Golar Power completes 96 hour reliability test at 1.5GW Sergipe Power Plant

Golar Power completes 96 hour reliability test at 1.5GW Sergipe Power Plant

Golar Power Limited (“Golar Power”) has successfully completed today the final operational test at the 1.5GW Sergipe Power Plant.

The test involves supplying the maximum load of the plant (1.5 GW) to the National Interconnected System (SIN) for a period of 96 continuous hours. The test is the final requirement of the National System Operator (ONS) in order to start commercial operations under the 25-year power purchase agreements.

For the test, the three gas turbines, the steam turbine and three heat recovery boilers operated in a combined cycle and delivered a volume in excess of 1.5GW, for 96 continuous hours. The test was successfully completed this morning at 03:00am (GMT).

Hamilton, Bermuda

March 17, 2020

Enquiries:

Golar Management Limited: 00

Eduardo Maranhao

Stuart Buchanan

EN
17/03/2020

Underlying

To request access to management, click here to engage with our
partner Phoenix-IR's CorporateAccessNetwork.com

Reports on Golar LNG Limited

 PRESS RELEASE

Golar LNG Limited Q1 2025 results presentation – Date change

Golar LNG Limited Q1 2025 results presentation – Date change Due to a newly scheduled official State visit to the GTA Hub in Mauritania and Senegal, which will be attended by senior management, Golar’s Q1 2025 results will be released before the NASDAQ opens on Tuesday, May 27, 2025. In connection with this the webcast presentation will be held at 1:00 P.M (London Time) on Tuesday May 27, 2025. The presentation will be available to download from the Investor Relations section at We recommend that participants join the conference call via the listen-only live webcast link provided. Sell-si...

ABGSC Shipping & Transport Research ... (+3)
  • ABGSC Shipping & Transport Research
  • Martin Mauseth
  • Petter Haugen
 PRESS RELEASE

Golar entered into 20-year agreements for 5.95mtpa nameplate capacity ...

Golar entered into 20-year agreements for 5.95mtpa nameplate capacity in Argentina – one of the world’s largest FLNG development projects. Golar LNG Limited (“GLNG”, “Golar” or “the Company”) is pleased to announce the Final Investment Decision (“FID”) and fulfilment of all conditions precedent for the 20-year re-deployment charter of the FLNG Hilli Episeyo (“FLNG Hilli” or “Hilli”), first announced on July 5, 2024. The vessel will be chartered to Southern Energy S.A. (“SESA”), offshore Argentina. In addition, Golar and SESA have signed definitive agreements for a 20-year charter for the M...

 PRESS RELEASE

Golar LNG Limited – Q1 2025 results presentation

Golar LNG Limited – Q1 2025 results presentation Golar LNG's 1st Quarter 2025 results will be released before the NASDAQ opens on Wednesday, May 21, 2025. In connection with this, a webcast presentation will be held at 1:00 P.M (London Time) on Wednesday May 21, 2025. The presentation will be available to download from the Investor Relations section at We recommend that participants join the conference call via the listen-only live webcast link provided. Sell-side analysts interested in raising a question during the Q&A session that will immediately follow the presentation should access t...

Jørgen Lian
  • Jørgen Lian

Golar LNG (Buy, TP: USD48.00) - Upside potential building

We believe focus for investors will be the potential contracts in Argentina rather than the Q1 report. Recent developments look to have left Golar LNG in pole position for two FLNGs for ~6mtpa Argentine LNG exports, and we would expect more visibility once the FID for Hilli is in place in Q2e. Moreover, we believe the project pipeline could allow for further announcements in due course as the company maintains an option for FLNG #4 at the shipyard. Hence, we find the risk/reward has improved des...

ResearchPool Subscriptions

Get the most out of your insights

Get in touch