategy is to develop very low capex assets while expanding the projects' resources and continuing to pursue complementary strategic acquisitions.

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

To view the source version of this press release, please visit

EN
18/03/2021

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on MINERA ALAMOS

 PRESS RELEASE

Minera Alamos Provides Santana Project Operations Update

Gold Leach Pad and Plant Nears CommissioningToronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - June 21, 2021) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to provide an update on the start-up of mining operations at the Santana gold mine, Sonora, Mexico.All construction has now been completed with the full leach pad now lined and available for stacking (see photo 1). First loading of mined material from the Nicho Norte pit commenced earlier this month (see photo 4) in preparation for the commissioning of leach operations around the end of th...

 PRESS RELEASE

Minera Alamos First Blast Completed at Santana Gold Mine as Mining Ope...

Toronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - May 20, 2021) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to announce that this week, the Company successfully executed the first planned production blasts at the Nicho Norte pit at the Santana gold mine in Sonora, Mexico. With this inaugural blast successfully completed drilling has already begun on subsequent blasting as the Nicho Norte pit is opened up.Photo 1 - Inaugural mining blast at the Nicho Norte zone - Bench 905To view an enhanced version of Photo 1, please visit:The initial blasti...

 PRESS RELEASE

Minera Alamos Selects Mining Contractor in Preparation for Start of Mi...

Toronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - March 31, 2021) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to announce the selection of TRIGUSA as mining contractor for the Santana gold mine, Sonora, Mexico. Trigusa's mining experience includes open pit mining, crushing, tailings dam construction and heap leach pads and ponds at projects in multiple states including Sonora."Our Mexican operations team has a long and positive history with Trigusa dating back to their involvement with the construction and operations at the El Castillo mine ...

 PRESS RELEASE

Minera Alamos Announces Stock Option Grant with Vesting Tied to Produc...

Toronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - March 18, 2021) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") The Board of Directors of Minera Alamos has approved the issuance of up to 7,250,000 options to Management, Directors, Employees and Consultants pursuant to its stock option plan. The options are exercisable at a price of $0.72 and expire in five years and are subject to certain vesting provisions based on attaining specific production milestones."It is approaching two years since the Company has provided a group wide option grant. These option...

 PRESS RELEASE

Minera Alamos Provides Santana Mine Construction Update

Toronto, Ontario and Vancouver, British Columbia--(Newsfile Corp. - January 27, 2021) - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to provide a construction update detailing progress at the Santana gold project, Sonora, Mexico, as the Company advances towards the commencement of mining.Leach solution ponds (barren and pregnant) are now fully lined and ready for operations (see Photo 1 below).The plant foundations have been completed and all previously fabricated plant structures (including carbon columns for gold recovery) have been delivered to site in prepar...